ICS27.180
P02
NB
EnergySectorStandardofthePeople’sRepublicofChina
NB/T31011-2019
ReplaceNB/T31011-2011
Preparationregulationforcostestimation
ofonshorewindpowerprojects
陆上风电场工程设计概算编制规定
及费用标准
(EnglishTranslation)
Issuedate:2019-06-04Implementationdate:2019-10-01
IssuedbyNationalEnergyAdministrationofthePeople’sRepublicofChina
NB/T31011-2019
AboutEnglishTranslation
ThisEnglishversionisoneofChina’senergysectorstandardseriesinEnglish.Itstranslationwas
organizedbyChinaRenewableEnergyEngineeringInstituteauthorizedbyNationalEnergy
AdministrationofthePeople’sRepublicofChinaincompliancewithrelevantproceduresandstipulations.
ThisEnglishversionwasissuedbyNationalEnergyAdministrationofthePeople’sRepublicofChinain
Announcement[202x]No.xxdatedxxxx,202x.
ThisversionwastranslatedfromtheChineseStandardNB/T31011-2019,Preparationregulationfor
costestimationofonshorewindpowerprojects,publishedbyChinaWater&PowerPress.Thecopyright
isreservedbyNationalEnergyAdministrationofthePeople’sRepublicofChina.Intheeventofany
discrepancyintheimplementation,theChineseversionshallprevail.
Manythanksgotothestafffromtherelevantstandarddevelopmentorganizationsandthosewhohave
providedgenerousassistanceinthetranslationandreviewprocess.
ForfurtherimprovementoftheEnglishversion,allcommentsandsuggestionsarewelcomeandshould
beaddressedto:
ChinaRenewableEnergyEngineeringInstitute
No.2Beixiaojie,Liupukang,XichengDistrict,Beijing100120,China
Website:
Translatingorganization:
Translatingstaff:
Reviewpanelmembers:
NationalEnergyAdministrationofthePeople’sRepublicofChina
I
NB/T31011-2019
翻译出版说明
本译本为国家能源局委托水电水利规划设计总院按照有关程序和规定,统一组织翻译的能源行
业标准英文版系列译本之一。202x年xx月xx日,国家能源局以202x年第x号公告予以公布。
本译本是根据中国水利水电出版社出版的《陆上风电场工程设计概算编制规定及费用标准》
NB/T31011—2019翻译的,著作权归国家能源局所有。在使用过程中,如出现异议,以中文版为
准。
本译本在翻译和审核过程中,本标准编制单位及编制组有关成员给予了积极协助。
为不断提高本译本的质量,欢迎使用者提出意见和建议,并反馈给水电水利规划设计总院。
地址:北京市西城区六铺炕北小街2号
邮编:100120
网址:
本译本翻译单位:
本译本翻译人员:
本译本审核人员:
国家能源局
II
NB/T31011-2019
Foreword
ThisstandardisdraftedinaccordancewiththerulesgivenintheGB/T1.1-2009Directivesfor
standardization—Part1:Structureanddraftingofstandards.
ThisstandardreplacesNB/T31011-2011Preparationregulationforcostestimationofonshorewind
powerprojects.Inadditiontoanumberofeditorialchanges,thefollowingtechnicalmodificationshave
beenmadeincomparisonwithNB/T31011-2011:
—Thescopeofthisstandardismodifiedtobeapplicabletothecostestimationfornewcentralized
onshorewindpowerplantsandmaybereferencedforotherwindpowerplants(see1ofthis
specification).
—Inworkbreakdown,“preparationworksofwindturbineinstallation”(seeofthisspecification)
and“safeandcivilizedconstructionmeasures”(seeofthisspecification)areaddedtothe
“auxiliaryconstructionworks”asfirst-levelitems.“Watersupplyforconstruction”(seeofNB/T
31010-2011),isdeletedfromfirst-levelitemsandisputunder“otherauxiliaryconstructionworks”(see
ofthisspecification).
