标识号,名称,工期,开始时间,完成时间,前置任务,大纲级别,备注
1,Designreviewofdrawingandlocatingofconstruction图纸设计审查及施工定位,48.d,2007/6/128:00,2007/7/2917:00,,1,
2,Reviewofdrawing(phase1)图纸审查(一期),15.d,2007/6/128:00,2007/6/2617:00,,2,
3,locate&layout定位放线,1.d,2007/6/148:00,2007/6/1417:00,,2,
4,Planningpermission规划许可证,25.d,2007/6/258:00,2007/7/1917:00,,2,
5,Builder'slicence施工许可证,30.d,2007/6/308:00,2007/7/2917:00,,2,
6,Reviewofdrawing(Phase2)图纸审查(二期),10.d,2007/7/158:00,2007/7/2417:00,,2,
7,Workshopconstruction厂房工程施工,176.d,2007/6/208:00,2007/12/1217:00,,1,
8,Workshop'ssection1construction厂房第一部分施工,146.d,2007/6/208:00,2007/11/1217:00,,2,
9,Compactionworkforsection1厂房第一部分强夯,7.d,2007/6/228:00,2007/6/2817:00,,3,
10,Excavatingearthforworkshop'ssection1厂房第一部分土方开挖,12.d,2007/6/258:00,2007/7/617:00,,3,
11,Foundationtrenchcleaningforworkshop'ssection1厂房第一部分基槽清理,2.d,2007/7/78:00,2007/7/817:00,10,3,
12,Checkandacceptthefoundationtrenchforworkshop'ssection1厂房第一部分基槽验收,1.d,2007/7/98:00,2007/7/917:00,11,3,
13,Foundationconstructionforworkshop'ssection1厂房第一部分基础施工,10.d,2007/7/108:00,2007/7/1917:00,12,3,
14,Lightningprotection&groundingconstructionforworkshop'ssection1(testingground-resistance)厂房第一部分避雷接地施工(接地电阻测试),10.d,2007/7/108:00,2007/7/1917:00,,3,
15,Checkandacceptthefoundationforworkshop'ssection1厂房第一部分基础验收,1.d,2007/7/208:00,2007/7/2017:00,14,3,
16,tampedbackfilloffoundationforworkshop'ssection1厂房第一部分基础夯填,10.d,2007/7/218:00,2007/7/3017:00,15,3,
17,"Undergroundpipenetworkinstallationforworkshop'ssection1(irrigationtest,pressuretest)厂房第一部分地下管网安装(灌水试验、压力试验)",10.d,2007/7/58:00,2007/7/1417:00,,3,
18,Steelstructuremakingforworkshop'ssection1厂房第一部分钢结构制作,40.d,2007/6/208:00,2007/7/2917:00,,3,
19,Steelstructureframeinstallationforworkshop'ssection1厂房第一部分钢结构骨架安装,20.d,2007/7/318:00,2007/8/1917:00,16,3,
20,Checkandacceptthesteelstructure'smainbodyforworkshop'ssection1厂房第一部分钢结构主体验收,1.d,2007/8/208:00,2007/8/2017:00,19,3,
21,Roofboardingandwallplateinstallationforworkshop'ssection1厂房第一部分屋面板、墙板安装,25.d,2007/8/218:00,2007/9/1417:00,20,3,
22,Interiorpartitionconstructionforworkshop'ssection1厂房第一部分内部隔墙施工,20.d,2007/8/218:00,2007/9/917:00,,3,
23,Internalandexternalwindowsanddoorsinstallationforwokshop'ssection1厂房第一部分内外门窗安装,25.d,2007/8/228:00,2007/9/1517:00,,3,
24,Internaldécorationconstructionforworkshop'ssection1厂房第一部分内装修施工,20.d,2007/9/158:00,2007/10/417:00,21,3,
25,"Stormwater/watersupplyandseweragesysteminstallationforworkshop'ssection1(irrigationtest,pressuretest)厂房第一部分雨水/给排水系统安装(灌水试验、压力试验)",41.d,2007/8/68:00,2007/9/1517:00,,3,
26,Laydowntrayandcableforworkshop'ssection1(commissioningwithpower)厂房第一部分桥架、电缆敷设(通电试运行),96.d,2007/8/68:00,2007/11/917:00,,3,
27,Hydrant/sprinklingsysteminstallationforworkshop'ssection1(pressuretest)厂房第一部分消防栓/喷淋系统安装(压力试验),61.d,2007/9/108:00,2007/11/917:00,,3,
