1、一、 总则.General1、为了确保船舶的建造质量,检验船舶性能,保证试验顺利进行,特制定轮机部分大纲。本大纲参照“海船系泊及航行试验通则(GB/T 3471 -1995”制定。1. To determine the fabrication quality of the ship, examine the sea going performance of the ship and determine this trial carried out well, the mooring test and the sea trial of machinery part is intended. Th
2、is program refer to “DOCK AND SEA TRIAL PROGRAM OF THE VESSEL(GB/T 3471 -1995”.2、试验由船舶制造部门主持,并会同现场验船师、船舶使用部门和设计部门的人员参加。2.This test is taken charge by the ship manufacture department and ships operators and design department to attend on the scene jointly with the Surveyor.3、试验应在下列条件具备后进行:3. Test sha
3、ll be carried out in accordance with the following condition:3.1系泊试验前应由制造部门向验船部门和使用部门提供机电设备、船舶各系统材质及船用产品检验合格证件,制造过程中的各种试验证件及装船后的试验安装测量记录卡以便交验。3.1 Before the mooring test ,manufacturers should send to operators and class by approved certificates of machine electricity equipments, ships material , shi
4、ps and navigate product, all kinds of test document while manufacturing and the installation record card after shipment.3.2系泊试验和航行试验所使用的测试仪器和仪表应具有国家有关主管机构签发的有效合格证件。3.2 All kind of test instrumentation and gauges applicator during mooring test and sea trial should be provided with the efficiency appr
5、oved certificate checked by the supervisor organization of Nation.4、试验分为系泊试验和航行试验两个阶段进行,系泊试验应在船舶各项的工程安装完毕后进行。航行试验是在全船各项工程全部竣工,系泊试验合格,取得验船部门同意后方可进行。The test is divided into two parts: the mooring test and sea trial, the mooring test shall be run after completing installation of engine in the vessel.
6、The sea trial shall be carried out after completion of the vessel, check of the mooring test and class admitted.5、试验后由制造部门将各种试验记录、报告、结论及完工图纸送验船部门、船舶使用部门及设计部门存查。5. After test, manufacture department shall send various test record, report, conclusion and the complete diagram to class, operators and de
7、sign department file for reference.二、 系泊试验、Mooring test1、舵装置及舵机试验1. The test of rudder installation and steering engine1.1试验条件1.1 trial conditiona、舵机及操舵系统安装完好,舵机机械零位正确无误,操舵器与舵叶之间的指示误差应符合产品技术条件的要求;a. rudder engine and steering system are installed integrally and check the correctness of rudder engine
8、s zero ,the indication error between steering machine and rudder blade shall be complied with requirement of technical condition .b、液压系统的溢流阀、缓冲阀、程序阀等按图纸要求调试完毕;b. Flood valve ,cushion valve and order valve of hydraulic system shall be debug in accordance with the requirement of drawings.c、安全阀校验合格;c c
9、heck of safety valved、舵装置的报警系统,包括动力源失电、断相、过载、控制电源失电、油类失压、油柜低液位及自动偏舵等模拟试验合格。d. Check tests of rudder device alarm system, which included electric power source failure, phase failure overload, control power source lose, oil pressure failure, oil tank low level and autopilot by simulation.1.2试验内容及程序1.2
10、 Test content & programThe electro-hydraulic steering engine shall be run for not less than 30 min under no-load condition, and check it as follow:a、检查舵角指示器、操舵器与舵叶之间的误差,检查时自中间位置向两舷转舵,舵角每增加5°核对一次,其舵叶与舵角指示器之间的误差应不大于±1°,并作记录;a. Examine the error between the rudder angle indicator 、st