—Inworkbreakdown,“collectionlineequipmentandinstallation”(seeofthisspecification)is
addedto“equipmentandinstallationworks”asfirst-levelitem.“Windturbineoutgoinglines”(see
ofthisspecification),“subsystemdebugging”(seeofthisspecification),“electricsystem
debugging”(seeofthisspecification),“electricalspecialprojecttest”(seeofthis
specification),“equipmentallocationincentralizedcontrolcenter”(seeofthisspecification)are
addedassecond-levelitems.First-levelitem“controlandprotectionequipmentandinstallation”(see
ofNB/T31010-2011),aswellassecond-levelitems“safetymonitoringequipment”(seeof
NB/T31010-2011),“environmentandwaterandsoilconservationequipment”(seeofNB/T
31010-2011),“nationalwindpowerinformationreportingsystem”(seeofNB/T31010-2011),and
“windpowerplantoperationmanagementsystem”(seeofNB/T31010-2011),arealldeleted.
—Inworkbreakdown,“collectionlines”(seeofthisspecification)isaddedto“civilworks”as
first-levelitem.“Windturbineoutgoinglineproject”(seeofthisspecification),“foundationworks
ofreactivepowercompensators”(seeofthisspecification)and“flood(moisture)controlworks”
(seeofthisspecification)areaddedassecondaryitems.“Accessroadsandbridges”aremerged
into“accessroads”in“transportation”(seeofthisspecification).First-levelitem“building”(see
ofNB/T31010-2011)isdeleted,andthesubordinateitemsareputunder“step-upsubstation”(see
ofthisspecification).Thesecondaryitem“others”(seeofNB/T31010-2011)isdeleted.
—Inworkbreakdown,“preliminaryworkcost”(seeofthisspecification)isaddedto“othercosts”
asafirst-levelitem.“Projectqualityinspectionandtestingcost”(seeofthisspecification),“norm
preparationandmanagementcost”(seeofthisspecification),andthe“as-builtdrawing
preparationfee”(seeofthisspecification)areaddedassecond-levelitems.Thesecond-levelitem
“preliminaryworkcost”(seeofNB/T31010-2011)isdeleted.“Costofmanagementdevices”and
“costoftoolsandproductionfurniture”in“operationalpreparationcost”aremergedinto“procurement
costofmanagementtoolsandapparatusandfurniture”(seeofthisspecification).
—Incostcomposition,“employeewelfare”and“laborprotectionexpense”under“laborcost”areput
under“enterpriseaccrualexpense”(seeofthisspecification)in“indirectcost”.“Measurecost”is
modifiedinto“otherdirectcost”(seeofthisspecification).Thesubordinateitem“costofsafeand
civilizedconstructionmeasures”islistedseparatelyasasecond-levelitemunder“auxiliaryconstruction
works”(seeofthisspecification).“Sitemanagementexpense”and“overheadcost”inindirect
costaremergedinto“overheadcost”(seeofthisspecification).“Socialsecuritycontributions”of
productionstaffisincludedinlaborcost(seeofthisspecification).“Normpreparationand
measuringcost”(seeofthisspecification)isadded.“Businesstax”intaxesischangedinto“value
addedtax”(see5.3.6ofthisspecification);“urbanmaintenanceandconstructiontax”,“education
surchargeandlocaleducationsurcharge”areaddedinto“overheadcost”(seeofthis
specification).
IV
NB/T31011-2019
—Instandardrates,“researchandexperimentcost”(see7.4.10ofthisspecification),“investigationand
designcost”(see7.4.11ofthisspecification)areadded.Theskilllevelsoflaborarechangedfrom
“highly-skilledworker,skilledworker,semi-skilledworkerandunskilledworker”into“highly-skilled
worker,skilledworkerandunskilledworker”,andtheunitpriceoflaborisadjustedfromman-hourto
man-day(see7.1.1ofthisspecification).Additionalconstructioncostforhigh-altitudeareas(see
ofNB/T31010-2011)isdeleted.Otherrelatedstandardratesareadjustedaccordingtotheproject
categories,costcomposition,calculationbaseofrate,marketpricelevelandthepolicyofreplacing
businesstaxwithvalue-addedtax.
