1、PMP 考试用到的公式Budgeted Cost of Work Scheduled = BCWS = Planned Value = PV Budgeted Cost of Work Performed = BCWP = Earned Value = EV Actual Cost of Work Performed = ACWP = Actual Cost = AC Budget at Completion = BACEstimate at Completion = EACEstimate to Complete = ETCVariance at Completion = VACVarian
2、ce = Plan - ActualCost Variance CV = BCWP - ACWP = EV - ACSchedule Variance SV = BCWP - BCWS = EV - PVCost Performance Index CPI = BCWP / ACWP = EV / AC Schedule Performance Index SPI = BCWP / BCWS = EV / PVEstimate at Completion EAC = BAC / CPIEstimate to Completion ETC = EAC - ACWP Variance at Com
3、pletion VAC = BAC - EACCoQ = ( ( Review Efforts + Test Efforts + Training Efforts + Rework Efforts + Efforts of Prevention) / Total Efforts) x 100 %PERT =O + 4ML + P6MEAN - AverageMODE - The “ most found ” numberRANGE - Largest - Smallest Measure.MEDIUM - No in the middle or avg. of 2 middle NosSTD.
4、 DEV. OF TASKTASK VAR. = (P -O) 2= Std. Dev A 2CP STD. DEV. =2+c 2+c 2SIGMA 1= 68.262=95.463=99.736=99.99Channels of CommunicationCOMM =(N2 - N) / 2= (N x (N -1) /2P R O J E C T S E L E C T I O NPV = F V .(1+r)?FV = PV x (1+r)NPV = S ( PV + PV + PV + PV )(1+r)? (1+r)? (1+r)? (1+r)?Cash Flow = Cash I
5、nflow -Cash OutflowDiscounted Cash Flow = CF x Discount FactorARR = S Cash Flow / No. of YearsROI = (ARR / Investment) * 100 %BCR = Benefits / CostExp. Value = Probability %x Consequence $Class of EstimatesDefinitive+5%Capital Cost+10-15%Appropriation+15-25%Feasibility+25-35%Order of Magnitude +35%C
6、ontract IncentivesSavings = Target Cost -Actual CostBonus = Savings x PercentageContract Cost = Bonus + FeesTotal Cost = Actual Cost + Contract CostPV (Present Value) = BCWS (Budgeted Cost of Work Schedule)EV (Earned Value) = BCWP (Budgeted Cost of Work Performed)AC (Actual Cost) = ACWP (Actual Cost
7、 of Work Performed)CV=EV - ACCPI= EV / AC (efficiency)SV=EV - PVSPI= EV / PVETC =:BAC -EVor(BAC -EV)/ CPIEAC =AC + ETCEAC =BAC / CPIVAC =BAC - EAC% COMPLETE = EV / BAC x 100% SPENT = AC / BAC x 100SV%SV / PV x 100CV%= CV / EV x 100EASY REFERENCE TO PROJECT MANAGEMENT COST EQUA TIONSTheProject s Budg
8、et:PV:Planned Value (PreviouslyCalled BCWS:Budgeted Cost of WorkScheduled)Theplanned value is the project budgetthat is part portion of the approvedcost estimate that is planned to be spenton the activity during a givenperiod.TheProject s Actual Cost:AC:Actual Cost (PreviouslyCalled ACWP:Actual Cost
9、 of WorkPerformed)The actual cost that is thetotal of direct and indirect costs incurred in accomplishing work on theactivity during the given period.TheProject s Earned eV:aluEV:Earned Value (Previouslyand Interchangeably Called BCWP:Budgeted Cost of Work Performed)EV is the method for measuring pr
