第1题Theconstructionorganizationdesigncanbedividedinto()accordingtodifferentpreparationobjects.AConstructionorganizationdesignofindividualprojectsBGeneraldesignofconstructionorganizationCConstructionorganizationdesignofunitprojectsDConstructionplanEConstructionorganizationdesignofsubprojects正确答案:BCD第2题Theconstructionandproductionofmodernarchitecturalproductshasbecomeacomprehensiveandcomplexsystemengineeringwith(),hightechnology,informatization,industrialization,andmodernization.AMultiplepersonnelBMultipletypesofworkCMultipleprofessionsDMultipledevices正确答案:ABCD第3题Theconstructionorganizationdesigncanbedividedinto()accordingtodifferentpreparationobjects.AConstructionorganizationdesignofindividualprojectsBGeneraldesignofconstructionorganizationCConstructionorganizationdesignofunitprojectsDConstructionplanEConstructionorganizationdesignofsubprojectsConstructionorganizationdesigncanbedividedintogeneralconstructionorganizationdesign,constructionorganizationdesignofunitprojects,andconstructionplanaccordingtodifferentpreparationobjects.正确答案:BCD第4题BIMisamulti-dimensionalmodelinformationintegrationtechnologydevelopedonthebasisofexistingCADtechnologyinthepastdecade,wheremulti-dimensionalreferstothree-dimensionalspace,thinkingtime,fivedimensions(),andthespecificapplicationsofNdimensions.ADesignBCostCImplementationphaseDOperationprocess第5题Theconstructionplanisaconstructiontechnologyandorganizationplanpreparedwith()asthemainobjecttoguideitsconstructionprocessindetail.ASingleprojectBUnitprojectCSubprojectDEngineeringproject第6题Thefollowing()isnotthemaincontentsoftheconstructionorganizationdesignoftheunitproject.AProjectoverviewandconstructioncharacteristicsBConstructionscheduleCEngineeringequipmentsupplierDConstructionlayout第7题Theconstructionorganizationdesignofunitprojectisorganizedbytheprojectmanager,preparedbytheprojectengineer,andapprovedby()ATechnicaldirectorofgeneralcontractingunitBTechnicalleaderoftheconstructionunitortechnicalpersonnelauthorizedbythetechnicalleaderCTechnicalleaderoftheprofessionalcontractingunitortechnicalpersonnelauthorizedbythetechnicalleaderDProjecttechnicalleader第8题Theoveralldesignofconstructionorganizationisjointlypreparedbythechiefengineerofthegeneralcontractingunit,inconjunctionwiththeengineersoftheconstructionunit,designunit,andsubcontractingunit,andthe()isresponsibleforapproval.ATechnicaldirectorofgeneralcontractingunitBTechnicalleaderoftheconstructionunitortechnicalpersonnelauthorizedbythetechnicalleaderCTechnicalleaderoftheprofessionalcontractingunitortechnicalpersonnelauthorizedbythetechnicalleaderDProjecttechnicalleader第9题Theoveralldesignofconstructionorganizationplaysaroleof().AImplementationBControllabilityCPracticalityDUsability第10题Aprojectthathasindependentdesignandconstructionconditionsandcannotindependentlyexertproductioncapacityorbenefitsiscalled().AConstructionprojectBSingleprojectCUnitprojectDPartialproject第11题Aworkshopproductionlineorindependentprojectthathasindependentdesigndocumentsandcangeneratebenefitsorproductioncapacityaftercompletionandproductioniscalled().AConstructionprojectBSingleprojectCUnitprojectDPartialproject第12题Whichofthefollowingstatementsisincorrectregardingbuildingproductsandconstructioncharacteristics.()AThefixednatureoftheproductdeterminesthefluidityofproductionBConstructionengineeringproductsnotonlyneedtomeetvariousfunctionalrequirements,butalsoachieveacertainartisticeffectCBuildingproductshavecomplexityDHighinvestmentinconstructionproductsandshortproductioncycle第1题Thecontentoftheprojectoverviewincludes(

)

andotheraspects.AOverviewofengineeringconstructionBArchitecturaldesignfeaturesCStructuralfeaturesDConstructionsiteconditionsE