TheNationalEnergyAdministrationofthePeople’sRepublicofChinaisinchargeoftheadministration
ofthisstandard.ChinaRenewableEnergyEngineeringInstitutehasproposedthisstandardandis
responsibleforitsroutinemanagement.Thesub-technicalcommitteeofwindfarmplanninganddesign
ofTechnicalCommitteeofWindPowerStandardizationinEnergySectorisresponsibleforthe
explanationofspecifictechnicalcontents.Commentsandsuggestionsintheimplementationofthis
standardshouldbeaddressedto:
ChinaRenewableEnergyEngineeringInstitute
No.2Beixiaojie,Liupukang,XichengDistrict,Beijing100120,China
Draftingorganizations:
ChinaRenewableEnergyEngineeringInstitute(ChinaRenewableEnergyEngineeringCost
ManagementCenter)
POWERCHINANorthwestEngineeringCorporationLimited
Chiefdraftingstaff:
GUANZongyinZHAOGuizhiLIHongyuHUANGLin
XUEHuijuanWANGYonggangSUNLihongZHANGJuan
ThisstandardreplacesNB/T31011—2011inwhole.
.
V
NB/T31011-2019
Introduction
Inrecentyears,withtherapiddevelopmentofonshorewindpowerindustryandsignificantimprovement
intechnologyandequipment,aswellastheintroductionofnewpoliciesfromthegovernmentinthe
aspectsofraisingtheincomeoflaborers,improvingproductionconditions,andstrengtheningproduction
safety,somenewcharacteristicsandnewsituationshaveemergedintheconstructionprocessofwind
powerprojects.
Inordertopromotethehealthyandorderlydevelopmentofonshorewindindustry,meettherequirements
ofprojectconstructionmanagement,betterreflecttherelevantnationalpolicies,furtherstrengthenand
standardizetheprojectcostmanagement,improvetheprojectcostmanagementsystem,unifythe
preparationregulationandstandardratesforcostestimationofonshorewindpowerprojects,reasonably
determinetheprojectcost,andimprovetheinvestmentreturns,thisstandardhasbeendeveloped
accordingtotherequirementsofDocumentGNKJ[2015]No.283“NoticeonReleasingtheDevelopment
andRevisionPlanofEnergySectorStandardin2015”issuedbyNationalEnergyAdministrationofthe
People’sRepublicofChina,andafterextensiveinvestigationandresearch,summarizationofpractical
experience,consultationofrelevantstandardsofChina,andwidesolicitationofopinions.
VI
NB/T31011-2019
Preparationregulationforcostestimationofonshorewind
powerprojects
1Scope
Thisstandardspecifiestheworkbreakdown,costcomposition,preparationofcostestimation,standard
rates,anddocumentationofcostestimation.
Thisstandardisapplicabletothecostestimationfornewcentralizedonshorewindpowerplants.Itmay
bereferencedforotherwindpowerplants.
2Normativereferences
Thefollowingreferenceddocumentisindispensablefortheapplicationofthisdocument.Fordated
references,onlytheeditioncitedapplies.Forundatedreferences,thelatesteditionofthereferenced
document(includinganyamendments)applies.
NB/T31010-2019QuotaforCostEstimationofOnshoreWindPowerProjects
3Generalprovisions
3.1Thisstandardisdevelopedtounifythecontent,depthandcalculationmethodsofcostestimationfor
onshorewindpowerprojects,reasonablydeterminethecosts,andimprovethequalityofcostestimation.
3.2ThisstandardshallbeusedtogetherwithNB/T31010-2019.
4Workbreakdown
4.1Generalrequirements
Thecostestimationofonshorewindpowerprojectsshallinvolveauxiliaryconstructionworks,
equipmentandinstallationworks,civilworksandothercosts,asshowninFigure1.
