临平政工出【2022】5号年产6000万套穿戴式智能化产品项目吊篮专项施工方案(A类方案)年月日年月日年月日南通鑫宸机械租赁有限公司2024年01月临平政工出【20225号年产6000万套穿戴式智能化产品项目吊篮专项施工方案目录第一章编制依据.............................................1第二章工程概况.............................................22.1工程建设概况.....................................................22.2危大工程概况和特点...............................................32.3风险辨识与分级..................................................282.4施工地的气候特征和季节性天气....................................292.5施工平面及立面布置..............................................302.6施工要求........................................................372.7技术保证条件....................................................38第三章施工安排............................................383.1项目管理目标....................................................383.2各项资源供应方式................................................383.3施工流水段的划分及施工流程......................................393.4工程施工重点和难点分析及应对措施................................393.5新技术应用要求..................................................40第四章施工计划............................................414.1施工进度计划....................................................414.2施工准备计划....................................................414.3资源配置计划....................................................42第五章施工工艺流程和工艺要求..............................435.1方案及技术参数..................................................435.2工艺流程与方法..................................................455.3施工方法........................................................465.4操作要求........................................................535.5施工要点........................................................565.6检查要求........................................................605.7安全技术交底....................................................61第六章各项保证措施........................................641临平政工出【20225号年产6000万套穿戴式智能化产品项目吊篮专项施工方案6.1安全保证措施....................................................646.2质量保证措施....................................................706.3进度保证措施....................................................726.4绿色施工保证措施................................................726.5季节施工保证措施................................................736.6成品保护保证措施................................................736.7技术保证措施....................................................746.8监控检测措施....................................................92第七章施工管理及作业人员配备和分工.........................947.1施工管理.......................................................947.2施工管理人员....................................................967.3专职安全人员....................................................977.4特种作业人员....................................................977.5其他作业人员....................................................97第八章验收要求............................................988.1验收标准........................................................988.2验收程序........................................................988.3验收内容.......................................................1008.4验收人员.......................................................101第九章应急处置措施.......................................1019.1应急处置组织机构与职责.........................................1019.2应急事件及其应急措施...........................................1059.3救援医院信息...................