11、eering machine and the rudder blade, The rudder turn from amidship position to two shipboard when testing, Collate when the rudder angle increase each 5°, with the error between the rudder blade and the rudder angle indicator shall be not more than±1°, then record it.b、检查舵角电气限位器动作的正确性
12、,应能使舵叶转至左、右舷各35°处停止;机械限位器的安装位置为36.5°。b. check the correctness of rudder angle gas limiters, The rudder blade turn to port andstarboard 35°and stop ,installation location of mechanical rudders stops is 36.5°.pumps ;examine the operation of hydraulic system, temperature rise of bea
13、ring and vibration; check whether have abnormal noise and leakiness during oil pump working. When doing continual steering, the angle turn form 0°to 35°port, 35°port to 35°stb,and carry out alternately ,finally to 0°,but not less than 10 round, preliminary measure the needed
14、 time form one shipboard 35° to other shipboard 30° when testing.the requirement time by prime survey be to 20s.1.3试验记录1.3 test recorda、电动液压舵机连续试验时应记录电动机的起动电流、工作电流、电压、转速及液压缸的油压等;a. Record starting current ,working current ,voltage, speed and hydraulic oil pressure of electric motor when do
15、ing continual test of the electro-hydraulic steering gear.b、测量记录各电动机及其控制箱的热态绝缘电阻值,其值应不低于1兆欧。b. Measure insulation resistance (hot condition of each electrical box & motor and recordit ,with the value is not less than 1 .2、灭火系统试验2.fire-extinguishing system trial2.1试验条件2.1 trial conditiona、各系统布置和安
16、装合格;b、各系统管路的液压试验和密性试验合格;c、安全阀校验合格。a. Check of the arrangement and installationb. check hydraulic test and tightness testc. check of safety valves2.2试验内容及程序2.2 Test content & program表2(table 2射高m height 水量m3/h capacity水枪口径mm Nozzles size 水枪口径mm Nozzles size水枪进口压力kgf/cm2water pressure16 19 16 192.
17、0 17.17 17.62 13.7 19.52.5 20.58 21.28 15.5 21.63.0 23.64 24.65 16.8 23.83.5 26.35 27.72 18.0 25.6emergency fire pump with two nozzles (size 19mm to be capable of delivering the two jets of water ,with the water pressure should not be less than 0.25 MPa, with the water rang not be less than 12m.2.3试
18、验记录2.3 experiment recorda、测量记录电动消防泵的电动机及其控制设备在效用试验前后的冷、热态绝缘电阻值,绝缘电阻应不小于1兆欧。a. Before or after function test ,Measure insulation resistance (cold and hot condition of electrical box & motor of fire pump and record it ,with the value is not less than 1 .b、测量记录二氧化碳系统的报警装置在效用试验后的热态绝缘电阻值,绝缘电阻应不小于1兆欧。
19、b. Measure insulation resistance (hot condition of CO2 system alarm device after functional test, with the value is not less than 1 .3、舱底系统及油污水分离器试验3.bilge water system and oil extractor & drain separator test3.1试验条件3.1 trial conditiona、舱底水系统的密性试验合格;b、安全阀校验合格。a. Check watertight test of bilge wa