1
NB/T31011-2019
Transportationforconstruction
Powersupply
Auxiliaryconstruction
Foundationworkofpowersetinstallation
works
Otherauxiliaryconstructionworks
Safeandcivilizedconstructionmeasures
Equipmentandinstallationofthepowerplant
Equipmentandinstallationofcollectionlines
Equipmentand
installation
Equipmentandinstallationofstep-up
substation
Otherequipmentandinstallation
Powerplant
Windpowerproject
Collectionlines
CivilworksStep-upsubstation
Transportation
Othercivilworks
Landuse
Preliminaryworkcost
Constructionadministration
Othercosts
Operationalpreparation
Investigationanddesign
Othercosts
Figure1Workbreakdownofcostestimation
4.2Workitems
4.2.1Theauxiliaryconstructionworksreferstothetemporaryworksandmeasuresfortheconstruction
2
NB/T31011-2019
ofmainworks,includingtemporaryroadworks,powersupplyworks,preparationworksforwindturbine
installation,otherauxiliaryworks,andmeasuresforsafeandcivilizedconstruction.Ifthereareauxiliary
constructionworksthatcombinebothpermanentandtemporaryfunctions,theyshallbelistedunderthe
correspondingitemsofpermanentworks.
Thetemporaryroadworksreferstothetemporaryroadsfortheconstructionofwindpower
projects,includingtheconstruction,reconstruction(expansion)andrehabilitationofroadsandbridges
(culverts).
Thepowersupplyworksreferstotheconnectionofpowersupplylinesof10kVandabove
fromtheexistingpowergridtothesite,andthepreparationofpowersupplyfacilitiesof35kVand
above.
Thepreparationworksforwindturbineinstallationreferstothesitepreparationworksforthe
on-siteassemblyandinstallationoftowers,windturbinesandotherequipment.
Otherauxiliaryconstructionworksrefertotheauxiliaryworksapartfromtheabove,suchas
mobilizationanddemobilizationoflargehoistingmachinery,watersupplyforconstruction,cofferdam
construction,sitelevelingfortemporaryfacilitiesofwindpowerplantinmountainousarea.The
mobilizationanddemobilizationoflargehoistingmachineryrefertothoseClassAmachineryincludedin
thenormsofmachine-shiftratesofconstructionmachinery.
Themeasuresforsafeandcivilizedconstructionrefertothemeasurestobetakenatthe
constructionsitebythecontractorinaccordancewithcorrespondingrequirements.
4.2.2Theequipmentandinstallationworksreferstoalltheequipmentconstitutingthefixedassetsof
thewindpowerplantandtheirinstallation,includingpowergenerationequipmentandinstallation,
collectionlineequipmentandinstallation,step-upsubstationequipmentandinstallation,andother
equipmentandinstallation.
Thepowergenerationequipmentandinstallationofthepowerplantreferstothewindpower
equipmentandinstallationintheplant,includingwindturbines,towers,outgoinglines,transformers,and
earthing.
Thecollectionlineequipmentandinstallationreferstotheequipmentandinstallationof
collectioncables,overheadcollectionlines,earthing,etc.,inthewindfarm.
Thestep-upsubstationequipmentandinstallationreferstotheequipmentandinstallationfor
powertransformation,powerdistribution,controlandprotectioninthestep-upsubstation,includingthe
maintransformersystem,powerdistributionequipment,reactivepowercompensationsystem,station
service(emergencypowersupply)system,powercables,earthing,monitoringsystem,AC(DC)system,
communicationsystem,remoteautomaticcontrolandpowermeteringsystem,subsystemdebugging,
electricalsystemdebugging,andelectricalspecialitemtest.
Otherequipmentandinstallationreferstothecorrespondingequipmentandinstallationother
thanmentionedabove,includingtheheating,ventilationandairconditioningsystem,outdoorlighting
system,firefightingsystem,watersupplyanddrainagesystem,occupationalhealthandsafetyequipment,
productionandmaintenancevehicles,equipmentallocationincentralizedcontrolcenter,andother
equipmentthatneedtobelistedseparately.
4.2.3Thecivilworksreferstothebuilding(structure)worksconstitutingthefixedassetsofthewind
powerplant,includingpowerplantworks,collectionlineworks,step-upsubstationworks,roadworks,
andothercivilworks.
Thepowerplantworksreferstoallkindsofbuilding(structure)worksinthepowerplant,
includingthefoundationworksofwindturbines,outgoinglineworks,foundationworksofwindturbine
transformers,earthingofwindturbinesandwindturbinetransformers.