................................1109.4应急物资准备...................................................111第十章计算书及相关图纸...................................11210.1计算书........................................................11210.2相关附件......................................................14610.3相关资质......................................................1502临平政工出【20225号年产6000万套穿戴式智能化产品项目吊篮专项施工方案第一章编制依据序号类别名称编号1中华人民共和国安全生产法(2021年)主席令第十三号2安全生产事故应急条例(2019国务院令第708号3建设工程安全生产管理条例(2003年)国务院令第393号5住房城乡建设部办公厅关于实施《危险性较大的分部分项工程安全管理规定》有关问题的通知建办质[2018]31号6《危险性较大的分部分项工程安全管理规定》住建部[2018]37号令7住房城乡建设部办公厅关于印发危险性较大的分部分项工程专项施工方案编制指南的通知建办质[2021]48号9《建筑施工脚手架安全技术统一标准》GB51210-201610《建筑结构可靠性设计统一标准》GB50068-201811《钢管脚手架扣件》GB15831-200612《建筑施工安全技术统一规范》GB50870-2013法律法规13《施工现场消防安全技术规范》GB50720-201114《混凝土结构工程施工规范》GB50666-201115《建筑结构荷载规范》GB50009-201216《混凝土结构设计规范》GB50010-201017《钢结构设计规范》GB50017-201718《钢丝绳夹使用方法》GB/T5976-200619《起重机钢丝绳保养、维护、安装、检验和报废》GB5972-201620《安全带国家标准》GB6095-202121《高处作业吊篮》GB/T19155-201722《施工脚手架通用规范》GB55023-202223《建筑施工扣件式钢管脚手架安全技术规范》JGJ130-201124《施工现场机械设备检查技术规范》JGJ160-201625《建筑施工安全检查标准》JGJ59-2011行业标准26《建筑施工工具式脚手架安全技术规范》JGJ202-201027《建筑施工高处作业安全技术规范》JGJ80-201628《施工现场临时用电安全技术规范》JGJ46-2005第1页共166页临平政工出【20225号年产6000万套穿戴式智能化产品项目吊篮专项施工方案序号类别名称编号29杭建工发(2015)/30《建筑施工高处作业吊篮安全管理技术规程》杭建监总[2010]45号31《关于加强建筑起重机械租赁、安装拆卸和使用安全管理的若干意见》杭建监总〔2010〕33号32地方文件《建筑施工高处作业吊篮安全管理技术规程》杭建监总[2010]45号33《关于加强建筑起重机械租赁、安装拆卸和使用安全管理的若干意见》杭建监总〔2010〕33号34《关于加强非标吊篮管理的通知》杭质安协【2016】12号35杭建工发(2017)255/36地方标准《建筑施工高处作业吊篮安全技术规程》DBJ33/T1271-2022《现行建筑施工规范大全》37/《高处悬挂作业安全技术培训材料》38/《ZLP系列高处作业吊篮使用说明书》39/其他40临平政工出【20225号项目设计图纸/41临平政工出【20225号项目施工组织设计/42临平政工出【20225号项目施工合同/第二章工程概况2.1工程建设概况表2.1-1工程建设基本概况表序号项目内容工程名称临平政工出[2022]5号年产6000万套穿戴式智能化产品项目1方案名称3#4#6#楼高处作业吊篮专项施工方案2建设地点杭州市临平区星桥街道棋盘山路以南、印花坞路以东、郁桥路以西、博望街以北本项目包含1#~6#楼,本方案主要对、、6#楼,最高高度为44.950米;其中建筑层数7层,最大高度40.450米;建筑层数83建设规模层,最大高度44.9506#建筑层数9层,最大高度37.550米。用地面积47069平方米,本项目总建筑面积2;其中地上127086m2地下30659m2。幕墙面积:110840m。4施工范围3#厂房、厂房和6#员工宿舍楼的外墙幕墙施工需要采用高处作业吊篮作为登高措施。5外墙材料玻璃幕墙、铝板幕墙、铝合金窗、穿孔铝板铝合金组合窗、铝板雨棚、金属栏杆等第2页共166页临平政工出【20225号年产6000万套穿戴式智能化产品项目吊篮专项施工方案6结构形式钢筋混凝土框架剪力墙结构7建筑性质3#、楼为厂房,楼为宿舍楼2.2危大工程概况和特点2.2.1各参建主体单位序号单位名称1建设单位杭州临平新城科创发展有限公司2建筑设计单位浙江绿城建筑设计有限公司3监理单位浙江明康工程咨询有限公司4总包单位中建新疆建工集团)有限公司5使用单位上海探见智能家居有限公司6吊篮安拆单位南通鑫宸机械租赁有限公司7吊篮租赁单位南通鑫宸机械租赁有限公司8吊篮生产单位南通宇博建筑机械制造有限公司2.2.2吊篮概况本工程3#厂房、4#厂房、6#员工宿舍楼共计三栋建筑楼,外立面幕墙的施工采用高处作业吊篮,最大高度为44.950米。吊篮施工主要用于外墙幕墙施工。吊篮悬挂机构总共采用5种形式,分别为:标准架设形式、非标架设形式1(后拉钢丝绳固定式)、非标架设形式2(前座板后支架增高6.0m)、非标架设形式3(前座板后支架增高5.0m)、非标架设形式4(前挑尺寸1.9~2.1m)。其中非标架设形式3属于备选方案,可代替安装高度1层位置的非标架设形式1。本项目有玻璃幕墙,金属幕墙,玻璃规格最大尺寸1.7米宽*2.7米,重量,230㎏高,铝板最大规格2.4宽*2米长,重量为26㎏,型材重量为15.75公斤,以上材料是工序分开,材料不会同时在吊篮内施工。表2.2.2-1吊篮搭设详表搭设位置架设形式类别数量(台)总量(台)3#厂房楼标准、非标1、非标2344#厂房楼标准、非标133966#员工宿舍楼标准、非标1、非标4292.2.3场地及周边环境本工程主要位于杭州市临平区星桥街道棋盘山路以南、印花坞路以东、郁桥路以第3页共166页临平政工出【20225号年产6000万套穿戴式智能化产品项目吊篮专项施工方案西、博望街以北。车辆从博望街进入项目地块。项目道路已经硬化,满足吊篮车辆进入要求。为减少卸货空间对沿街立面的影响,卸货场地被安置在厂区施工建筑升降机或塔吊附近的为临时堆场,园区内的交通流畅有序。图2.2.3-1项目地理位置图2.2.3-2施工总平面图(包含道路、出入口、堆场、人货梯位置)第4页共166页临平政工出【20225号年产6000万套穿戴式智能化产品项目吊篮专项施工方案图2.2.3-4项目周边环境图2.2.3-4项目效果图2.2.4危大工程特点根据本工程建筑特点,项目重点难点位置安装分析及解决方案:3#、4#、6#楼共计4栋建筑楼外立面施工采用高处作业吊篮,主要搭设在屋顶或屋架层,屋面防水正在施工(为避免交叉施工,配重式位置再防水施工完成后搭设,无配置式可在防水施工前搭设),建筑幕墙位置立面基本平整无凹凸,3栋建筑相似,依3#为例说明。