28,Heatingsysteminstallationforworkshop'ssection1(pressuretest)厂房第一部分暖气系统安装(压力试验),59.d,2007/8/168:00,2007/10/1317:00,,3,
29,Dustcollection/compressedair/naturalgas/coolingwater.etcsystemmainductinstallationforworkshop'ssection1厂房第一部分除尘/压缩空气/燃气/冷却水等系统主(风道)管道安装,86.d,2007/8/168:00,2007/11/917:00,,3,
30,Firealarmdetectionforworkshop'ssection1(linkedcommissioning)厂房第一部分消防报警检测装置(联动试车),67.d,2007/9/48:00,2007/11/917:00,,3,
31,Lightingfixtureinstallationforworkshop'ssection1(commissioningwithpower)厂房第一部分照明灯具等系统安装(通电试运行),65.d,2007/9/68:00,2007/11/917:00,,3,
32,IT/tel/CCTV/assesscontrolinstallationandcommissioningforworkshop'ssection1厂房第一部分网络/电话/监控门禁元件安装和试运行,30.d,2007/10/88:00,2007/11/617:00,,3,
33,Fabricgroundconstructionforworkshop'ssection1厂房第一部分地面施工,20.d,2007/7/258:00,2007/8/1317:00,,3,
34,Groundslabconstructionforworkshop'ssection1厂房第一部分地面面层施工,10.d,2007/10/68:00,2007/10/1517:00,,3,
35,Finalcleanupforworkshop'ssection1厂房第一部分竣工清理,5.d,2007/11/78:00,2007/11/1117:00,32,3,
36,Checkandacceptworkshop'ssection1byemployer厂房第一部分业主验收,1.d,2007/11/128:00,2007/11/1217:00,35,3,
37,Workshop'ssection2construction厂房第二部分施工,146.d,2007/6/208:00,2007/11/1217:00,,2,
38,Excavatingearthforworshop'ssection2厂房第二部分土方开挖,15.d,2007/6/208:00,2007/7/417:00,,3,
39,Foundationtrenchcleaningforworkshop'ssection2厂房第二部分基槽清理,5.d,2007/7/58:00,2007/7/917:00,38,3,
40,Checkandacceptthefoundationtrenchforworkshop'ssection2厂房第二部分基槽验收,1.d,2007/7/108:00,2007/7/1017:00,39,3,
41,Foundationconstructionforworkshop'ssection2厂房第二部分基础施工,15.d,2007/7/118:00,2007/7/2517:00,40,3,
42,Lightningprotection&groundingconstructionforworkshop'ssection2(testingground-resistance)厂房第二部分避雷接地施工(接地电阻测试),13.d,2007/7/118:00,2007/7/2317:00,,3,
43,Checkandacceptthefoundationforworkshop'ssection2厂房第二部分基础验收,1.d,2007/7/268:00,2007/7/2617:00,41,3,
44,tampedbackfilloffoundationforworkshop'ssection2厂房第二部分基础夯填,8.d,2007/7/278:00,2007/8/317:00,43,3,
45,"Undergroundpipenetworkinstallationforworkshop'ssection2(irrigationtest,pressuretest)厂房第二部分地下管网安装(灌水试验、压力试验)",10.d,2007/7/278:00,2007/8/517:00,,3,
46,Steelstructuremakingforworkshop'ssection2厂房第二部分钢结构制作,40.d,2007/6/308:00,2007/8/817:00,,3,
47,Steelstructureframeinstallationforworkshop'ssection2厂房第二部分钢结构骨架安装,20.d,2007/8/48:00,2007/8/2317:00,44,3,
48,Checkandacceptthesteelstructure'smainbodyforworkshop'ssection2厂房第二部分钢结构主体验收,1.d,2007/8/248:00,2007/8/2417:00,47,3,
49,Roofboardingandwallplateinstallationforworkshop'ssection2厂房第二部分屋面板、墙板安装,25.d,2007/8/258:00,2007/9/1817:00,48,3,
50,Interiorpartitionconstructionforworkshop'ssection2厂房第二部分内部隔墙施工,20.d,2007/8/268:00,2007/9/1417:00,,3,
51,Internalandexternalwindowsanddoorsintallationforworkshop'ssection2厂房第二部分内外门窗安装,25.d,2007/8/288:00,2007/9/2117:00,,3,