10、ojectperformance.Itcomparesthe amount of work planned with what was actually accomplishedtodetermine if cost and schedule performance is as planned.Theearned value, previously and interchangeably called the Budgeted Cost ofWork Performed (BCWP), is a percentage of the total budget equal to thework a
11、ctually performed.CostVariance:CV:Cost VarianceCV is any difference from the estimatedcost of an activity and the actual cost of that activity.In earnedvalue analysis, CV = EV -ACScheduleVariance:SV:Schedule VarianceSV is any difference from the between thescheduled completion of an activity and the
12、 actual completion of thatactivity.In earnedvalue analysis, SV = EV - PVCostPerformance Index:CPI:Cost Performance IndexCPI is the ratio of budget cost to actualcosts.In earned value analysis, CPI =(EV/AC)CumulativeCPI = (sum of all individual EV budgets / sum of all individual ACs)SchedulePerforman
13、ce Index:SPI:Schedule Performance IndexThe SPI is used in some application areasto forecast the project completion date.SPI = (EV/PV)(Sourcefor above equations:PMBOK? , Section 10.3.2.4, Publishedby the Project Management Institute (PMI), 2000 edition)Valuable Hints NOT Written in Project Management BooksAbout Costs(Ormore succinctly “ How to know you re in trouble ”)When EVis used in a cost variance equation, it always goes first:CV = EV -AC(ValuableHint:If you g
温馨提示
- 1. 本站所有资源如无特殊说明,都需要本地电脑安装OFFICE2007和PDF阅读器。图纸软件为CAD,CAXA,PROE,UG,SolidWorks等.压缩文件请下载最新的WinRAR软件解压。
- 2. 本站的文档不包含任何第三方提供的附件图纸等,如果需要附件,请联系上传者。文件的所有权益归上传用户所有。
- 3. 本站RAR压缩包中若带图纸,网页内容里面会有图纸预览,若没有图纸预览就没有图纸。
- 4. 未经权益所有人同意不得将文件中的内容挪作商业或盈利用途。
- 5. 人人文库网仅提供信息存储空间,仅对用户上传内容的表现方式做保护处理,对用户上传分享的文档内容本身不做任何修改或编辑,并不能对任何下载内容负责。
- 6. 下载文件中如有侵权或不适当内容,请与我们联系,我们立即纠正。
- 7. 本站不保证下载资源的准确性、安全性和完整性, 同时也不承担用户因使用这些下载资源对自己和他人造成任何形式的伤害或损失。
最新文档
- 2025年通信专业技术人员职业资格考试中级设备环境试题与答案
- 2025年人工智能公需课试题答案合集
- 2025年高级审计师资格考试精-选真题及答案
- 2025年河南省中小学教师招聘考试试题及答案详解
- 2026及未来5年中国松果饰品数据监测研究报告
- 2025年cpa注册会计师会计真题试卷含答案
- 2026浙江省卫生系统招聘考试(口腔医学)历年参考题库含答案详解2卷
- 2026浙商银行招聘考试(综合知识)历年参考题库含答案详解3卷
- 2026河南省医疗卫生系统招聘考试(面试)历年参考题库含答案详解3卷
- 2026河南机关事业单位工勤技能岗位等级考试(烹饪工·技师/二级)历年参考题库含答案详解2卷
- 新疆维吾尔自治区二级造价工程师考试模拟题库及答案:建设工程计量与计价实务、水利工程(2025年)
- 2025年高院遴选面试题及答案
- 公共视频全域协同系统建设方案
- 山东省济宁市邹城市第十中学2025-2026学年七年级上学期分班考试英语试题(含答案)
- DB37∕T 4825.3-2025 药品、医疗器械、化妆品企业日常监督检查管理规范 第3部分:日常监督检查
- 浙江省丽水市2024-2025学年高二下学期期末考试生物试卷
- GB/T 45232-2025建筑排水排污用聚丙烯(PP)管道系统
- 幼儿园学拼音基础篇单韵母教学课件
- 基础护理服务工作规范
- 科研办公楼经济效益与社会效益分析
- 《新编大学生军事理论与技能(第2版)》全套教学课件
评论
0/150
提交评论