第5页共166页临平政工出【20225号年产6000万套穿戴式智能化产品项目吊篮专项施工方案3#楼南立面3#楼北立面第6页共166页临平政工出【20225号年产6000万套穿戴式智能化产品项目吊篮专项施工方案3#楼西立面3#楼东立面第7页共166页临平政工出【20225号年产6000万套穿戴式智能化产品项目吊篮专项施工方案3#楼剖立面第8页共166页临平政工出【20225号年产6000万套穿戴式智能化产品项目吊篮专项施工方案3#楼剖立面3#楼剖立面第9页共166页临平政工出【20225号年产6000万套穿戴式智能化产品项目吊篮专项施工方案8层平面图屋顶平面图第10页共166页临平政工出【20225号年产6000万套穿戴式智能化产品项目吊篮专项施工方案屋架平面图结构平面图第11页共166页临平政工出【20225号年产6000万套穿戴式智能化产品项目吊篮专项施工方案本项目三栋楼屋顶均为出屋面框架,结构梁出屋面高度4.5m(3#、4#楼)、4.0m(5#楼)、5.0m(3#4#楼局部露台)、9.5m(3#4#楼局部露台),完成面高出结构梁0.1m,防水层0.15m,结构梁400*800mm、400*900mm、300*900mm、300*800mm四种规格,混凝土采用C30。此处计划前支架采用座板安装在结构梁顶部,后端采用钢丝绳拉结方式固定在下一道梁或下方女儿墙内侧。为更方面施工,高度5m以下位置,计划前端座板安装结构梁上,后端增高搁置在大屋面上,此处架设形式作为备选方案,根据现场实际情况选用。具体详见非标架设形式1(后拉钢丝绳固定式)、非标架设形式3(前座板后支架增高5.0m)。屋顶大样图第12页共166页临平政工出【20225号年产6000万套穿戴式智能化产品项目吊篮专项施工方案局部露台位置大样图第13页共166页临平政工出【20225号年产6000万套穿戴式智能化产品项目吊篮专项施工方案局部露台位置大样图第14页共166页临平政工出【20225号年产6000万套穿戴式智能化产品项目吊篮专项施工方案非标架设形式(后拉钢丝绳固定式)非标架设形式(前座板后支架增高5.0m)第15页共166页临平政工出【20225号年产6000万套穿戴式智能化产品项目吊篮专项施工方案3#4#6#楼炮楼女儿墙高度≯1.0m,3#楼北立面靠西和4#楼东立面靠北位置女儿墙高度0.9m,这些区域可直接采用标准架设形式搭设。3#楼西北角,此处7层为露台,屋顶层有结构梁,结构400*900mm,结构边缘有800mm高、150mm宽女儿墙,此处吊篮计划采用前支架采用定制座板,安装在400-150=250mm宽的结构梁顶,后支架增高搁置在7层露台屋面上。6#楼局部炮楼位置,炮楼位于稍微向内,与现场结构女儿墙有一定空间,标准前挑尺寸范围不能满足使用要求,需要前挑尺寸加长。具体详见标准架设形式、非标架设形式2(前座板后支架增高6.0m)、非标架设形式4(前挑尺寸加长1.9~2.1m)。屋顶大样图第16页共166页临平政工出【20225号年产6000万套穿戴式智能化产品项目吊篮专项施工方案炮楼位置大样图露台位置局部平面图第17页共166页临平政工出【20225号年产6000万套穿戴式智能化产品项目吊篮专项施工方案炮楼位置局部平面图标准架设形式第18页共166页临平政工出【20225号年产6000万套穿戴式智能化产品项目吊篮专项施工方案非标架设形式(前座板后支架增高6.0)非标架设形式(前挑尺寸加长1.9~2.1m)建筑造型较宽,转角位置不宜施工位置需要增设悬臂平台,或者通过安装旋转矮支座的使用来满足现场施工条件(祥见下方可旋转矮支座详图)。3#楼4#楼logo位置、6#楼立面水平造型位置施工,需要多次微调吊点位置,先施工立面幕墙,再前移吊点施工造型幕墙或水平悬挑造型幕墙,施工原则:先里后外;造型施工原则:自上而下,减少前挑尺寸。第19页共166页临平政工出【20225号年产6000万套穿戴式智能化产品项目吊篮专项施工方案立面施工步骤图可旋转矮支座详图悬臂平台安装节点图施工区域6m范围内是警界区域,设置警界线。吊篮施工期间需有专人值班,避免第20页共166页临平政工出【20225号年产6000万套穿戴式智能化产品项目吊篮专项施工方案垂直交叉作业;五级及以上大风及雷电雨雪天气停止作业;施工期间吊篮支架体与屋面主体避雷系统用导体连接。非标悬挂机构(前小座板/后支座增高)安装方法步骤如下:1、前支架采用座板时,支架把标准支架换成小座板即可(座板采用70*4或80*4方管原厂加工),座板需要使用后置机械螺栓固定;2、连接后支架与调节杆(本工程增高高度3.5~6.0米,增高采用70方管套80方管),调整适当的高度后用螺栓固定;3、将后吊杆穿入后调节杆内;4、安装中吊杆:将中吊杆两端分别穿入前吊杆和后吊杆内;5、安装上支架:把上支架座板套在前吊杆上端,穿入螺栓固定;6、将吊耳安装在前吊杆头部,将拉杆体1、2、3安装好同时将加强钢丝绳放入上支架上部的滑轮槽内;7、将所有螺栓紧固结实;具体加固措施见详图。8、前梁外伸1.7m内时每个后支架安装20块配重块,25KG/块,500kg*2=1000kg;9、吊篮安装需进行加高,并按下图进行加固,加固用材料均采用50X50X4mm角钢(连接尽量使用螺丝加固,螺丝无法加固处,采用焊接进行加固)。10、其余同标准悬挂架安装方式一样。11、非标悬挂机构(后斜拉钢丝绳固定式)安装方法步骤如下:12、放样定位安装前支架小支托(座板),支架把标准支架换成小支托(原厂加工),小支托使用M16后置机械后扩孔锚栓固定(使用部位:屋面结构柱);13、连接前梁、中梁和后梁;14、安装上支架:把上支架座板套在前吊杆上端,穿入螺栓固定;15、将吊耳安装在前吊杆头部,将拉杆体1、2、3安装好同时将加强钢丝绳放入上支架上部的滑轮槽内;16、再次调整,安装吊紧钢丝绳并调整;17、将所有螺栓紧固结实;具体加固措施见详图。18、安装后垃架,安装拉结钢丝绳,成八字形对称布置,然后使用花篮螺栓调紧;19、安装二次保护钢丝绳,此钢丝绳不需要拉近,需要松弛,用于拉结钢丝绳及相关位置失效后起到二次拉结作用,防止吊篮悬挂机构倾覆。20、其他加工件、安装节点和措施图第21页共166页临平政工出【20225号年产6000万套穿戴式智能化产品项目吊篮专项施工方案第22页共166页临平政工出【20225号年产6000万套穿戴式智能化产品项目吊篮专项施工方案第23页共166页临平政工出【20225号年产6000万套穿戴式智能化产品项目吊篮专项施工方案第24页共166页临平政工出【20225号年产6000万套穿戴式智能化产品项目吊篮专项施工方案第25页共166页临平政工出【20225号年产6000万套穿戴式智能化产品项目吊篮专项施工方案21121-12-2吊篮后支座加高立杆与配重架连接剖面图21121-12-2吊篮后支座加高立杆与转接套管连接剖面图21122-2