Engineeringbudgetdocumentsandrelatedquotas正确答案:ABCD第2题Architecturaldesignoverviewincludes(

).ABuildingareaoftheproposedprojectBFloor

numberandheightofbuildingCTypesofmainstructureconstructionDWaterproofingandenergy-savingrequirementsforbuildingsEFoundationembedmentdepth正确答案:BAD第3题Theoverviewofunitproject

buildingstructureengineeringincludes(

).AStructuraltypeBFoundationtypeCStructuralsafetylevelDBuildingfireresistance正确答案:DCBA第4题Thepreparationbasisfortheconstructionorganizationdesignofunitprojectsincludes(

).APossibleconditionsprovidedbytheconstructionunitforprojectconstructionB

ConstructionproductsituationCRequirementsofsuperiorsupervisoryunitsandconstructionunitsforthisprojectDApprovedconstructiondrawingsEGeneralConstructionDesign正确答案:ACDE第5题Theengineeringoverviewintheconstructionorganizationdesignofunitprojectsincludes(

).AMainsituationoftheprojectBDesigncharacteristicsofeachprofessionC

MainconstructionconditionsD

FeasibilitystudyreportE

Engineeringconstructioncharacteristics正确答案:ECBA第6题ModuleTwotest第1题Constructiondeploymentreferstotreatingtheentireengineeringconstructionprojectasasystem,predictingandmakingdecisionson____thataffect

theentiresystem.Itshouldmainly

clarifythedivisionoflaborandorganizationalarrangementsforconstructiontasks,determinethemaincontentofpreparationwork,anddevelop____,auxiliaryengineering,4____

of

____

and

themain____of

____.Theconstructiondeploymentshouldbebasedonthescaleoftheconstructionproject,thenatureoftheproject,andthe____

ofconstructionprocess.Startingfromtheneedsofproduction,coordinateandarrangetheconstructionandhandoversequenceofallprojects.正确答案::Majorissues正确答案::Mainproject正确答案::Constructionprocedures正确答案::Ancillaryworks正确答案::Constructionplan正确答案::Subproject正确答案::Objectiveconditions第2题Thefollowing

()isnotthebasisforthepreparationofunitprojectconstructiondeployment.AConstructioncontractorbiddingdocumentsBConstructiondrawingsCGeneraldesignofconstructionorganizationDEngineeringorganizationandmanagementagency第3题Thefollowing

()doesnotbelongtotheconstructiondeploymentofunitprojects.ADetermineconstructionobjectivesBDetermineprojectcostCEstablishaconstructionsiteprojectmanagementorganizationDScheduleandspatialorganization第4题Accordingtothe"ConstructionProjectManagementStandards"GB/AccordingtoT50326-2017,theresponsibilitiesofaprojectmanagerinclude().AOrganizeorparticipateinthepreparationofprojectmanagementimplementationplansBDistributebenefitswithinthescopeofauthorizationCEnsureprojectfundingisinplaceDDevelopinternalcompensationmethodsEDynamicallymanageresources正确答案:ABE第5题Thestatement

()

abouttheconstructionorganizationoftheprojectisincorrect.AAnadvancedandscientificprojectmanagementmodelandasoundorganizationalstructureareprerequisitesforensuringthesmoothprogressofconstruction.BTheprojectorganizationalstructureistheguaranteeforengineeringprojectstoachievegoodsocialandeconomicbenefits.CTheprojectorganizationistheprimarycontentthattowards

thesuccessorfailureofprojectmanagement.DTheprojectorganizationis

to

clearly

divide

the

responsibilitiesforprojectmanagementpersonnel第6题SinglechoicequestionsTheprojectmanagerofaconstructionenterprisereferstotheprojectmanagerwhoisentrustedby()tobefullyresponsiblefortheconstructionprocessoftheengineeringproject,andistherepresentativeofthelegalrepresentativeoftheconstructionenterpriseontheengineeringproject.ARepresentativeofthelegalrepresentativeoftheenterpriseBOwnersCEnterpriselegalpersonDLegalrepresentativeoftheenterprise第7题Thecorrectexpressionoftheconstructionsequenceforhighrisecast-in-placereinforcedconcretestructurebuildingsis().AThemainbuildingwillbeconstructedfirst,andthepodiumbuildingwillbeconstructedlaterBThepodiumbuildingwillbeconstructedfirst,andthemainbuildingwillbeconstructedlaterCThemainbuildingandthepodiumbuilding

