精品文档-下载后可编辑PMP认证考试练习题(29,30)PMP认证考试练习题(29,30)

一、PMP认证考试练习题(29)

1.Whichofthefollowingimpactsthecriticalpath?[2.5分]

A.Changingthetaskduration.

B.Reducethefreefloatofanactivity.

C.Executingabackwardpass

D.AorB.

E.Noneoftheabove.

2.Therangeoftimeallowedforanactivitytobecompletedinisthe().[2.5分]

A.Plannedtime(Duration).

B.Floattime(LS-ES,orLF-EF).

C.Criticaltime(whenES=LS,orEF=LF).

D.Scheduledtime(LF-ES).

E.Event.

3.Freefloatistheamountoftimethatanactivitymaybedelayedwithoutaffectingthe().[2.5分]

A.Earlystartofthesucceedingactivities.

B.Latestartofthesucceedingactivities.

C.Projectfinish.

D.Costoftheproject.

E.Noneoftheabove.

4.UsingtheproblemstatedintheSpecialwindow,Calculatethedeviationofdurationforthetask,usingthePERTconceptofstandarddeviationoftaskduration.[2.5分]

A.0.5

C.1.8

D.2.2

E.2.8

5.Incrashingatask,youwouldfocuson:[2.5分]

A.Asmanytasksaspossible.

B.Noncriticaltasks.

C.Acceleratingperformanceoftasksoncriticalpath.

D.Accelerateperformancebyminimizingcost.

E.AandD.

6.UsingtheproblemstatedintheSpecialwindow,Calculatetheexpectedvalueofduration(indays)usingthePERTconceptoftheexpecteddurationofatask[2.5分]

B.8.8

C.9.1

D.9.7

E.10.5

7.UsingtheWBSintheSpecialwindow,aninstanceofaworkpackageis:[2.5分]

A.Buildhouse

B.Excavate

C.PrepareFoundation

D.BandC.

E.Noneoftheabove

8.Allofthefollowingarecategoriesofamilestoneinascheduleexcept:[2.5分]

A.Enddate.

B.Contractdates.

C.Keyeventsscheduled.

D.Imposeddates.

E.Taskduration.

9.TheactualconfigurationofaPERT/CPMnetwork()theamountofresourcesthatcanbedevotedtotheproject.[2.5分]

A.Increases.

B.Isnotaffectedby

C.Doesnotrequire

D.Isheavilydependentupon

E.Istheonlymeansofdetermining

10.Excessiveflexibilityinspecifyingrequirementswill()thelikelihoodoftimeoverruns.[2.5分]

A.Reduce.

B.Eliminate.

C.Double

D.Increase

E.Notaffect

11.Thekeypurposeofprojectcontrolisto:[2.5分]

A.Planaheadforuncertainties.

B.Generatestatusreports.

C.Keeptheprojectontrack.

D.Developtheprojectroadmap.

E.Alloftheabove.

12.Fasttrackingmeansto:[2.5分]

A.Speedupaprojectthroughparalleltasks.

B.Swaponetaskforanother.

C.Reducethenumberoftasksifpossible.

D.BandC.

E.Noneoftheabove.

13.Asaprojectiscarriedoutandslacktimeisconsumedonindividualtasks,theslackleftoverfortheremainingtasksis:[2.5分]

A.Insignificant.

B.Reduced.

C.Unchanged.

D.Increased.

E.Doubled.

14.Thepurposeofadummyactivityinanactivity-on-arrowdiagramisto:[2.5分]

A.Identifyataskthatcouldbereplacedbyanother.

B.Taketheslacktimeintoaccount.

C.Showataskthatisnotnecessarilyneeded.

D.Denoteamilestone.

E.Showadependencyrelationship.

15.OnNovember1,$1000worthofworkontaskAwassupposedtohavebeendone(BCWS);however,theBCWPwas$850.Calculatetheschedulevariance:[2.5分]

A.¥-100

B.¥100

C.¥-150

D.¥150

E.85%

16.Aplanhasbudgetedthreeweeksofeffortforconsultants,butthejobwasdoneinonlytwoweeks.Calculatethevariance:[2.5分]

A.1.50%

B.33.00%

C.75%

D.67%

E.Noneoftheabove.