1-1吊篮转接套管与悬挂机构调节杆架连接剖面图第26页共166页临平政工出【20225号年产6000万套穿戴式智能化产品项目吊篮专项施工方案第27页共166页临平政工出【20225号年产6000万套穿戴式智能化产品项目吊篮专项施工方案2.3风险辨识与分级序号风险评价作业活动/危险源危害直接经验场所判断是否不可接受与危险源有关的法律法规风险控制策划1吊篮作业挑梁零部件不齐全、连接不牢靠;结构有开焊、变形、裂纹、破损、严重疲劳操作平台倾覆√《建筑施工高处作业安全技术规范》、《高处作业吊篮》制订健康安全目标和管理方案、执行《运行控制程序》2吊篮作业前梁的外伸长度,两根挑梁之间的距离不符合说明书规定;设备坠落√《建筑施工高处作业安全技术规范》、《高处作业吊篮》制订健康安全目标和管理方案、执行《运行控制程序》3吊篮作业配重块数量、重量不符合说明书规定;码放不整齐,无防止位移、稳定措施主结构有破损、焊设备坠落√《建筑施工高处作业安全技术规范》、《高处作业吊篮》制订健康安全目标和管理方案、执行《运行控制程序》4吊篮作业缝开裂、严重锈蚀;螺栓或铆钉松动;平台自动连接长度不符合说明书规定设备坠落√《建筑施工高处作业安全技术规范》、《高处作业吊篮》制订健康安全目标和管理方案、执行《运行控制程序》安全防护不齐全、《建筑施工高处作业未设置腹杆;安全安全技术规范》、制订健康安全5吊篮作业护栏的高度在建筑物一侧面小于,高处坠落√《高处作业吊篮》目标和管理方案、执行《运其余三面小于行控制程序》1.1m;平台底板不完整,《建筑施工高处作业制订健康安全6吊篮作业无防滑措施;无排水孔;平台四周无高处坠落√安全技术规范》、《高处作业吊篮》目标和管理方案、执行《运挡板;行控制程序》安全锁未在检测有效期内;在锁绳站台下,安全锁自动复位:1)离心式安全锁:当吊篮平台7吊篮作业下滑速度大于25m/min时,安全锁无法在超过100mm距离内自动锁住悬吊平台的钢丝绳;2)摆臂式安全锁:在工作时,吊篮平台纵向倾斜角度大于°,不符合说操作平台倾覆√《建筑施工高处作业安全技术规范》、《高处作业吊篮》制订健康安全目标和管理方案、执行《运行控制程序》第28页共166页临平政工出【20225号年产6000万套穿戴式智能化产品项目吊篮专项施工方案序号风险评价作业活动/危险源危害直接经验场所判断是否不可接受与危险源有关的法律法规风险控制策划明书规定所使用钢丝绳不《建筑施工高处作业8吊篮作业符合规定;有扭结、压扁、弯折、断丝、断股、断芯、笼状畸变等变形;设备坠落√安全技术规范》、《高处作业吊篮》制订健康安全目标和管理方案、执行《运行控制程序》安全钢丝绳无独立《建筑施工高处作业于工作钢丝绳另行安全技术规范》、悬挂,钢丝绳的规《高处作业吊篮》制订健康安全9吊篮作业格、型号不符合说明书规定;保险绳设备倾覆√目标和管理方案、执行《运未独立设置,其直行控制程序》径应大于16mm,并配备安全卡上、下限位装置,《建筑施工高处作业制订健康安全10吊篮作业报警信号装置安装位置不符合说明书设备坠落√安全技术规范》、《高处作业吊篮》目标和管理方案、执行《运规定行控制程序》11吊篮作业在紧急状态下无法切断主电源的急停按钮高处坠落√《建筑施工高处作业安全技术规范》、《高处作业吊篮》制订健康安全目标和管理方案、执行《运行控制程序》12吊篮作业供电未采用三相五线制,接零、接地未采用黄绿相接线触电事故√《施工现场临时用电安全技术规范》绩效监视和测量等13吊篮作业无可靠的接地,未做接地检测;配电箱外壳的未做绝缘电气控制部分应有触电事故√《建筑施工升降机安装、使用、拆卸安全技术规程》制订健康安全目标和管理方案、执行《运行控制程序》防水防振、防尘措物体制订健康安全14吊篮作业施,电控柜门装锁;主电源控制回打击、√《建筑机械使用安全技术规程》目标和管理方案、执行《运路应独立于各控制坍塌行控制程序》电路;2.4施工地的气候特征和季节性天气杭州气候:亚热带季风气候。四季分明,雨量充沛。全年平均气温17.8℃,平均相对湿度70.3%,年降水量1454毫米,年日照时数1765小时。夏季气候炎热,湿润,是新四大火炉之一。相反,冬季寒冷,干燥。春秋两季气候宜人,是观光旅游的黄金季节。第29页共166页临平政工出【20225号年产6000万套穿戴式智能化产品项目吊篮专项施工方案杭州地处长江三角洲南沿和钱塘江流域,地形复杂多样。杭州市西部属浙西丘陵区,主干山脉有天目山等。东部属浙北平原,地势低平,河网密布,湖泊密布,物产丰富,具有江南水乡特征。2.5施工平面及立面布置1、平面布置图第30页共166页临平政工出【20225号年产6000万套穿戴式智能化产品项目吊篮专项施工方案第31页共166页临平政工出【20225号年产6000万套穿戴式智能化产品项目吊篮专项施工方案2、立面布置图第32页共166页临平政工出【20225号年产6000万套穿戴式智能化产品项目吊篮专项施工方案3、吊篮部署预计此项目安装ZLP-630型电动吊篮机位数量为96台次,吊篮平面布置图详见附图。说明:安装方式出现有括号时代表吊篮两个悬臂为两种架设形式,其他说明吊篮两个悬臂均为同一种架设形式,同一机位出现先后顺序架设不一样时,按最多材料的架设形式标示。相似建筑标高按最大建筑的标高描述。表2.5-1吊篮配置表3#楼屋顶布置台吊篮机位移位施工,依图纸方位说明编号位置长度(m)安装方式安装楼层高度悬挂机构尺寸配重备注1号东立面6非标140.4501.5m/1.5m0+0kg2号东立面6非标140.4501.3m/1.5m0+0kg3号东立面6标准(非标1)40.4501.7m/4.4m(1.3m/1.5m)500+0kg4号东立面6非标140.4501.3m/1.5m0+0kg5号东立面4非标140.4501.3m/1.5m0+0kg6号东立面4.5+1.2非标135.9501.3m/1.5m0+0kg7号南立面6非标135.9501.3m/1.5m0+0kg第33页共166页临平政工出【20225号年产6000万套穿戴式智能化产品项目吊篮专项施工方案8号南立面6非标135.9501.3m/1.5m0+0kg9号南立面4.5非标135.9501.3m/1.5m0+0kg10号南立面4.5+1.2非标135.9501.3m/1.5m0+0kg11号南立面6非标140.4501.3m/1.5m0+0kg12号南立面4.5非标140.4501.3m/1.5m0+0kg13号南立面5非标140.4501.3m/1.5m0+0kg14号南立面5.5非标140.4501.3m/1.5m0+0kg15号南立面4非标140.4501.3m/1.5m0+0kg16号南立面6非标140.4501.3m/1.5m0+0kg17号南立面4.5+1.2非标140.4501.3m/1.5m0+0kg18号南立面6非标140.4501.3m/1.5m0+0kg19号南立面6非标140.4501.3m/1.5m0+0kg20号南立面4.5+1.2非标140.4501.5m/1.5m0+0kg21号西立面4.5非标140.4501.5m/1.5m0+0kg22号西立面6非标140.4501.5m/1.5m0+0kg23号西立面6非标140.4501.5m/1.5m0+0kg24号西立面4.5+1.2非标140.4501.5m/1.5m0+0kg25号西立面6标准40.4501.7m/4.4m500+500kg26号西立面5非标140.4501.3m/1.5m0+0kg27号西立面6非标235.9501.7m/4.4m500+500kg28号北立面4.5+1.2非标235.9501.7m/4.4m500+500kg29号北立面6标准35.9501.7m/4.4m500+500kg30号北立面5标准35.9501.7m/4.4m500+500kg31号北立面3.5标准35.9501.7m/4.4m500+500kg32号北立面3.5非标140.4501.3m/1.5m0+0kg33号北立面6非标140.4501.5m/1.5m0+0kg34号北立面4.5+1.2非标140.4501.5m/1.5m0+0kg4#楼屋顶布置台吊篮机位移位施工,依图纸方位说明编号位置长度(m)安装楼层高度安装方式悬挂机构尺寸配重备注1号南立面6非标144.9501.5m/1.5m0+0kg第34页共166页临平政工出【20225