willbe

parallelly

constructedDThemainbuildingandthepodiumbuilding

willbe

alternately

constructed第8题Whenahousehashighorlowfloorsorspans,thecorrectconstructionsequenceis().AStartingconstructionfromhighfloor

orhighspanBStartingconstructionfromalowfloor

orlowspanCStartingconstructionfromhighandlowfloorsorattheintersectionofhighandlowspansDArrangetheconstructionsequenceaccordingtotheconvenienceofconstruction第9题Themainprojectgenerallyadoptstheconstructionstartingpointflowdirectionof().A

FrombottomtotopBFromtoptobottomCFromcentertotop,fromtoptocenterDAlloftheaboveareacceptable第10题Theconstructionsequenceforoutdoordecorationisgenerally().AFrombottomtotopBFromtoptobottomCSimultaneouslyDAlloftheaboveareacceptable第11题Themostcommonlyusedconstructionsequencein

interiorandexteriordecorationis().AExterior

beforeinteriorBInteriorbeforeexteriorCSimultaneouslyDNorequirements第12题Theconstructioncharacteristicofcast-in-placereinforcedconcretehigh-risebuildingsis

().ALargeamountofplasteringworkBHighstabilityrequirementsforconstructionequipmentCLargeamountofbricklayingDMultipleprefabricatedcomponentswithlargeliftingcapacity第13题Thebasicprinciplesthatunitengineeringconstructionproceduresshouldfolloware().AFirstundergroundandthenabovegroundBCivilconstructionbeforeequipmentCFirstthemainbody,thentheenclosureDDecoration

beforestructureEFirstabovegroundandthenunderground正确答案:ABC第14题Theconstructionobjectivesincludequalityobjectives,constructionperiodobjectives,safetyobjectives,civilizationobjectives,costobjectives,etc.第15题Theconstructionprocessofdifferenttypesofbuildingshasdifferentconstructionsequences.

Theconstructionprocessofthesametypeofbuildinghasonlyonefixedandunchangingconstructionsequence.ModuleThreetest第1题Thefollowing

()belongstotheconstructiondepartmentoftheunitproject.ADetermineconstructionobjectivesBDetermineprojectcostCEstablishaconstructionsiteprojectmanagementorganizationDScheduleandspatialorganization正确答案:ACD第2题Theconstructionsequenceshouldfollowtheprincipleof"undergroundfirst,thenaboveground,mainbodyfirst,thenenclosure,structurefirst,thendecoration,andequipmentfirst,thencivilengineering".第3题Thefollowingwork()isthekeycontentoftheconstructionplan.ASelectconstructionmethodsandmachineryBDeterminethestartingpointandflowdirectionofconstructionCDeterminetheconstructionsequenceDDeterminetheconstructionorganizationmethod第4题Thefollowing()isnotpartoftheconstructionplan.ADetermineconstructionmethodsBDeterminetheconstructionsequenceCSelectconstructionmachineryDEstimatethequantitiesofmajorprojects第5题Theconstructionplanoftheunitprojectmainlydeterminestheconstructionsequence,constructionmethods,andselectthe

applicableconstructionmachinery.ASingleprojectBUnitprojectCDivisionalandsubprojectDConstructionprocess第6题Allworkerswhoexcavateworkpitsshouldstrictlyfollowthe()

oftheconstructionmanagementpersonnel.ASafetytechnicaldisclosureBSafetyeducationCOnsitedemonstrationDGraduallyassignwork第7题Theinstallationoffoundationpitsupportmustbecarriedoutintheorderof().AExcavationbeforesupportBTrenchingsupport,firstsupporting,thenexcavatingCSupportingwhileexcavatingDDigtothebottomofthegroovebeforesupporting第8题Thetemplateanditsbracketmustbesetwith()duringtheinstallationprocess.AFacilitiesforensuringengineeringqualityBFacilitiesforimprovingconstructionspeedCFacilitiestoensurematerialconservationDTemporaryfixedfacilitiesthatcaneffectivelypreventoverturning第9题Thecontinuousoperationtimeofthemixingdeviceoftheconcretemixertruckshallnotexceed()hours.A6B8C10D12第10题Thetransportationtimeoftheconcrete