Thecollectionlineworkscomprisesthecivilworksofthecollectioncablelines,thecivilworks
ofoverheadcollectionlines,andoverheadcollectionlineearthing.
3
NB/T31011-2019
Thestep-upsubstationworksreferstothestructureworksinthestep-upsubstation,including
thesiteleveling,foundationworksofmaintransformer,foundationworksofreactivepower
compensators,foundationworksofpowerdistributionequipment,structuresofpowerdistribution
equipment,productionbuildings,auxiliarybuildings,siteofficesandlivingquarters,andoutdoorworks.
Amongwhich,theproductionbuildingscomprisethecentralcontrolroom(building),distributionroom
(building),reactivepowercompensatorroom,etc.Theauxiliarybuildingscomprisethesewagetreatment
room,firepumproom,firefightingequipmentroom,dieselgeneratorroom,boilerroom,storehouse,
garage,etc.Thesiteofficesandlivingquarterscomprisetheoffices,dutyroom,dormitory,canteen,guard
room,etc.Theoutdoorworkscomprisesthewalls,gates,siteroads,sitegroundhardening,sitegreening,
andotheroutdoorworkswhichincludethewatersupplypipes,drainagepipes,inspectionwells,rainwater
wells,sewagewells,wellcovers,valves,septictank,anddrainageditches.
Theroadworksreferstotheaccessroadsandsiteroadsofthewindfarm.Theaccessroadsrefer
toroadsconnectingtothepowerplantandthestep-upstation.Thesiteroadsrefertotheroadsfor
maintenanceinsidethepowerplant.
Othercivilworksreferstothoseotherthanmentionedabove,includingtheenvironmental
protection,waterandsoilconservation,occupationalhealthandsafety,safetymonitoring,watersupply
forfirefighting,productionandliving,flood(moisture)control,allocationofcentralizedproductionand
operationmanagementfacility,andotherworksthatneedtobelistedseparately.
4.2.4Othercostsrefertothecostswhichareindispensabletotheprojectbutareexcludedinequipment
cost,installationcost,orcivilworkscost.Othercostsincludethelandusecost,preliminaryworkcost,
constructionadministrationcost,operationalpreparationcost,scientificresearch,investigationanddesign
cost,andothers.
Thelandusecostreferstotheexpensespaidinaccordancewithrelevantnationalandlocallaws
andregulationstoobtainthesiteneededforprojectconstruction,includingthelandacquisitionfee,
temporarylandacquisitionfee,compensationforattachmentsontheacquiredland,andsiteclearance
expense.
Thepreliminaryworkcostreferstotheexpensesincurredincarryingoutvariousworksbefore
thecompletionofthereviewofthepre-feasibilitystudyreport(orbeforethepreparationofthewindfarm
project).
Theconstructionadministrationcostreferstovariousadministrationexpensesincurredinthe
processofprojectpreparation,construction,commissioning,acceptanceandhandover,includingthe
overheadofprojectowner,constructionsupervisioncost,consultingservicecost,technicalandeconomic
reviewcost,projectqualityinspectionandtestingcost,normpreparationandmanagementcost,project
acceptancecost,andinsurancepremium.
Theoperationalpreparationcostreferstotheexpensesincurredformakingnecessary
preparationbytheprojectlegalpersonforprojectoperation,includingtheexpenseforproduction
personneltrainingandearlymobilizationintotheplant,expenseforpurchasingmanagementappliance,
tools,apparatusandfurniture,expenseforpurchasingspareparts,andexpenseforcommissioning.
Thescientificresearch,investigationanddesigncostreferstotheexpensesincurredinscientific
researchandtest,investigationanddesignfortheconstructionoftheproject,includingthescientific
researchandtestcost,investigationanddesigncost,andas-builtdrawingpreparationfee.
Othersrefertothetaxesandfeestobepaidinaccordancewithrelevantnationalregulations,
likethecompensationforwaterandsoilconservation,etc.
4.2.5TheworkbreakdownshallcomplywithAnnexAofthisstandard.Thelevel2andlevel3itemsin
TableA.1toTableA.4maybeaddedordeleteddependingontheprojectdesign.