52,Internaldécorationconstructionforworkshop'ssection2厂房第二部分内装修施工,20.d,2007/9/198:00,2007/10/817:00,49,3,
53,"Stormwater/watersupplyandseweragesysteminstallationforworkshop'ssection2(irrigationtest,pressuretest)厂房第二部分雨水/给排水系统安装(灌水试验、压力试验)",40.d,2007/8/168:00,2007/9/2417:00,,3,
54,Laydowntrayandcableforworkshop'ssection2(commissioningwithpower)厂房第二部分桥架、电缆敷设(通电试运行),85.d,2007/8/138:00,2007/11/517:00,,3,
55,Hydrant/sprinklingsysteminstallationforworkshop'ssection2(pressuretest)厂房第二部分消防栓/喷淋系统安装(压力试验),60.d,2007/9/78:00,2007/11/517:00,,3,
56,Heatingsysteminstallationforworkshop'ssection2(pressuretest)厂房第二部分暖气系统安装(压力试验),74.d,2007/8/248:00,2007/11/517:00,,3,
57,Dustcollection/compressedair/naturalgas/coolingwater.etcsystemmainductinstallationforworkshop'ssection2厂房第二部分除尘/压缩空气/燃气/冷却水等系统主(风道)管道安装,91.d,2007/8/78:00,2007/11/517:00,,3,
58,Firealarmdetectionforworkshop'ssection2(linkedcommissioning)厂房第二部分消防报警检测装置(联动试车),58.d,2007/9/98:00,2007/11/517:00,,3,
59,Lightingfixtureinstallationforworkshop'ssection2(commissioningwithpower)厂房第二部分照明灯具等系统安装(通电试运行),60.d,2007/9/78:00,2007/11/517:00,,3,
60,IT/tel/CCTV/assesscontrolinstallationandcommissioningforworkshop'ssection2厂房第二部分网络/电话/监控门禁元件安装和试运行,24.d,2007/10/48:00,2007/10/2717:00,,3,
61,Fabricgroundconstructionforworkshop'ssection2厂房第二部分地面施工,25.d,2007/8/58:00,2007/8/2917:00,,3,
62,Groundslabconstructionforworkshop'ssection2厂房第二部分地面面层施工,15.d,2007/10/88:00,2007/10/2217:00,,3,
63,Finalcleanupforworkshop'ssection2厂房第二部分竣工清理,6.d,2007/11/68:00,2007/11/1117:00,,3,
64,Checkandacceptworkshop'ssection2byemployer厂房第二部分业主验收,1.d,2007/11/128:00,2007/11/1217:00,63,3,
65,Workshop'ssection3construction厂房第三部分施工,167.d,2007/6/298:00,2007/12/1217:00,,2,
66,Compactionworkforsection3厂房第三部分强夯,7.d,2007/6/298:00,2007/7/517:00,,3,
67,Excavatingearthforworkshop'ssection3厂房第三部分土方开挖,10.d,2007/7/58:00,2007/7/1417:00,,3,
68,Foundationtrenchcleaningforworkshop'ssection3厂房第三部分基槽清理,5.d,2007/7/158:00,2007/7/1917:00,67,3,
69,Checkandacceptthefoundationtrenchforworkshop'ssection3厂房第三部分基槽验收,1.d,2007/7/208:00,2007/7/2017:00,68,3,
70,Foundationconstructionforworkshop'ssection3厂房第三部分基础施工,10.d,2007/7/218:00,2007/7/3017:00,69,3,
71,Lightningprotection&groundingconstructionforworkshop'ssection3(testingground-resistance)厂房第三部分避雷接地施工(接地电阻测试),10.d,2007/7/218:00,2007/7/3017:00,,3,
72,Checkandacceptthefoundationforworkshop'ssection3厂房第三部分基础验收,1.d,2007/7/318:00,2007/7/3117:00,71,3,
73,tampedbackfilloffoundationforworkshop'ssection3厂房第三部分基础夯填,10.d,2007/8/18:00,2007/8/1017:00,72,3,
74,"Undergroundpipenetworkinstallationforworkshop'ssection3(irrigationtest,pressuretest)厂房第三部分地下管网安装(灌水试验、压力试验)",10.d,2007/8/18:00,2007/8/1017:00,,3,
75,Steelstructuremakingforworkshop'ssection3厂房第三部分钢结构制作,35.d,2007/7/138:00,2007/8/1617:00,,3,
76,Steelstructureframeinstallationforworkshop'ssection3厂房第三部分钢结构骨架安装,20.d,2007/8/118:00,2007/8/3017:00,73,3,