fromunloadingfromthemixertothecompletionofpouringshallnotexceed()minutes.A30B40C45D60第11题Thehorizontalbarsettingofasinglerowscaffoldshouldmeettherequirements().AOneendisfixedtothelongitudinalhorizontalrodwitharightanglefastener,andtheotherendisinsertedintothewallatadepthofnolessthan180mmBOneendisfixedtothelongitudinalhorizontalrodwitharightanglefastener,andtheotherendisinsertedintothewallwithadepthofnolessthan100mmCOneendisfixedtothelongitudinalhorizontalrodwitharightanglefastener,andtheotherendisinsertedintothewallatadepthofnolessthan80mmDOneendisfixedtothelongitudinalhorizontalrodwitharightanglefastener,andtheotherendisinsertedintothewallwithadepthofnolessthan50mm第12题Theinclinationanglebetweenthediagonalbraceandthegroundshouldbe().ABetween45and75BBetween45and60CBetween30and60DBetween30and75第13题Whenpreparingtheorganizationdesignplanforpipejackingconstructioninengineeringprojects,itisnecessarytodeveloptargetedandeffective().AConstructiontechnicalindicatorsBConstructionscheduleCMaterialsavingmeasuresDSafetytechnicalmeasuresandspecialplans第14题Thefollowing()requiresexpertargumentation.AInstallationofbuildingcurtainwallswithaconstructionheightof50mandaboveBManualexcavationpileproject

withexcavationdepthof11mandaboveCSteelstructureinstallationproject

withaspanof30mandaboveDUndergroundworkproject第15题Thespecialconstructionplanneedstobesignedby()beforeimplementation.ATechnicalleaderandprofessionalsupervisionengineeroftheconstructionunitBProjecttechnicalleaderandprofessionalsupervisionengineerCProjectmanagerandchiefsupervisionengineerDTechnicalleaderandchiefsupervisingengineeroftheconstructionunit第16题Theconstructionplanshouldbepreparedby().AProjectsupervisortechnicalpersonnelBProjectmanagerCEnterprisetechnicalleaderDPersoninchargeoftheenterprise第17题Beforetheimplementationofthespecialconstructionplan,thepreparationpersonnelorprojecttechnicalleadershouldconducttechnicaldisclosuretotheconstructionsite

().ASafetyofficerBTeamleaderCPersoninchargeoflaborserviceDAdministratorsandoperatorsModuleFourtest第1题Accordingtorelevantnationalregulations,thefollowingprojectsthatrequireseparatepreparationofspecialconstructionplansinclude().AFoundationpit,trenchsupportanddewateringengineeringwithexcavationdepthnotexceeding5m(including5m)BHorizontalconcretecomponentformworksupportsystemwithaheightexceeding8moraspanexceeding18mCEarthexcavationengineeringforfoundationpitsandtrencheswithexcavationdepthexceeding3m(including3m)DProjectsthatusemanual,mechanicalorblastingdemolitionEHorizontalconcretecomponentformworksupportsystemandspecialstructureformworkengineering正确答案:CDE第2题Thefollowingstatements()doesnotbelongtothecharacteristicofsequentialconstruction.ANotfullyutilizingtheworkingfaceforconstruction,resultinginalongconstructionperiodBThe

professionalworkteamsareunabletooperatecontinuouslyandhavetimeintervals,resultingintheinabilitytobalancetheuseoflaborandconstructionequipmentandotherresourcesCTheamountofresourcesinvestedperunittimehasmultiplied,andtemporaryfacilitiesonsitehaveincreasedDTheamountoflabor,constructionmachinery,materials,andotherresourcesinvestedperunittimeisrelativelysmall,whichisconducivetotheorganizationofresourcesupply第3题Inthefollowingdescription,whatdoesnotbelongtothecharacteristicsofparallelconstructionis().AFullyutilizetheworkingfaceforconstruction,withashortconstructionperiodBTheamountofresourcesinvestedperunittimeisrelativelybalanced,whichisconducivetothesupplyandorganizationofresourcesCTheorganizationandmanagementoftheconstructionsitearerelativelycomplexDSuitableforlarge-scalebuildingclusterswithtightschedulerequirementsandengineeringtasksorganizedinbatchesandstages第4题Amongthefollowingdescriptions,()