20、ter system;b. Check of safer valve3.2试验内容及程序3.2 Test content & program灵活性试验。a、试验结束后,应测量记录油水分离器污水泵的电动机及其控制设备的热态绝缘电阻值,其值应不小于1兆欧。a. After test, Measure insulation resistance (hot condition of electrical box & motor of oil extractors drain pump and record it, with the value is not less than 1 .b
21、、油污水分离装置效用试验中,应测量记录分离后水的含油量。b. Measure oil in separated water and record during test.4、压载系统试验4. Ballast System test4.1试验条件4.1 trial conditiona、压载系统经密性试验合格;b、压载泵或管路上的安全阀校验合格。a. Check test of ballast system tightnessb. check of safety valves4.2试验内容及程序4.2 Test content & programa、各压载泵进行试验时应记录电动机的起动电
22、流及工作电流。b、试验后测量并记录电动机及控制设备的热态绝缘电阻值。其值应不小于1兆欧。a. Record starting current and working current of motor when testing.b. Measure insulation resistance (hot condition of each electrical box & motor and record it ,with the value is not less than 1 .5、生活及排水系统试验5. Test of Scuppers and sanitary discharge
23、systems5.1试验条件5.1 trial conditiona、各生活系统的管路及设备安装完好,并密性试验合格;b、各水柜清洗完毕;c、安全阀及减压阀校验合格;d、各压力水柜的水位及各泵的控制调整完毕;e、按设计要求调整好热水柜的温度调节阀。使热水温度保持在60°70c°左右。a. after pipeline and equipment of each service sys.are installed ,take the efficient test.b. each water tank must be washed.c. check of relief valv
24、e and decompression valved. the water level of each pressure water tank and control of each pump must be regulated.e. regulate the temp. valve of the hot water tank make sure that the temp. is about60°70c°.5.2试验内容及程序5.2 Test content & program5.3试验记录a、生活和排水系统各泵试验时应记录电动机的起动电流及工作电流;b、试验后测
25、量记录电动机及控制设备的热态绝缘电阻值。其值应不小于1兆欧。5.3 experiment recorda. Record starting current &working current of motor when testing of Scuppers and sanitary discharge systemsb. After test, measure insulation resistance (hot condition of each electrical box & motor and record it ,with the value is not less
26、than 1 .6、通风系统试验6.Ventilation System test6.1试验条件6.1 trial conditiona、通风系统及设备安装合格;b、各机械通风舱室施工完毕。a. Check of installation of Ventilation System & equipment;b. Finishing construction of Mechanical ventilation engine room.6.2试验内容及程序6.2 Test content & programpipe ,funnel jalousie etc.6.3试验记录6.3 e
27、xperiment recorda、风机进行效用试验时,应记录其电动机的起动电流及工作电流;b、试验后测量并记录风机电动机及其控制设备的热态绝缘电阻值。a. Record starting current and working current of motor when doing funs function test;b. Measure insulation resistance (hot condition of electrical box & motor of blower and record it after test.7、主、辅机冷却系统试验7.M/E and A/E
28、 cooling test7.1试验条件7.1 trial conditiona、系统的布置和安装合格;b、泵及管路上的安全阀校验合格;c、系统的高温报警装置模拟试验合格。a. Check of the arrangement and installationb. check of safety valves of pump & pipingc. check test of temp.high alarm device by simulation7.2试验内容及程序7.2 Test content & program7.3试验记录各冷却泵试验结束后,应测量记录电动机及其控制设备
29、的热态绝缘电阻值,其值应不小于1兆欧。7.3 experiment recordAfter test of cooling pump, measure insulation resistance (hot condition of electric box & motor and record it ,with the value is not less than 1 .7.4 空调系统效用试验。7.4 A/E system function test效用试验结束后,空调机及其控制设备和水泵应测量热态绝缘电阻值,其值应不小于1兆欧。Measure insulation resistan