号年产6000万套穿戴式智能化产品项目吊篮专项施工方案2号南立面6非标144.9501.3m/1.5m0+0kg3号南立面6标准(非标1)44.9501.7m/4.4m(1.3m/1.5m)500+0kg4号南立面6非标144.9501.3m/1.5m0+0kg5号南立面4非标144.9501.3m/1.5m0+0kg6号南立面4.5+1.2非标140.4501.3m/1.5m0+0kg7号西立面6非标140.4501.3m/1.5m0+0kg8号西立面6非标140.4501.3m/1.5m0+0kg9号西立面4.5非标140.4501.3m/1.5m0+0kg10号西立面4.5+1.2非标140.4501.3m/1.5m0+0kg11号西立面6非标144.9501.3m/1.5m0+0kg12号西立面4.5非标144.9501.3m/1.5m0+0kg13号西立面5非标144.9501.3m/1.5m0+0kg14号西立面5.5非标144.9501.3m/1.5m0+0kg15号西立面4.5非标144.9501.3m/1.5m0+0kg16号西立面6非标144.9501.3m/1.5m0+0kg17号西立面4.5+1.2非标144.9501.5m/1.5m0+0kg18号西立面4.5非标144.9501.5m/1.5m0+0kg19号西立面6非标144.9501.5m/1.5m0+0kg20号西立面6非标144.9501.5m/1.5m0+0kg21号北立面4.5+1.2非标144.9501.5m/1.5m0+0kg22号北立面6非标144.9501.3m/1.5m0+0kg23号北立面6非标144.9501.3m/1.5m0+0kg24号北立面6标准44.9501.7m/4.4m500+500kg25号北立面5非标144.9501.3m/1.5m0+0kg26号北立面6标准40.4501.7m/4.4m500+500kg27号东立面4.5+1.2标准40.4501.7m/4.4m500+500kg28号东立面6标准40.4501.7m/4.4m500+500kg29号东立面6标准40.4501.7m/4.4m500+500kg30号东立面4标准40.4501.7m/4.4m500+500kg31号东立面3.5非标144.9501.3m/1.5m0+0kg第35页共166页临平政工出【20225号年产6000万套穿戴式智能化产品项目吊篮专项施工方案32号东立面6非标144.9501.5m/1.5m0+0kg33号东立面4.5+1.2非标144.9501.5m/1.5m0+0kg6#楼屋顶布置台吊篮机位移位施工,依图纸方位说明编号位置长度(m)安装方式安装楼层高度悬挂机构尺寸配重备注1号南立面4.5+1.2非标137.5501.5m/1.5m0+0kg2号南立面6非标137.5501.5m/1.5m0+0kg3号南立面3.5非标137.5501.5m/1.5m0+0kg4号南立面6非标137.5501.5m/1.5m0+0kg5号南立面4.5+1.2非标137.5501.5m/1.5m0+0kg6号西立面6非标137.5501.5m/1.5m0+0kg7号西立面6非标137.5501.5m/1.5m0+0kg8号西立面6非标137.5501.5m/1.5m0+0kg9号西立面6非标137.5501.5m/1.5m0+0kg10号西立面6非标137.5501.5m/1.5m0+0kg11号西立面3非标137.5501.5m/1.5m0+0kg12号北立面4.5+1.2非标137.5501.5m/1.5m0+0kg13号北立面6非标137.5501.5m/1.5m0+0kg14号北立面3非标137.5501.5m/1.5m0+0kg15号北立面6非标137.5501.5m/1.5m0+0kg16号北立面4.5+1.2非标137.5501.5m/1.5m0+0kg17号东立面6非标137.5501.5m/1.5m0+0kg18号东立面5.5非标137.5501.5m/1.5m0+0kg19号东立面4.5+1.2非标137.5501.5m/1.5m0+0kg20号东立面6非标137.5501.5m/1.5m0+0kg非标1(非标4)37.5501.5m/1.5m(2.1m/4.4m)21号东立面60+650kg22号东立面6非标137.5501.5m/1.5m0+0kg23号东立面6非标137.5501.5m/1.5m0+0kg24号东立面6非标137.5501.5m/1.5m0+0kg25号东立面6标准(非标4)37.5501.7m/4.4m(2.1m/4.4m)500+650kg第36页共166页临平政工出【20225号年产6000万套穿戴式智能化产品项目吊篮专项施工方案26号东立面6非标137.5501.5m/1.5m0+0kg27号东立面4.5+1.2非标137.5501.5m/1.5m0+0kg28号东立面5.5非标137.5501.5m/1.5m0+0kg29号东立面6非标137.5501.5m/1.5m0+0kg2.6施工要求1、吊篮的设计力求做到结构安全可靠,造价经济合理。2、确保吊篮在使用周期内安全、稳定、牢靠。3、吊篮在搭设及拆除过程中要符合工程施工进度要求。操作人员需取得特殊作业人员资格上岗证。4、吊篮主要用于幕墙安装,吊篮不得用以幕墙材料的垂直运输,吊篮施工过程中悬挂限载标志,明确两个人操作,携带工具每人小于25公斤。5、吊篮租赁安装单位派技术人员负责现场指导安装,由承租使用方负责协调配合搬运设备配件,吊篮安装单位有资质的人员负责安装和拆卸作业,在地面5米范围,应设置警戒区,施工单位指派专人负责统一指挥和监督,禁止无关人员进入。6、现场材料的堆放与搬运:吊篮进场后统一安放在空旷处,整理之后有塔吊或施工电梯运到吊篮安装位置。7、对于吊篮平台在施工时注意采用橡胶软保护,减缓平台与产品的碰撞保护成品。8、安装及施工作业人员进行作业时,必须在建筑稳固可靠的地方挂好安全带并做好充分的放坠落措施,严禁超载与未做安全防护措施就进行施工作业。9、总承包单位应将使用分包单位纳入其安全管理范围,并严格执行《建筑施工高处作业吊篮安全技术规程》浙江省工程建设标准DBJ33/T1271-2022和建办质[2018]31号文的相关要求。10、评审要求《建筑施工高处作业吊篮安全技术规程》浙江省工程建设标准DBJ33/T1271-2022的3.0.4第3条“特殊安装形式和加设副篮的吊篮施工”需要组织技术论证;结合《高处作业吊篮安装、拆卸、使用技术规程》JB/T11699-2013的第4.4条“对于特殊的建筑结构和非标设计方案,吊篮安装、拆卸的专项施工方案需经过评审”;本项目非标吊篮属于特殊安装形式,需要编制方案并进行专家评审论证。11、设备要求根据“《建筑施工工具式脚手架安全技术规范》JGJ202-2010:5.4.4:高处作业第37页共166页临平政工出【20225号年产6000万套穿戴式智能化产品项目吊篮专项施工方案吊篮所用的构配件应是同一厂家的成品”的要求;本工程非标吊篮支臂、构配件应由原厂家生产,且应具有足够的增高连接强度,不得擅自加工或选用。2.7技术保证条件严格执行该《专项施工方案》1、安全:工作钢丝绳、安全钢丝绳、独立安全绳(含自锁器、安全带)三保险。工作钢丝绳插进电机中,用于提升吊篮用。安全钢丝绳插进安全锁中,安全锁在吊篮倾斜(3°—14°)时可自动锁住钢丝绳,防止吊篮侧翻。独立安全绳是工人安全带的挂点,施工人员在上吊篮时,必须戴好安全带,安全带的自锁器必须扣在独立安全绳上,以防止吊篮坠落时可保证施工人员的安全。