77,Checkandacceptthesteelstructure'smainbodyforworkshop'ssection3厂房第三部分钢结构主体验收,1.d,2007/8/318:00,2007/8/3117:00,76,3,
78,Roofboardingandwallplateinstallationforworkshop'ssection3厂房第三部分屋面板、墙板安装,25.d,2007/9/18:00,2007/9/2517:00,77,3,
79,Interiorpartitionconstructionforworkshop'ssection3厂房第三部分内部隔墙施工,20.d,2007/9/28:00,2007/9/2117:00,,3,
80,Internalandexternalwindowsanddoorsintallationforworkshop'ssection3厂房第三部分内外门窗安装,25.d,2007/9/58:00,2007/9/2917:00,,3,
81,Internaldécorationconstructionforworkshop'ssection3厂房第三部分内装修施工,30.d,2007/9/268:00,2007/10/2517:00,78,3,
82,"Stormwater/watersupplyandseweragesysteminstallationforworkshop'ssection3(irrigationtest,pressuretest)厂房第三部分雨水/给排水系统安装(灌水试验、压力试验)",45.d,2007/9/18:00,2007/10/1517:00,,3,
83,Laydowntrayandcableforworkshop'ssection3(commissioningwithpower)厂房第三部分桥架、电缆敷设(通电试运行),97.d,2007/9/18:00,2007/12/617:00,,3,
84,Hydrant/sprinklingsysteminstallationforworkshop'ssection3(pressuretest)厂房第三部分消防栓/喷淋系统安装(压力试验),50.d,2007/10/188:00,2007/12/617:00,,3,
85,Heatingsysteminstallationforworkshop'ssection3(pressuretest)厂房第三部分暖气系统安装(压力试验),68.d,2007/9/308:00,2007/12/617:00,,3,
86,Dustcollection/compressedair/naturalgas/coolingwater.etcsystemmainductinstallationforworkshop'ssection3厂房第三部分除尘/压缩空气/燃气/冷却水等系统主(风道)管道安装,90.d,2007/9/88:00,2007/12/617:00,,3,
87,Firealarmdetectionforworkshop'ssection3(linkedcommissioning)厂房第三部分消防报警检测装置(联动试车),58.d,2007/10/108:00,2007/12/617:00,,3,
88,Lightingfixtureinstallationforworkshop'ssection3(commissioningwithpower)厂房第三部分照明灯具等系统安装(通电试运行),60.d,2007/10/88:00,2007/12/617:00,,3,
89,IT/tel/CCTV/assesscontrolinstallationandcommissioningforworkshop'ssection3厂房第三部分网络/电话/监控门禁元件安装和试运行,35.d,2007/11/28:00,2007/12/617:00,,3,
90,Fabricgroundconstructionforworkshop'ssection3厂房第三部分结构地面施工,25.d,2007/8/128:00,2007/9/517:00,,3,
91,Groundslabconstrucitonforworkshop'ssection3厂房第三部分地面面层施工,17.d,2007/10/268:00,2007/11/1117:00,,3,
92,Finalcleanupforworkshop'ssection3厂房第三部分竣工清理,6.d,2007/12/68:00,2007/12/1117:00,,3,
93,Checkandacceptworkshop'ssection3byemployer厂房第三部分业主验收,1.d,2007/12/128:00,2007/12/1217:00,92,3,
94,Officebuildingconstruction办公楼施工,123.d,2007/7/58:00,2007/11/417:00,,1,
95,Foundationconstruction基础施工,10.d,2007/7/58:00,2007/7/1417:00,,2,
96,Lightningprotection&groundingconstruction(testingground-resistance)避雷接地施工(接地电阻测试),10.d,2007/7/58:00,2007/7/1417:00,,2,
97,Checkandacceptthefoundation基础验收,1.d,2007/7/158:00,2007/7/1517:00,,2,
98,Mainbodyconstruction主体施工,30.d,2007/7/168:00,2007/8/1417:00,,2,
99,Indoorpartitionwallandbrickconstruction内隔墙及砌体施工,30.d,2007/8/158:00,2007/9/1317:00,,2,
100,Checkandacceptthemainbody主体验收,1.d,2007/9/148:00,2007/9/1417:00,99,2,
101,Officebuildinginternalandexternaldécoration办公楼室内外装饰装修,60.d,2007/9/18:00,2007/10/3017:00,,2,