30、ce (hot condition of control box & A/E and water pump and record it ,with the value is not less than 1 .8、主、辅机滑油系统试验8.1试验条件8.1 trial conditiona、系统的布置和安装合格;b、安全阀校验合格;c、系统的高温及低压报警装置模拟试验合格。a. check of the arrangement and installationb. Check of safety valvec. test of temp.high &low-pressure ala
31、rm device was checked by simulation.8.2试验内容及程序8.2 Test content & program8.3试验记录试验结束后,测量记录电动机及其控制设备的热态绝缘电阻值,其值应不小于1兆欧。8.3 experiment recordAfter test, measure insulation resistance (hot condition of each electrical box & motor and record it ,with the value is not less than 1 .9、主、辅机燃油系统试验9.M/
32、E,A/E fuel oil system test9.1试验条件9.1 trial conditiona、系统的布置和安装合格;b、安全阀校验合格;c、燃油舱低位报警及泵的自动启动和停泵装置校验合格。a. check of the arrangement and installationb. Check of safety valve9.2试验内容及程序9.2 Test content & program9.3试验记录9.3 experiment record试验记录结束后,测量记录电动机及其控制设备的热态绝缘电阻值,其值应不小于1兆欧。Measure insulation resi
33、stance (hot condition of electrical box & motor and record it aftertest ,with the value is not less than 1 .10、燃油及滑油离心分油机试验10. Centrifugal Fuel oil& Lubricating oil purifier test10.1试验条件10.1 trial conditiona、系统的布置和安装合格;b、各报警系统校验合格;a. check of the arrangement and installationb. Check of alarm
34、 system10.2试验内容及程序10.2 Test content & program10.3试验记录10.3 experiment recorda、试验结束后,应测量记录电动机及其控制设备的热态绝缘电阻值。11、空气压缩机及压缩空气系统试验11. air compressor & compressed air system test11.1试验条件11.1 trial conditiona、空气压缩机及压缩空气系统的布置和安装合格;b、压缩空气系统(包括空气瓶气密试验合格(试验在额定工作压力下进行,时间不少于2h;c、空气机、空气瓶和压缩空气管路上的安全阀及减压阀校验合格
35、。a. the arrangement of air compressor and compressed air system to be eligible.b. compressed air system (include air bottle efficient test to be eligible.c. relief valve and pressure reduce valve on air compressor ,air bottle and compressed air pipeline to be eligible.11.2试验内容及程序11.2 Test content &a
36、mp; program11.3试验记录11.3 record of testa、试验时应测量记录电动机起动电流和工作电流、气密试验时间和压力降;b、测量记录电动机及其控制设备的热态绝缘电阻值。a. Record the starting circuit and working circuit ,time of airtight test and reducing pressure.b. measure the insulation resistance of electric motor and control equipment in hot state12、液压系统试验12 hydraul
37、ic pressure test12.1试验条件12.1 trial conditiona、液压传动管系液压试验合格;b、各安全阀校验合格;c、循环油箱低位报警装置及滑油系统的高温和低压报警装置模拟试验合格;d、滑油系统清洁合格。a. fluid drive piping efficient testb. relief valve test12.2试验内容及程序12.2 Test content & program12.3试验记录12.3 record of test13、空气管、测量管及液位遥测系统的效用试验13.efficient test of air ,sounding and
38、 level inspecting system.13.1检查空气管的安装完整性,自油舱引出的空气管,应检查金属防火网是否安装齐全。13.1 check installation integrality of the air pipe . metal fire damper about air pipe from oil tank to be checked.13.2各测量管以测深尺插入时,应上下自如,无阻碍现象。13.2 when insert the sounding pipe and sounding ruler, it should not be blocked.13.3低于舱壁甲板的
39、测量管,其管口的自闭旋塞动作应灵活。13.3 the nozzle cock of sounding pipe below the bulkhead deck to be agile.13.4测量管管口的铜质封盖应配置齐全,管口应标有清楚的标志。13.4 the brass close over of nozzle of sounding pipe to be equipped completely with the clear indication at the nozzle.14、主推进系统试验14.main propel system test14.1试验条件14.1 trial con