17.Resourcelevelingwilloftenaffecttheprojectbymakingit:[2.5分]

A.Shorter.

B.Longer

C.Moreresponsivetocustomerneeds.

D.AandC.

E.BandC.

18.UsingthefigureintheSpecialwindow,TheslacktimeinActivity"G"is()weeks.[2.5分]

19.UsingthefigureintheSpecialwindow,Activity"D"hasalateststarttimeof()weeksandalatestfinishtimeof()weeks.[2.5分]

A.2,10

B.4,12

C.6,14

D.7,15

E.9,17

20.UsingthefigureintheSpecialwindow,Activity"L"hasanearlystarttimeof()weeksandanearlyfinishtimeof()weeks.[2.5分]

A.11,13

B.12,14

C.13,15

D.14,16

E.15,17

二、PMP认证考试练习题(30)

1.UsingthefigureintheSpecialwindow,TheCriticalpathis()weeks.[2.5分]

A.21

B.22

C.23

D.24

E.25

2.UsingthedatashownintheSpecialwindow,ActivitiesP,Q,andTarecriticalpathactivities.Inordertoshortenthetimedurationoftheproject,whichactivityshouldbe"crashed"first?[2.5分]

3.UsingthefigureintheSpecialwindow,Byhowmanyweekscanactivity"F"slipwithoutextendingtheenddateoftheproject?[2.5分]

4.UsingthefigureintheSpecialwindow,Thecriticalpathis:[2.5分]

A.A-B-G

B.C-G

C.C-D

D.E-F

E.A-B-GandC-D

5.ThefirststepinbuildingaPERT/CPMnetworkisto:[2.5分]

A.Createaflowchart

B.Determinethecriticalpath

C.Showtaskrelationships

D.Createaworkbreakdownstructure

E.Noneoftheabove.

6.Thecriticalpathinaschedulenetworkisthepaththat:[2.5分]

A.Takesthelongesttimetocomplete

B.Mustbedonebeforeanyothertasks

C.Allowssomeflexibilityinschedulingastarttime.

D.Isnotaffectedbyscheduleslippage

E.Alloftheabove.

7.Assumethatyouhaveanetworkwhereanactivityonthecriticalpathcanbecrashedbytwoweeks.Iftheactivityisactuallycrashedbytwoweeks,then:[2.5分]

A.Theproject'sschedulewillbereducedby2weeks.

B.Theavailableslackonthenoncriticalpathswillincrease.

C.Anewcriticalpathmayappearafterthecrash.

D.Alloftheabove.

E.AandB.only.

8.YourteamhaspreparedaCPMscheduleforyourreview.Younoticethatonenodehassixinputs(includingtwodummyactivities)andfouroutputs(whichincludeonedummyactivity).Selectthecorrectstatementfromthefollowing:[2.5分]

A.Thisisavalidrepresentationifthelogiciscorrect.

B.Thisisinvalidbecauseanodecanhaveamaximumofonedummyinputrepresentationifthelogiciscorrect.

C.Thisisinvalidbecausenodescannothavebothdummyinputsanddummyoutputs.

D.Thisisainvalidbecausethenumberofoutputsmustequalthenumberofinputs.

E.Thisisinvalidbecauseamaximumoftwoinputsandtwooutputsareallowedusingthecriticalpathmethod.

9.Duringprojectexecution,thecustomerauthorizesandfundsascopechangewhichrequiresamajorchangeintheschedule.Thebaselineschedule:[2.5分]

A.Nowbecomesthenewschedule,includingthechanges,andtheoriginalbaselineisdisregarded.

B.Isstilltheoriginalbaselinebutannotatedtoreflectthatachangehastakenplace.

C.Isamendedtoreflectthescopechange,buttheoriginalbaselineisstillmaintainedforpost-projectreview.

D.Ismeaninglesssinceeveryscheduleupdatechangesthebaseline(i.e.,arubberbaseline.)

E.Isthesamesincebaselineschedulescannotchangeoncethedevelopmentphaseiscompleted.

10.Networkschedulesarepreparedduringthe()phaseandupdatedduringthe()phase.[2.5分]

A.Conceptual,execution.

B.Development,implementation.

C.Development,close-out.

