1、Fujian LNG Cooldown Presentation福建液化天然气冷却演示福建液化天然气冷却演示Option 4.方案方案4Cooldown Unloading System & T-0202冷却卸载系统冷却卸载系统&T-0202Cooldown Steps冷却步骤冷却步骤1. Displace Nitrogen from T-0202 & Unloading System Piping before cooldown冷却前将氮气抽离出T-0202和卸载系统管道2. Cooldown Unloading and T-0202 only仅冷却卸载系统和T-02023. Displac

2、e LNG from unloading into T-0202将液化天然气从卸载系统运至T-02024. Re-cooldown the facility with a second ship用另一艘船只再次冷却设备Cooldown Description冷却说明冷却说明nDisplace the Nitrogen from T-0202 with vapor from the ship vaporizer用船只汽化器中的蒸汽置换T-0202中的氮气nCooldown the Unloading and LP sendout systems with cold vapor from ship

3、用船上的冷蒸汽冷却卸载和LP输出系统nCooldown T-0202 until design temperature将T-0202冷却至设计温度nUnload all cargo into T-0202 将船上所有气体卸载到T-0202nShip departs船只驶离nRecover unloading system LNG to T-0202将卸载系统中的液化天然气运回T-0202Preparation准备阶段准备阶段nA valve lineup will be done for each step安排每一步的阀门开关顺序nMonitoring of all cooldown inst

4、ruments will be on the DCS trends由集散控制系统监视所有的冷却设备nMonitoring of the unloading lines movement will be by a team of engineers将由一队工程师监视卸载管线作业nCommunication with the ship will be from the CBI focal point in the CCR与船只的联系将由CBI中央控制室精英人员执行Step 1: Nitrogen Displacement步骤步骤1:氮气置换:氮气置换nValve line up to direct

5、 the ship vapor to T-0202 bottom fill line.执行阀门开关顺序,引导船上蒸汽进入T-0202底部的充液管线nDirect the Nitrogen through the BOG system to the Flare Stack引导氮气通过BOG系统进入火炬塔nControl the Tank pressure on 06-PV-0004控制06-PV-0004上的储罐压力nNitrogen target is 30%所需氮气量为30nEstimated time for 12 hrs估计所需时间为12个小时Step 2: Unloading Syst

6、em Cooldown步骤步骤2:卸载系统冷却:卸载系统冷却nVapor Cooldown of the unloading system卸载系统的蒸汽冷却 nCooldown will be controlled by the ship on instructions from the DCS operator冷却作业由船只根据集散控制系统操作员的指令进行控制nCooldown rate will be 10 to 20 deg / hr冷却速率为10-20/小时nCooldown can start during the Nitrogen displacement from T-0202在

7、氮气抽离T-0202的期间可以开始冷却nTarget temperature -100C at T-0202 riser T-0202立管目标温度为-100nTime for this step.16 hrs.这一步所需时间为16个小时Step 3: Filling the Unloading Lines步骤步骤3:卸载管线充液:卸载管线充液nLNG can be introduced to the unloading arm when -100C is reached at T-0202 riser on 02-TIT-2021 / 02-TIT-2022当02-TIT-2021/02-TI

8、T-2022上的T-0202立管达到-100时,可以将液化天然气装入卸载臂nTwo ship stripping pumps can be started to fill the unloading system.启动两个船只扫舱泵对卸载系统进行充液nApproximate volume of LNG required 850m3 所需液化天然气容积约为850m3nFilling rate 150 m3/hr from ship充液速率为每小时150m3nEstimated time for this step is. 10 hrs.这一步所需时间为10个小时Step 4: LNG Coold

9、own of T-0202步骤步骤4:T-0202的液化天然气冷却的液化天然气冷却nWhen LNG is detected at PIT on T-2020 riser the 02-HV-2002B on the tank must be closed.在T-2020立管上的PIT检测到液化天然气时必须关闭储罐上的02-HV-2002BnOne stripping pump stopped and 02-HV-2001 Spray valve opened停止一台扫舱泵,打开02-HV-2001喷射阀nSpray cooling of the tank can begin at 3 to

10、5C /hr.以每小时3到5的速度开始对储罐进行喷淋冷却nEstimated cooldown time is 50 hrs.估计冷却时间为50个小时 nCooldown is finished when50 mm of LNG is measured on tank floor储罐底上的液化天然气达到50mm时结束冷却.Step 5 Tank T-0202 Filling步骤步骤5:T-0202充液充液nFilling of the tank can begin when all floor thermocouple are reading -156C and at 50mm level当所

11、有的底面热电偶读数为-156并达到50mm时可以开始储罐充液.nRequest the ship to start a cargo pump要求船只启动装卸油泵.nPumps can be started to the maximum limit of two unloading arms (8000m3/hr).可以以两个卸载臂的最大速率(8000m3/hr)运转油泵.nEstimated time for this step16 hrs. (depends on ship cargo size).估计所需时间为16个小时(取决于船只液量)Ship Departure船只驶离船只驶离nWhe

12、n cargo transfer is complete, the unloading arms can be disconnected following vendor procedure.充液完成后,可以根据供应商程序拆下卸载臂.nThe V-0102 Drain Drum emptied.排空V-0102干燥滚筒.nThe Unloading system LNG allowed to weather off.卸载系统使液化天然气不受天气影响.nThe unloading system purged by Nitrogen.用氮气吹扫卸载系统.Fig 1 Cooldown Diag. Overview图图1 冷却图总览冷却图总览Fig: 2 Nitrogen Displacement图图2:氮气置换:氮气置换LNG Vapor Cooldown液化天然气蒸汽冷却液化天然气蒸汽冷却Filling Unloading System卸载系统充液卸载系统充液Cooldown of T-0202T-0202冷却冷却Filling T-0202T-0202充液充液Displacing LNG to T-020

温馨提示

  • 1. 本站所有资源如无特殊说明,都需要本地电脑安装OFFICE2007和PDF阅读器。图纸软件为CAD,CAXA,PROE,UG,SolidWorks等.压缩文件请下载最新的WinRAR软件解压。
  • 2. 本站的文档不包含任何第三方提供的附件图纸等,如果需要附件,请联系上传者。文件的所有权益归上传用户所有。
  • 3. 本站RAR压缩包中若带图纸,网页内容里面会有图纸预览,若没有图纸预览就没有图纸。
  • 4. 未经权益所有人同意不得将文件中的内容挪作商业或盈利用途。
  • 5. 人人文库网仅提供信息存储空间,仅对用户上传内容的表现方式做保护处理,对用户上传分享的文档内容本身不做任何修改或编辑,并不能对任何下载内容负责。
  • 6. 下载文件中如有侵权或不适当内容,请与我们联系,我们立即纠正。
  • 7. 本站不保证下载资源的准确性、安全性和完整性, 同时也不承担用户因使用这些下载资源对自己和他人造成任何形式的伤害或损失。

评论

0/150

提交评论