102,Officebuildinginternalandexternalwindowsanddoorsinstallation办公楼室内外门窗安装,20.d,2007/9/218:00,2007/10/1017:00,,2,
103,Lightningprotectionnetinstallationandtesting避雷网安装和检测,24.d,2007/8/158:00,2007/9/717:00,,2,
104,Hydrant/watersupplyandseweragesysteminstallation消火栓/给排水系统安装,50.d,2007/8/318:00,2007/10/1917:00,,2,
105,"Electricpipelaydownandlightingfixtureandswitch,socketinstallation电气配管预埋和照明灯具、开关插座安装(通电照明试运行)",94.d,2007/7/288:00,2007/10/2917:00,,2,
106,Firealarmdetection消防报警检测装置,81.d,2007/8/108:00,2007/10/2917:00,,2,
107,Sanitarywareinstallation卫生洁具安装,20.d,2007/10/108:00,2007/10/2917:00,,2,
108,IT/tel/CCTV/assesscontrolinstallationandcommissioning网络/电话/监控门禁元件安装和试运行,30.d,2007/9/308:00,2007/10/2917:00,,2,
109,Finalcleanup竣工清理,5.d,2007/10/308:00,2007/11/317:00,,2,
110,Checkandacceptbyemployer业主验收,1.d,2007/11/48:00,2007/11/417:00,109,2,
111,"Outdoorwork(Harden,Greening,enclosurewall,indextag)室外工程(硬化、绿化、围墙、标牌)",173.d,2007/6/128:00,2007/12/117:00,,1,
112,Roadsoutsidecompaction室外道路强夯,6.d,2007/7/68:00,2007/7/1117:00,,2,
113,"Pumproom,pond,substation,powerroomconstruction.etc泵房、水池、变电所、动力房等施工",50.d,2007/7/108:00,2007/8/2817:00,,2,
114,Equipmentofpumproom/high-lowdistributionequipment/compressedairequipmentinstallationandcommissioning泵房设备/变电所高低压配电设备/压缩空气设备安装和试运行,40.d,2007/8/278:00,2007/10/517:00,,2,
115,Dustcollectionequipment/coolingwaterequipmentinstallationandcommissioning除尘设备/冷却水塔设备安装和试运行,60.d,2007/9/28:00,2007/10/3117:00,,2,
116,"Levelground,constructionsitefacilities场地平整、临时设施",30.d,2007/6/128:00,2007/7/1117:00,,2,
117,Outdoorretainingwallconstruction室外挡土墙施工,120.d,2007/6/288:00,2007/10/2517:00,,2,
118,Outdoorwatersupply&sewerage/storm-water/electricnetworklaydown室外给排水/雨水/电气管网敷设,120.d,2007/6/298:00,2007/10/2617:00,,2,
119,"Outdoorgreening,
温馨提示
- 1. 本站所有资源如无特殊说明,都需要本地电脑安装OFFICE2007和PDF阅读器。图纸软件为CAD,CAXA,PROE,UG,SolidWorks等.压缩文件请下载最新的WinRAR软件解压。
- 2. 本站的文档不包含任何第三方提供的附件图纸等,如果需要附件,请联系上传者。文件的所有权益归上传用户所有。
- 3. 本站RAR压缩包中若带图纸,网页内容里面会有图纸预览,若没有图纸预览就没有图纸。
- 4. 未经权益所有人同意不得将文件中的内容挪作商业或盈利用途。
- 5. 人人文库网仅提供信息存储空间,仅对用户上传内容的表现方式做保护处理,对用户上传分享的文档内容本身不做任何修改或编辑,并不能对任何下载内容负责。
- 6. 下载文件中如有侵权或不适当内容,请与我们联系,我们立即纠正。
- 7. 本站不保证下载资源的准确性、安全性和完整性, 同时也不承担用户因使用这些下载资源对自己和他人造成任何形式的伤害或损失。
最新文档
- 【提高卷】2024年浙教版数学七年级下册6.3扇形统计图 同步练习
- 【培优卷】2020-2021学年沪教版小学五年级数学下册《第三章 简易方程(二)》单元测试题(含解析)
- 【提高卷】2024年浙教版数学七年级下册6.4 频数与频率 同步练习
- 《不动产测绘(活页式)》 课件全套 1-5不动产测绘概述- 不动产测绘成果的检查与验收
- 实习生自我小结
- 促销方案之汽修厂促销活动方案
- 2024年企业员工劳动合同标准范文(二篇)
- 2024年咨询服务委托协议格式版(二篇)
- 2024年购房居间合同(二篇)
- 2024年农产品购销合同范例(三篇)
- (茅台酒)白酒酿造工职业技能认定-制曲制酒考试题库附参考答案【典型题】
- 泰国社会与文化智慧树知到期末考试答案章节答案2024年浙江越秀外国语学院
- 2024年贵州黔西南州教育局公益性岗招聘历年公开引进高层次人才和急需紧缺人才笔试参考题库(共500题)答案详解版
- 学习课件铸牢中华民族共同体意识PPT
- 浅析多消防控制室合并联网改造
- 货物验收单;
- 内科疑难(危重)病例讨论记录规范及模板
- 探地雷达技术介绍
- 塔吊安全教育讲话稿
- 模拟法庭(民事)-剧本
- 国土资源局领导管理失职的检讨书
评论
0/150
提交评论