D.Implementation,close-out.

E.Planning,finishing.

11.SchedulingsystemssuchasPERT,ADM,andPDMareprojectmanagementtoolstobeusedby:[2.5分]

A.Theprojectmanagerandprojectofficepersonnel.

B.Theprojectteamandfunctionalmanagers.

C.Theprojectsponsor.

D.Alloftheabove.

E.AandB.only.

12.Increasingresourcesonthecriticalpathactivitiesmaynotalwaysshortenthelengthoftheprojectbecause:[2.5分]

A.Certainactivitiesaretime-dependentratherthanresource-dependent(i.e.,usingthreeovensratherthanonetobakeacake).

B.Safety,OSHAandEPAmayhaveplacedrestrictionsonthenumberofpeopleusedoncertainactivitiesorinthephysicallocationoftheproject.

C.Theskillleveloftheaddedresourcesmightnotbeappropriatefortheactivitiestobeperformed.

D.Addingmoreresourcesmaycreateadditionalworkandproduceinefficiencies(i.e.,additionalpeoplemayneedtrainingandsupervision.)

E.Alloftheabove.

13.AlinemanagerprovidesyouwiththreeestimatesforhisactivityinyourPERTnetwork.Hisestimatesare2weeksoptimistically,4weeksmostlikely,and12weekspessimistically.Theexpectedtimewhichwouldappearonthechartwouldbe:[2.5分]

A.4weeks

B.5weeks

C.6weeks

D.7weeks

E.Noneoftheabove.

14.Managementhasdecidedto"crash"aprojectinordertoavoidpenaltypaymentsforlatedeliveries.Tocrashtheproject,eitherovertimeoradditionalresourcesshouldbeassignedto:[2.5分]

A.Allactivities.

B.Onlythoseactivitieswiththelongesttimedurations.

C.Thoseactivitiesonthecriticalpathbeginingwiththelongesttimedurationactivities.

D.Thoseactivitieswiththegreatestdegreeofrisk.

E.Noneoftheabove.

15.Anetworkhasbeendevelopedwithresourcesfromsixdifferentdepartments.Oneofthesixdepartmentshasjustinformedyouthattheycanincreasethenumberofemployeesfrom5to8.Thiswillresultin:[2.5分]

A.Ashorteningofthecriticalpath.

B.Ashorteningofthenoncriticalpath.

C.Adecreaseinthetotalcostoftheproject.

D.Anincreaseinthecostoftheproject.

E.AthroughDarepossiblebaseduponwheretheresourcesaredeployed.

16.Barchartsaremostappropriatefor:[2.5分]

A.Comparingactualtoplannedperformancetoeachactivity.

B.Showingslacktime.

C.Showingcriticalpathdependencies.

D.Showingwhichactivitiescanberearrangedinparallel.

E.Alloftheabove.

17.Anon-criticalpathactivityiscompletedinhalfthetime.Then,[2.5分]

A.Thecriticalpathisalsoreduced.

B.Theslackinthepathcontainingthisactivitywillincrease.

C.Thetotalcostforthisactivityhasdecrea

温馨提示

  • 1. 本站所有资源如无特殊说明,都需要本地电脑安装OFFICE2007和PDF阅读器。图纸软件为CAD,CAXA,PROE,UG,SolidWorks等.压缩文件请下载最新的WinRAR软件解压。
  • 2. 本站的文档不包含任何第三方提供的附件图纸等,如果需要附件,请联系上传者。文件的所有权益归上传用户所有。
  • 3. 本站RAR压缩包中若带图纸,网页内容里面会有图纸预览,若没有图纸预览就没有图纸。
  • 4. 未经权益所有人同意不得将文件中的内容挪作商业或盈利用途。
  • 5. 人人文库网仅提供信息存储空间,仅对用户上传内容的表现方式做保护处理,对用户上传分享的文档内容本身不做任何修改或编辑,并不能对任何下载内容负责。
  • 6. 下载文件中如有侵权或不适当内容,请与我们联系,我们立即纠正。
  • 7. 本站不保证下载资源的准确性、安全性和完整性, 同时也不承担用户因使用这些下载资源对自己和他人造成任何形式的伤害或损失。

评论

0/150

提交评论