4
NB/T31011-2019
5Costcomposition
5.1Generalrequirements
ThecompositionoftotalcostofanonshorewindpowerplantisshowninFigure2.
Equipmentcost
Civilworksand
installationcost
TotalcostOthercosts
Contingency
Interestduring
construction
Figure2Compositionoftotalcost
5.2Equipmentcost
5.2.1Theequipmentcostconsistsoforiginalpricesofequipment,freightandmiscellaneouscharges,
transportationinsurancepremium,andprocurementandstorageexpense.
5.2.2Theoriginalpricesofequipment:
a)Theoriginalpricesofdomesticequipmentrefertothefactoryprices;
b)Theoriginalpricesofimportedequipmentconsistofthecostinsuranceandfreight(CIF),tariff,
value-addedtaxes,agentcharges,goodsinspectionfeesandportcharges.
5.2.3Thefreightandmiscellaneouschargesrefertoallexpensesincurredinequipmenttransportation
frommanufacturerstothesite,includingtheexpensesfortransportation,dispatching,handling,packing
andlashing,andothermiscellaneousexpenses.
5.2.4Thetransportationinsurancepremiumreferstotheinsurancepaidforthetransportationof
equipment.
5.2.5Theprocurementandstorageexpensereferstovariousexpensesincurredintheprocessof
materialpurchaseandstorage.
5.3Civilworksandinstallationcost
5.3.1ThecompositionofcivilworksandinstallationcostisshowninFigure3.
5
NB/T31011-2019
Laborcost
BasicdirectcostMaterialcost
Directcost
温馨提示
- 1. 本站所有资源如无特殊说明,都需要本地电脑安装OFFICE2007和PDF阅读器。图纸软件为CAD,CAXA,PROE,UG,SolidWorks等.压缩文件请下载最新的WinRAR软件解压。
- 2. 本站的文档不包含任何第三方提供的附件图纸等,如果需要附件,请联系上传者。文件的所有权益归上传用户所有。
- 3. 本站RAR压缩包中若带图纸,网页内容里面会有图纸预览,若没有图纸预览就没有图纸。
- 4. 未经权益所有人同意不得将文件中的内容挪作商业或盈利用途。
- 5. 人人文库网仅提供信息存储空间,仅对用户上传内容的表现方式做保护处理,对用户上传分享的文档内容本身不做任何修改或编辑,并不能对任何下载内容负责。
- 6. 下载文件中如有侵权或不适当内容,请与我们联系,我们立即纠正。
- 7. 本站不保证下载资源的准确性、安全性和完整性, 同时也不承担用户因使用这些下载资源对自己和他人造成任何形式的伤害或损失。
最新文档
- 2026年10月02日 兰州市城关区考核基地 拜耳医药 医药代表 29人
- 江西省新余市2025-2026学年高一上学期期末化学试题(含答案)
- 2026中老年人群老人秋冬防病保健专题培训课件
- 大疱性皮肤病
- 2026初中德育工作汇报课件:家校社协同育人
- 2026新学期中小学生诺如病毒感染的预防课件
- 辽宁辽阳市第一中学(西藏班)2025-2026学年八年级下学期期末质量监测道德与法治试卷(含答案)
- 2025-2026年护士资格考试内科护理学冲刺练习
- 2025-2026年全民阅读竞赛测试卷
- 2025-2026年重庆市部编版七年级物理上册第5章力学练习题
- 2026年阿里云ACP云计算工程师认证考试真题题库
- S224颍上至赛涧段道路工程K6~K9初步设计
- 物业公司与理发店合同
- 2026年4月自考02323操作系统概论试题及答案含评分参考
- 工程复工报告(完整版)
- 中医学会工作制度
- 2026中国金融监管科技应用现状及政策导向分析报告
- GA/T 2348-2025信息安全技术网络安全等级保护5G接入安全测评要求
- B站BiliiliWorld招商策划通案
- 2026年冲压模具维护作业指导书
- 2026年抗癫痫发作药物联合使用专家共识
评论
0/150
提交评论