isthecharacteristicofflowconstruction.AConstructionwillbecarriedoutsequentiallyoneachconstructionsectionbyaprofessionalteamBMultipleprofessionalteamscannotbeinvolvedinflowconstructionduringthesametimeperiodCEachprofessionalteamshouldorganizeconstructioninacontinuousandbalancedmanneraccordingtotheconstructionsequenceDFullyutilizetheworkingface第5题Thefollowingparameters()belongstotheprocessparameter.ANumberofconstructionprocessesBWorkingfaceCNumberofconstructionlayersDDuration第6题Thefollowingparameters()belongstothespatialparameter.ANumberofconstructionprocessesBNumberofconstructionsectionsCFlowrhythmDFlowpace第7题Thefollowingparameters()belongstothetimeparameter.ANumberofconstructionprocessesBWorkingfaceCFlowrhythmDNumberofconstructionlayers第8题Acertainprojectisdividedintofourflowsections,withtwoconstructionteamsconductingequalrhythmflowconstruction.Iftheflowrhythmis4days,theconstructionperiodis().A16daysB18daysC20daysD24days第9题Acertainsubprojectisdividedinto4constructionprocessesand3constructionsections,andtheflowconstructionwithequalstepspacinganddifferentpaceisorganized.Iftheflowrhythm

is6,2,4,and8daysrespectively,theflowpace

is()days.A1B2C4D6第10题Acertainprojectconsistsofthreeconstructionprocesses:A,B,andC,andisconstructedinfourstages.TheflowrateistA=6days,tB=4days,andtC=2days.If

differentflowpaceanddifferentflowrhythmconstructionisattempted,theflowperiodiscalculatedas().A30daysB32

daysC34daysD36days第11题Acertainconstructionprojecthasfourtechnologicalprocesses,eachofwhichiscarriedoutinfivestages.Thedurationofeachprocessineachstageis:4days,6days,5days,6days,and4days;3days,4days,7days,3days,2days;3days,5days,4days,6days,7days;and5days,8days,2days,4days,and4days.Theconstructionperiodshouldbe().A33daysB43daysC53daysD63days第12题Thedummyarrow

representsthevirtualwork,andthedummyarrowlinecanplaytheroleof().AContactBDifferentiationCCircuit

breakerDAlloftheaboveare第13题Theincorrectstatementaboutnodesinthedualcodenetworkdiagramis().ANodesrepresentthemomentswhenpreviousworkendsandsubsequentworkbegins,andtheydonotrequiretimeorresourcestobeconsumedBThetailnodeofthearrowlinerepresentsthebeginningofthework,andthearrownodeofthearrowlinerepresentstheendoftheworkCAccordingtothedifferentpositionsofnodesinthenetworkdiagram,theycanbedividedintostartingnodes,endingnodes,andintermediatenodesDThearrownodenumbermustbesmaller

thanthearrowtailnodenumber第14题Thefollowingstatement()about

thesinglecodenetworkdiagramisincorrect.ATheworkname,duration,andnodenumberrepresentedbythenodearemarkedincirclesandboxesBArrowlinesneithertakeuptimenoruseresourcesCSinglecodenetworkdiagramsalsohavedummyarrowsDAjobcanonlyhaveonecodeandcannothaveduplicatecodesAnswer第15题Theincorrectstatementabouttherulesfordrawingdualcodenetworkdiagramsis().AConnectionswithnoarrowsorbidirectionalarrowsarenotallowedinthenetworkdiagramBThesequencerelationshipdeterminedbytheprocessorworkprogramiscalledtheprocesslogicrelationshipCTheintersectionofworkingarrowsinthenetworkdiagramcanbehandledusingthebridgeorpointingmethodDCrossingofworkarrowsisnotallowedinthenetworkdiagramAnswer第16题Acertainnetworkplanisshowninthefigurebelow,andthe