2、施工设备:吊篮设备在出库前,必须检验:a、外观整洁;b、各部件无锈蚀、开焊、变形;c、安全锁摆臂灵敏、有效;d、限位板平直无变形,限位开关完整有效;e、提升机运转良好,性能可靠;满足以上条件后方可运往施工现场,投入的施工设备满足安装要求和进度保障;所有施工设备进场前保证其能正常使用外,还必须保证其安全可靠,性能稳定;现场配备有足够的易损件材料,必须有施工设备操作规程,严格管理;对机械进行保修、维修,保证施工设备充分满足施工需要。3、投入使用前必须经过空载试验、额载试验和超载试验。4、安全绳(安全生命绳)的安装:安全绳的安装必须独立于所对应的吊篮单独固定在屋面能满足承载要求的固定点上,并将其放置于悬吊平台中间部位。其中安全绳中间不得有破损、老化等情况。第三章施工安排3.1项目管理目标质量目标严格按照设计图纸及施工验收规范进行作业,每一分项工程都达到国家规定的合格验评标准,达到检测要求参数要求。年事故负伤频率控制在3‰以内;重大伤亡事故为零;杜绝高空坠落、物体打击、火灾、触电、中暑、中毒等事故;杜绝业主、社会相关方和员工的重大投诉;施工现场安全检查达到业主安全检查标安全文明施工目标准;粉尘、污水、噪声达到城市管理要求;安全教育:工人岗前三级教育率达到100%,特种工人持证上岗率达到;施工管理人员安全培训率达到100%;保险:依法实施工伤保险和劳动保护,所有在现场施工的施工人员买保险率达到;争创公司级安全文明工地;满足总包、业主要求,计划2024年01月20日吊篮进场安装,工期目标2024年06月日完成施工吊篮拆除,工期5个月,具体依项目进度为准。3.2各项资源供应方式表3.2-1劳务资源安排一览表第38页共166页临平政工出【20225号年产6000万套穿戴式智能化产品项目吊篮专项施工方案施工项目名称专业施工队名称资质要求开始施工时间建设工期分包方式分包商选择方式责任人吊篮租赁南通鑫宸机械租赁有限公司合格01月日150天专业分包项目选择公司批准储旭表3.2-2工程用大宗物资供应安排一览表物资名称租赁单位拟选供应商使用地点要求进场时间责任人ZLP630型吊篮上海探见智能家居有限公司南通鑫宸机械租赁有限公司杭州2024年01月储旭表3.2-3工程用原材料需要量计划序号材料名称规格需要量需要时间单位数量2024/01//责任人1吊篮ZLP630个9696//童文全3.3施工流水段的划分及施工流程本工程建筑楼共计布置96台吊篮机位移位施工。吊篮详细布置情况见附图(吊篮布置图)。施工流程:外落地脚手架—垂直运输—安装吊篮—吊篮使用—吊篮移位—吊篮使用—吊篮拆除—垂直运输—撤场吊篮组件可利用总包货运电梯和塔吊运至相关安装位置后才可安装吊篮,计划安装。注意电梯和塔吊拆除后使用室内电梯进行垂直运输。吊篮安装和拆卸作业时,在作业范围6m外设置警戒区,派专人负责统一指挥和监督,禁止无关人员进入。本项目初始安装,屋顶悬挂机构基本满铺布置,因建筑相对不高,平台采用隔台安装,安装位置使用完成,仅仅抽出钢丝绳,然后移位平台至相邻位置,钢丝绳穿入吊篮平台即可使用,移位方便快捷,减少成本。3.4工程施工重点和难点分析及应对措施序号重点和难点具体分析应对措施备注1操作人员违规使用吊篮操作人员违规使用吊篮,空中进出或者运输货物吊篮使用时吊篮公项目安全部安排专人负责吊篮安全管理,已经发现违规使用的操作人员立即清场司检查不及时,项项目每周一组织吊篮专项2检查、维修不及时目检查不及时,检检查,形成书面检查纪查问题不能及时整要,定人定时间整改到位改落实3安全绳较多,固定点不统一每台吊篮配备n条生命绳,需要选择多个固定点安全绳固定点全部选择出屋面烟道,设备基础、出屋面机房等第39页共166页临平政工出【20225号年产6000万套穿戴式智能化产品项目吊篮专项施工方案3.5新技术应用要求1、吊篮应用要求本项目幕墙外立面的施工采用高处作业吊篮,常规配重式吊篮要求配重必须安放到位,采用钢丝绳困扎,防脱放到,配重必须足重,满足倾覆力矩3倍的安全要求。本项目采用后拉钢丝绳固定式,属于无配重式,必须满足杭州地标的相关要求。如后端钢丝绳安全系数12倍的要求,后置锚栓直径不得小于16mm,后拉钢丝绳需要2根成八字形拉结(两侧对称),钢丝绳之间角度范围为15°~30°,钢丝绳与悬挂机构的夹角≮40°,钢丝绳下端安装位置高度不宜>5m,前支架小支托时高度不宜大于400mm,前挑尺寸不宜大于1.5m,后端拉结钢丝绳位置不宜<1.5m。同时还需增设一根钢丝绳作为二次保护措施使用2、吊篮选型计算此工程材料主要有玻璃幕墙、铝板幕墙等,材料运输工作依靠人货梯或塔吊等运输设备运至各个相应楼层,吊篮不作为垂直运输设备,只作为材料临时放置及辅助安装设备,所以按照实际施工需要计算出符合要求荷载的吊篮型号;其中判定吊篮型号的荷载为垂直竖向荷载(既活荷载)包括:操作人员、施工工具、施工材料的重量计算如下:经施工图比对后吊篮上安排2名工人辅助安装。荷载计算:内部荷载=辅助材料重量+工人体重+工具重量=100kg+160kg+40kg=300kg(最大运输辅材时)≤300kg(平台最大额定起重量)材料计算:工人体重≈80×2=160Kg(按平均一人80Kg计算)工具重量≤40Kg根据其第6.3.2及6.3.3条规定:可将提升机构的极限工作载荷进行降级,因此本项目中提升机ZDT63的极限工作载荷规定为500kg,即ZLP630型吊篮额定载荷为500kg(500kg×2-480kg=520kg取整数规定为500kg),安全载荷应控制在额定载荷的80%,即500kg×0.8约为400Kg≥300kg,符合承载要求。为安全计适当减少安全载荷,本项目规定为300kg。故此工程使用ZLP630型吊篮。安全荷载内允许放置材料的最大重量=300kg-80kg×2-40kg=100kg,严禁超载。临第40页共166页临平政工出【20225号年产6000万套穿戴式智能化产品项目吊篮专项施工方案时材料的单件玻璃重量30kg,每次最大放置3块,合计90kg,满足安全使用。第四章施工计划4.1施工进度计划1、工期目标跟随幕墙工程施工计划进度,将于2024年月份开始搭设吊篮;将于2024年06月份开始拆除吊篮。吊篮具体进度计划搭设位置吊篮机位数安装(开始)时间拆除(结束)时间3#楼342024年01月日2024年06月日4#楼332024年01月日2024年06月日6#楼292024年01月日2024年06月日4.2施工准备计划1、技术准备吊篮安装方案已经编制完成,并经监理审核批准;吊篮施工人员需为吊篮专业安装施工人员,并持证上岗;吊篮操作人员必须经培训方可上岗操作;施工前应对施工人员进行安全和技术交底工作;已根据地方政府要求完成备案手续。2、现场准备现场场地已具备运输、安装条件。在吊篮进场时,在楼层内设置电箱,提供电源。在使用吊篮位置的结构上,应具备基本平整条件。若有其它杂物,应及时清理干净,以便于吊篮的安装或移动。吊篮租赁安装单位派技术人员负责现场指导安装,由承租使用方负责协调配合搬运设备配件,吊篮安装单位有资质的人员负责安装和拆卸作业,在地面5米范围设置警戒区,施工单位指派专人负责统一指挥和监督,禁止无关人员进入。材料搬运:水平搬运包括平台、绳坠铁、电器系统等;垂直搬运包括屋面悬挂装置、钢丝绳、配重块等。在实施水平及垂直搬运过程中,架体、配重等相关部件需在塔吊及室外升降电梯的配合下完成运输。在搬运过程中,需注意机械零部件的保护工作,防止零部件遗失。同时应对包括平台架、安全锁、主梁、支架、配重块等内容进行进场验第41页共166页临平政工出【20225号年产6000万套穿戴式智能化产品项目吊篮专项施工方案收。吊篮架设施工为屋面施工完毕,且在外架拆除完毕后,吊篮作业与屋面施工无交叉作业,施工前整理屋面安装面上的物品。3、进场准备必须符合《建筑施工工具式脚手架安全技术规范》、《高处作业吊篮》等规范要求;吊篮进场时,吊篮租赁单位应提供产品合格证及使用说明书,吊篮所用的构配件应是同一厂家的产品。总承包单位应组织监理机构对进场的安全绳、安全锁、配重块、电器系统、悬挂结构、钢丝绳、安全带、提升机、悬吊平台等吊篮构件的有效日期进行验收,不合格的产品不得入场。4.3资源配置计划4.3.1劳动力配置计划序号工种人数进场时间服务单位1特种安拆人员52024年01月日吊篮安拆单位2电工12024年01月日吊篮安拆单位3劳务若干2024年01月日吊篮安拆单位4操作人员若干2024年01月日吊篮使用单位4.3.2材料与设备计划名称型号数量备注提升机LTD6302个台