40、ditiona、主机、齿轮箱及轴系和螺旋桨等的安装验收合格;b、试验前主柴油机经磨合试验,并已初步调整各缸的工作参数;c、为主机运转服务的辅助机械装置、泵及管系已经系泊试验合格;d、试验用的柴油、滑油和冷却水应符合主机使用说明书的要求;e、测试仪表或设备检定合格;f、主机的安全保护装置及各系统的报警装置调试合格(或有产品厂合格证件。a.arrangement of M/E ,gearbox ,shafting and propeller to be eligible.b.Before test, primary regulation to be done to main diesel engi
41、ne including its working parameter of each cylinder.c.Auxiliary equipment, pump and piping serviced for M/E to be done with mooring test eligible.d.The D.O., L.O. and cooling water for test to be complied with specification of M/E manual.e.Measure gauge and equipment to be checked eligible.f.Protect
42、ion device of M/E and alarm device of each system to be regulated eligible.(or have the eligible certification of maker14.2试验内容及程序14.2 Test content & program表3(table3工况序号NO. 扭矩比值%(80%Netorsion and vibration ratio试验时间hTime1 39 0.52 63 0.53 83 0.54 100 24倒车astern Ahead rating speed正车额定转速的70%10mina
43、、可倒顺齿轮传动装置的倒、顺试验,应进行3次;b、齿轮传动装置的滑油低压及高温报警,应进行模拟试验,检查报警动作是否准确可靠。a. ahead and stern test to be carried out to gearbox for 3 times.b. Test of L.O. low-pressure and high temp.alarm shall be carried out by simulation, checka、安全系统的试验在主机停车的情况下进行模拟试验,校核整定值;b、应急停车试验:分别按下各控制站的应急停车机构动作,并发出相应的报警和显示;a. Safety te
44、st shall be carried out by simulation at M/E stop condition and check the set value;b. Emer. Stop test: do the Emer. Stop action of each control station separately and15、柴油发电机组及配电板试验15. diesel generator sets and switchboard test15.1试验条件15.1 trial conditiona、发电机组和配电板的安装及有关电缆的敷设验收合格;b、柴油机在额定负荷下各缸的负荷均匀
45、性调试合格;c、安全保护装置及报警装置调试合格(或有产品厂合格证件。a. Installation of D/G set and switchboard and relative cable to be eligible.b. equal regulation of each cylinder of diesel engine with rated load to be eligible.c. check of safety and alarm device ( or provide approved certificates by maker15.2试验内容及程序15.2 Test content & program表4 (table 4工况序号No. 发电机负荷%load试验时间htime1 2 3 4 5 2550751001020.5电机部分则应将各种负荷下的电压、电流、功率因数、转速作好测量记录。试验后应测量记录热态情况下的绝缘电阻值。其值应不小于1兆欧。发电机于100%负荷试验结束后,
温馨提示
- 1. 本站所有资源如无特殊说明,都需要本地电脑安装OFFICE2007和PDF阅读器。图纸软件为CAD,CAXA,PROE,UG,SolidWorks等.压缩文件请下载最新的WinRAR软件解压。
- 2. 本站的文档不包含任何第三方提供的附件图纸等,如果需要附件,请联系上传者。文件的所有权益归上传用户所有。
- 3. 本站RAR压缩包中若带图纸,网页内容里面会有图纸预览,若没有图纸预览就没有图纸。
- 4. 未经权益所有人同意不得将文件中的内容挪作商业或盈利用途。
- 5. 人人文库网仅提供信息存储空间,仅对用户上传内容的表现方式做保护处理,对用户上传分享的文档内容本身不做任何修改或编辑,并不能对任何下载内容负责。
- 6. 下载文件中如有侵权或不适当内容,请与我们联系,我们立即纠正。
- 7. 本站不保证下载资源的准确性、安全性和完整性, 同时也不承担用户因使用这些下载资源对自己和他人造成任何形式的伤害或损失。
最新文档
- 中枢神经系统脱髓鞘疾病的临床护理
- 现代通信及应用概述
- 府奖学金申请书
- 简易委托支付协议
- 2025年幼儿教育教学工作总结模版
- 策划部部门工作总结模版
- 物流管理集装箱体系优化
- 重症疾病护理核心要点解析
- 服装搭配系统化培训指南
- 流动人口清查总结
- 《人工智能通识导论(慕课版)》全套教学课件
- 烘培创业合伙协议书
- 北京2025年国家大剧院招聘24名专业技术人员笔试历年参考题库附带答案详解
- 2024建安杯信息通信建设行业安全竞赛题库及答案【三份】
- 2025年信息系统管理知识考试试题及答案
- 中介股东合同范例
- 马法理学试题及答案
- 2025年全国保密教育线上培训考试试题库附完整答案(夺冠系列)含答案详解
- 合伙人协议书模板
- 2025年下半年扬州现代农业生态环境投资发展集团公开招聘易考易错模拟试题(共500题)试卷后附参考答案
- 2025年中考第一次模拟考试卷:生物(成都卷)解析版
评论
0/150
提交评论