flowinglogicalrelationship()

isincorrect.AC,D

isafterABAisbeforeCCE,

F,GisafterCDD

isafterB第17题Accordingtothedrawingrulesfordualcodenetworkdiagrams,thereare()drawingerrorsinthefollowingnetworkdiagrams.A5B4C3D2第18题Inthenetworkplan,theearliesttimeforworkshouldbe().AThemaximumvalueoftheearliestcompletiontimeforitspreviousworkBThemaximumvalueoftheearliestcompletiontimeforitssubsequentworkCTheminimumvalueoftheearliestcompletiontimeforitspreviousworkDTheminimumvalueoftheearliestcompletiontimeforitssubsequentwork第19题Inacertainnetworkplan,workAhastwosubsequenttasks,CandD.ThedurationofWorkCandDis12daysand7days,respectively.ThelatestcompletiontimeforworkCandDisthe18thand10thdays,respectively.Therefore,thelatestcompletiontimeforworkAis()day.A3B5C6D8第20题Inthecalculationoftimeparametersforasinglecodenetworkplan,thetimeintervalbetweenadjacenttasks,LAGi-j,equalsto().AThedifferencebetweentheearlieststarttimeofsubsequentworkandtheearlieststarttimeofthisworkBThedifferencebetweentheearliestcompletiontimeofsubsequentworkandtheearlieststarttimeofthisworkCThedifferencebetweentheearlieststarttimeofsubsequentworkandtheearliestcompletiontimeofthisworkDThedifferencebetweenthelatestcompletiontimeofurgentworkandtheearliestcompletiontimeofthiswork第21题Inasinglecodenetworkplan,iftheknowntimeparameter(indays)ofworkCismarkedasshowninthefollowingfigure,thelateststarttime,earliestcompletiontime,andtotaltimedifferencefortheworkare()days,respectively.A3,10,5B3,8,5C5,10,2D5,8,2第22题Thedualcodetimescalenetworkplanforacertainprojectisshowninthefigure,indicatingthefreetimedifferenceandtotaltimedifferenceofworkB

is().AAbout2weeksBAbout4weeksC2weeksand4weeksrespectivelyD3weeksand4weeksrespectively第23题Thedualcodetimescalenetworkplanforpartialengineeringofacertainproject

isshowninthefollowingfigure.Thecorrectstatementaboutthenetworkplanis().AWorkC,E,I,LconstitutethecriticalpathBThetotaltimedifferenceforworkHis2daysCWorkA,C,H,andLarecriticaltasksDThetotaltimedifferenceforworkDis1day正确答案:ABD第24题Thefollowing

()

isincorrectaboutthebasicmethodsofscheduleoptimization.AThebasicmethodforoptimizingprojectscheduleistochangethelogicalrelationshipbetweentasksinthenetworkBWhenselectingkeytasksandcompressingtheirduration,thekeytaskwiththesmallestoptimizationcoefficientshouldbechosenCDuringtheprocessofoptimizingtheprojectschedule,criticalworkcannotbecompressedintononcriticalworkDWhenthedurationofallkeytaskshasreachedthelimitthatcanbeshortenedbuttheconstructionperiodstillcannotmeettherequiredduration,adjustmentsshouldbemadetotheoriginaltechnicalandorganizationalplansoftheplan,ortherequiredconstructionperiodshouldbere-approved.第25题Thepurposeofcostoptimizationistoseek().AMinimumcostBMinimumworkingperiodCThecostoftheshortestconstructionperiodDDurationatthelowestcost第26题Intheengineeringnetworkplan,thetotaltimedifferenceandfreetimedifferenceofMhavebeen4daysand2daysrespectively.Whencheckingitsprogress,itwasfoundthatthedurationofthisworkhasbeenextendedby5days,indicatingtheactualprogressofthisworkM