安全锁LSB30(LSG20)2把台电控箱YEJ90L-4F381个台架设高度吊篮平台Q235A钢制成1套台
低于100行程开关LX-K1/4112个台底长度最大5.5米,架设电缆电缆重型橡胶软电缆1根台安全绳锦纶安全绳(Φ16mm)1根台钢丝绳4x31WS+PP-2160-8.34根台最大高度低于60米,篮底长度不超过自锁器新型自锁器(Φ16-20)1个台米。吊篮悬挂机构Q235B钢制成2副台配重水泥制40块台(标准)4.3.3机械设备配置计划序号机具、设备名称规格型号数量进场时间出场日期责任人1升降机电梯SC200/200(6#楼)12023.11.152024.7.26第42页共166页临平政工出【20225号年产6000万套穿戴式智能化产品项目吊篮专项施工方案2室内电梯/2//3汽车吊50t1//4电焊机BX1-315A2//4.3.4计量设备配置计划名称型号数量进场时间备注安全带由使用方自行配置(建议使用坐式安全带)2024年01月日力矩扳手东工(22mm、24mm)1把2024年01月日力矩扳手威达(300mm)1把2024年01月日胶管10mm厚1500米2024年01月日软保护风速仪由使用方自行配置2024年01月日接地电阻摇表现场共用2024年01月日绝缘电阻摇表现场共用2024年01月日第五章施工工艺流程和工艺要求5.1方案及技术参数5.1.1吊篮布置情况该工程布置吊篮96台吊篮机位,实际也可根据工程进度需求通过悬架满铺平台移位吊篮完成,具体使用台数根据工程施工进度与要求进行调整,详细布置情况见附图《吊篮平面布置图》《屋顶层吊篮架设方案图》。(使用吊篮台数及长度根据工程实际情况和进度安排决定)5.1.2施工用吊篮型号及说明施工中使用的ZLP630型吊篮技术参数介绍如下:生产厂家:南通宇博建筑机械制造有限公司(产品商标:宇博)1、ZLP630型吊篮型号型号ZLP长度1.5m-6m(标准节分为1.0m1.5m/2m三种)ZLP630型号吊篮组成部件:LTD6.3提升机2台LSB30安全锁2把电控箱1套第43页共166页临平政工出【20225号年产6000万套穿戴式智能化产品项目吊篮专项施工方案屋顶吊架2付工作平台1套直径8.3mm钢丝绳4根电缆线1条安全绳1条自锁器1个COB1手控手柄1个配重块(25Kg)40块2、主要技术参数ZLP630型吊篮主要技术参数额定载重量:630施工安全载重量:本项目300kg提升速度:9~11m/min)最大提升高度:100m工作平台尺寸:长6m/宽0.7m/高1.195m前吊杆伸出长度:1.1m~1.7m支架调节高度范围:1.44m~2.14m配重块总重量:2××25=1000Kg提升机额定提升力:6.17KN提升机功率:1.5KW提升机制动力矩:15Nm钢丝绳结构:4×31SW+Fc—钢丝绳破断力:51KN安全锁锁绳角度:≤14°3、吊篮正常工作环境环境温度-15oC~+40oC环境相对湿度<90%(25oC)电源电压偏离额定值±5%工作处阵风风力<8.3m/s(相当于5级风力)4、说明书内技术参数截图第44页共166页临平政工出【20225号年产6000万套穿戴式智能化产品项目吊篮专项施工方案5.2工艺流程与方法第45页共166页临平政工出【20225号年产6000万套穿戴式智能化产品项目吊篮专项施工方案工地勘察架设方案检测认可进场时现场负责采取措施禁止闲人入内现场部件搬运到
位组装吊篮悬挂平台安装悬挂安装安全锁提升机安装非标悬挂机构安装电器箱安装非标悬挂机构的固定保护装置安装上限位挡块垂放电缆冲击测试钢丝绳端部固定穿钢丝绳连接电源接电模式升降试验试运行操作说明移交手续5.3施工方法吊篮安装严格按照本公司的《ZLP系列高处作业吊篮使用说明书》、《安全操作规程》以及安装工艺流程进行施工1、安装步骤悬挂机构配重块钢丝绳安全锁提升机悬挂平台穿钢丝绳,平台正位电器箱限位块2、悬挂机构的安装1)调节悬挂支架的前伸缩架,使前梁下侧面高于女儿墙(或其它障碍物)高度,第46页共166页临平政工出【20225号年产6000万套穿戴式智能化产品项目吊篮专项施工方案在可能的情况下,在悬挂机构定位后,在前梁伸出端下侧面与女儿墙间加垫木块固定。前梁伸出端悬伸长度ZLP630型为1.3米,前后支架间距离取4.6米,最大安全载重300kg。前梁伸出端悬伸长度为1.7米,前后支架间距离取4.4米,最大安全载重300kg现场必须做好限载措施。具体关系参数见下表。ZLP630型吊篮安装高度、前梁伸出长度与最大安全载重量关系表安装高度m前梁伸出长度m前后支架间距m配重最大安全载重1.34.63001001.54.410003001.74.43002)张紧加强钢丝绳时,使前梁略微上翘3-5厘米,产生预应力,提高前梁刚度。3)装夹钢丝绳时,①绳夹的数量是4个,U形开口在钢丝绳尾端对侧,且方向对齐。绳夹应从吊装点处开始依次夹紧,并在最后一个绳夹和前一个绳夹间,使钢丝绳有少许拱起。②使用金属压件详见下图:4)垂放钢丝绳时,将钢丝绳自由盘放在楼台面,将绳头仔细抽出后沿墙而缓慢向下滑入,钢丝绳放完后应将缠结的绳小心分开压住,地面多余的钢丝绳仔细盘好扎紧。5)悬挂支架定位后,带前后座脚轮的用插销固定。6)配重块每块25公斤,将配重块均衡套置于后座的四根配重块安装杆上。配重第47页共166页临平政工出【20225号年产6000万套穿戴式智能化产品项目吊篮专项施工方案块数量根据前梁悬伸长度、前后座间距离和悬吊载荷验算确定。7)吊篮每月须由吊篮专业维保人员进行一次检查和维护,以确保使用安全。3、悬吊平台的安装:悬吊平台的安装顺序:低栏杆低栏杆低栏杆提升机安装架(两端)高栏杆高栏杆高栏杆4、悬吊平台的安装、调整:1)选择平整的地坪做安装面。2)用底架、高、低栏杆分别把基本节组装并初步连接好,调整高、低栏杆,使它们保持在一条直线上。3)安装两端提升机安装架使安全锁支板朝向平台外侧。4)装成后均匀紧固全部连接螺栓。5)在低栏杆一侧的中部横杆的适当位置装好靠墙支撑轮。5、安全锁及提升机的安装:1)安全锁和提升机分别安装于悬吊平台两端提升机安装架上的安全锁支架和提升机支承中,安全锁安装时使摆臂滚轮朝向平台内侧。2)提升机安装于悬吊平台内,安装时将提升机搬运至悬吊平台内,使提升机背面的矩形凹框对准提升机支承,插入销轴并用锁销锁定后,在提升机箱体上端用二只连接螺栓将提升机固定在提升机安装架的横框上,也可以在通电后,在悬吊平台外将工作钢丝绳穿入提升机内,并点动上升按钮将提升机吊入悬吊平台内进行安装。