().AItdoesnotaffectthetotalconstructionperiodorthenormalprogressofsubsequentworkBItdoesnotaffecttheoverallconstructionperiod,butthestarttimeofitsfollow-upworkwillbepostponedby5daysCDelaythestarttimeofitsimmediateworkby5daysandextendthetotalconstructionperiodby3daysDDelaythestarttimeofitsfollow-upworkby3daysandextendthetotalconstructionperiodby1day第27题Thefollowingstatements

()

aboutnodesisincorrect.AThenumberofitsarrownodeshouldbesmallerthanthenumberofthearrowtailnodeBThenodeisonlythetransitionpointbetweenthetwotasks,anditneitherconsumestimenorresourcesCAllnodesinanetworkdiagramshouldbeuniformlynumberedwithoutanymissingorduplicatenumberingDNodesrepresentthebeginningorendofatask,representedbycirclesAnswer第28题Thefollowingstatements

()

isincorrect.AInanetworkdiagram,thereisatleastonecriticalpathBAnetworkplanonlyhasonecriticalrouteCUndercertainconditions,criticalandnoncriticalroutescanbetransformedintoeachotherDAnetworkplanmayhavemultiplecriticalpaths第29题Virtualworkinadualcodenetworkdiagram

().AConsume

bothtimeandresourcesBNeitherconsumestimenorresourcesCOnlyconsumetime,notresourcesDNotconsumetime,onlyconsumeresources第30题Thefollowingdescriptionsofthedrawingrulesfordualcodenetworkdiagrams

()

isincorrect.ANoloopallowedBLineswithdoublearrowscanappearbetweennodesCArrowsorarrowlineswithoutnodesatthetailarenotallowedDArrowlinesshouldnotcross第31题Whentheplannedconstructionperiodequalsthecalculatedconstructionperiod,andthetotaltimedifferenceiszero,thefreetimedifferenceis().AGreaterthanzeroBMaybezeroCUnabletodetermineDMustbezero第32题AcertainjobhastwoimmediatetasksCandD.ThelatestcompletiontimeisC=18days,D=10days,andtheworkdurationisC=8days,D=2days.Therefore,thelatestcompletiontimeforthisjobis().A20daysB10daysC8daysD15days第33题IftheearlieststarttimesfortasksAandBare8

days

and7

days

respectively,andtheirdurationsare4

days

and6

days

respectively,thentheearlieststarttimefortheirjoint

immediateworkCis().A8daysB7daysC12daysD13days第34题Giventhattheimmediatefollow-uptasksforworkAareBandC,withdurationsof9,5,and3daysrespectively.TheearlieststarttimeforworkAisonthe8thday,andthelatestcompletiontimeforworkBandCisonthe26thand29thdaysrespectively,thetotaltimedifferenceforworkAis().A3daysB4daysC5daysD6days第35题Itisknownthatthefreetimedifferenceforacertainjobintheengineeringnetworkplanis5days,withatotaltimedifferenceof7days.Whenthesupervisingengineercheckstheprogress,itisfoundthatonlytheactualprogressoftheworkisdelayedandaffectstheconstructionperiodby3days,thentheactualp

温馨提示

  • 1. 本站所有资源如无特殊说明,都需要本地电脑安装OFFICE2007和PDF阅读器。图纸软件为CAD,CAXA,PROE,UG,SolidWorks等.压缩文件请下载最新的WinRAR软件解压。
  • 2. 本站的文档不包含任何第三方提供的附件图纸等,如果需要附件,请联系上传者。文件的所有权益归上传用户所有。
  • 3. 本站RAR压缩包中若带图纸,网页内容里面会有图纸预览,若没有图纸预览就没有图纸。
  • 4. 未经权益所有人同意不得将文件中的内容挪作商业或盈利用途。
  • 5. 人人文库网仅提供信息存储空间,仅对用户上传内容的表现方式做保护处理,对用户上传分享的文档内容本身不做任何修改或编辑,并不能对任何下载内容负责。
  • 6. 下载文件中如有侵权或不适当内容,请与我们联系,我们立即纠正。
  • 7. 本站不保证下载资源的准确性、安全性和完整性, 同时也不承担用户因使用这些下载资源对自己和他人造成任何形式的伤害或损失。

评论

0/150

提交评论