采用后一种方法安装时,须将提升机出绳口处稳妥垫空,并在钢丝绳露出出绳口时用手小心将绳引出,防止钢丝绳头部冲击地面受损。6、电控箱安装于悬吊平台中间部位的高栏杆上,电箱门朝向悬吊平台内侧,再将电控箱固定在栏杆的方管上。电控箱安装固定后,将电源电缆、电机电缆、操纵开关电缆的接插头插入电箱下端的相应插座中。7、通电、检查1)电源是否380V电源,电源电缆接出是否可靠固定。第48页共166页临平政工出【20225号年产6000万套穿戴式智能化产品项目吊篮专项施工方案2)顶面悬挂机构安放平稳,固定可靠连接螺栓无松动,平衡配重块固定可靠。3)钢丝绳连接处的绳口装夹正确,螺母拧紧可靠。4)悬垂钢丝绳应分开,无打结、缠绕和折弯。5)提升机、安全锁及悬吊平台安装正确。连接可靠连接螺栓无松动或虚紧,连接处构件无变形或开裂现象。6)电缆接插件接插正确无松动,保险锁扣可靠锁紧。7)建筑施工立面上无明显凸出物或其它障碍物。通电后检查及要求:8)闭合电箱内开关,电气系统通电。9)将转换开关置于左位置,分别点动操纵开关的上升和下降按钮,左提升机电机正反运转。10)将转换开关置于中间位置,分别点动操纵开关的上升和下降按钮,左、右提升机电机同时正反运转。11)将转换开关置于中间位置,启动左右提升机后,按下电箱门上紧停按钮(红色),电机停止运转。旋动紧停按钮使其复位后,可继续启动。12)将转换开关置于中间位置,启动左右提升机后,分别按下各行程开关触头时电机应停止运转。放开触头后,可继续启动。8、穿工作钢丝绳穿工作钢丝绳:位于悬挂机构前端内侧位置的二根钢丝绳是工作钢丝绳,穿入提升机机内。1)将钢丝绳穿入端穿过安全锁摆臂上的滚轮槽后,插入提升机上端进绳口,至插不进时将钢丝绳略为提起后用力下插,使钢丝绳插紧后提升机内。2)转动转换开关并按下相应的上升按钮,使钢丝绳平衡地自动穿绕于提升机的转动盘上。3)将穿出的钢丝绳通过提升机支架下端,垂直引放到悬吊平台外侧,并盘放好。4)两端提升机分别穿绳至钢丝绳拉紧时即刻停止,然后将转换开关转至中间位置,点动上升按钮,同时拉住悬吊平台两端,使其在自重作用下平衡处于悬吊状态,防止悬吊平台离开地面时与墙面或其他物体撞击。待悬吊平台离地面20-30厘米时停止上升,并检查悬吊平台是否处于水平状态,如有倾斜,可将转换开关转至低端检查,并点动上升按钮,使悬吊平台低端提升机直至处于水平位置。第49页共166页临平政工出【20225号年产6000万套穿戴式智能化产品项目吊篮专项施工方案9、穿安全钢丝绳将位于悬挂机构前梁端头外侧的钢丝绳,穿入安全锁内。穿绳时先将安全锁摆臂向上抬起,再将钢丝绳穿入端插入安全锁上方的进绳口中,用手推进,自由通过安全锁后,从安全锁下方的出绳口将钢丝绳拉出,直至将钢丝绳拉紧。10、安装上限位装置:当工作吊篮上升时,装在安全锁上的限位开关碰触上限位块,可使吊篮停止上升,保障施工安全。11、重锤是固定在安全钢丝绳下端用来拉紧和稳定钢丝绳,防止悬吊平台在提升机将钢丝绳随同拉起而影响悬吊平台正常运行。安装时,将二个半片夹在钢丝绳下端离开地面约5-6厘米,然后用螺栓紧固于钢丝绳上。12、验收、交接安装完毕后,组织有关人员进行检查,并填写《电动吊篮安装交接表》,由使用单位项目负责人签字后方可投入使用。13、安全大绳及自锁器的安装安全大绳在楼顶的攀挂点必须牢固,切不可将安全大绳攀挂悬挂机构上面,顶部挂完后安全大绳放置于吊篮的中间,自锁器直接安装在安全大绳上面。注意:自锁器不得装反。14、吊篮的拆除措施1)吊篮拆卸程序(1)拆卸前必须把吊篮平台下降至地面或者施工最低点,并确认钢丝绳完全没有受力,处于放松状态;(2)开动左右提升机继续向下,抽出2根工作钢丝绳。并把左右安全锁中的安全钢丝绳抽出,之后切断吊篮电源。(3)悬挂机构拆除步骤如下:①从吊篮上支架处把工作钢丝绳和安全钢丝绳以及电缆线和安全绳逐一抽上去;②拆除钢丝绳固定点的卡扣,并将钢丝绳、电缆线及安全绳盘好并固定;③将悬挂机构吊臂后移至安全范围,松掉固定螺栓的螺母,将拉勾旋转放松后,拆除前臂前端拉杆体及后臂后端拉杆体,再拆除上支架;④将后支架、后臂、中臂、前支架、前臂拆除螺栓后依次向后退出。(4)工作平台拆除步骤如下:①拆除左右两端提升机及行程开关的航空插头,将电源线缠绕整齐;第50页共166页临平政工出【20225号年产6000万套穿戴式智能化产品项目吊篮专项施工方案②拆除左右两端提升机与提升机安装架的固定螺栓,把左右提升机卸下后再拆除提升机安装架;③拆除左右端板固定螺栓后依次拆除前、后护栏。2)拆除吊篮时操作要点及注意事项(1)禁止工作平台悬空时,拆除悬挂机构部件;(2)禁止先拆除固定处卡口及配重后抽出工作钢丝绳及安全钢丝绳;(3)拆除步骤应按照先拆除悬挂机构后拆除工作平台的程序进行;(4)拆除支架螺栓的步骤应按照安装时相反的步骤进行。3)吊篮拆卸作业流程示意图进场时派专人负责采取措施禁止行人入内(吊篮停放平稳)切断总电源分离控制箱与电源电缆收尽电源电缆移除配重块、拆除钢丝绳拆除生命绳
拆除安全抽出钢丝绳锁、提升机、电器箱拆除悬挂机构部分吊篮平台解体零部件整理退场15、安装结束后的检查与调整(运转调试)1)启动电源,上下运动吊篮3~5次,每次的升高高度约为5米,再检查各连接点的安装情况。2)将转换开关打向一侧,启动上下开关,当工作平台倾斜时调试安全锁的锁绳状况。3)启动上下开关让平台上升,用手触压上限位,调试上限位的距离及灵敏度。4)在调试运行检查时应符合以下要求:(1)各连
温馨提示
- 1. 本站所有资源如无特殊说明,都需要本地电脑安装OFFICE2007和PDF阅读器。图纸软件为CAD,CAXA,PROE,UG,SolidWorks等.压缩文件请下载最新的WinRAR软件解压。
- 2. 本站的文档不包含任何第三方提供的附件图纸等,如果需要附件,请联系上传者。文件的所有权益归上传用户所有。
- 3. 本站RAR压缩包中若带图纸,网页内容里面会有图纸预览,若没有图纸预览就没有图纸。
- 4. 未经权益所有人同意不得将文件中的内容挪作商业或盈利用途。
- 5. 人人文库网仅提供信息存储空间,仅对用户上传内容的表现方式做保护处理,对用户上传分享的文档内容本身不做任何修改或编辑,并不能对任何下载内容负责。
- 6. 下载文件中如有侵权或不适当内容,请与我们联系,我们立即纠正。
- 7. 本站不保证下载资源的准确性、安全性和完整性, 同时也不承担用户因使用这些下载资源对自己和他人造成任何形式的伤害或损失。
最新文档
- 军事医院面试题目及答案
- 信贷管理基本制度
- 住院日清单制度
- 企业财务决策制度
- 产品服务流程制度
- 中国建造师制度
- 2026年盐津县公安局警务辅助人员招聘备考题库及答案详解参考
- 2025-2030中国脱油有机卵磷脂粉末市场营销策略与投资风险预警研究报告
- 2025至2030智慧农业技术应用分析及政策扶持与市场拓展研究报告
- 固态电池专利布局分析及车企战略投资与量产时间表
- 短险销售技巧培训课件
- 山东省济南市2024-2025学年高二上学期1月期末考试英语含答案
- 2026云南省产品质量监督检验研究院招聘编制外人员2人笔试模拟试题及答案解析
- 制造部部门介绍
- 化工品物流枢纽项目运营管理方案
- 2025年新公开选拔中小学校长笔试试题与答案
- 丈夫家暴协议书模板
- 2026中国中药饮片智能煎煮设备市场培育与渠道建设报告
- 2025小学三年级英语上册期末测试卷(人教版)
- 2025年液压传动试题及 答案
- 2026年建筑装饰公司应收账款管理管理制度
评论
0/150
提交评论