Rocklandsproject
INSTALLATIONOVERVIEWInstallationStatusasat10-NOV-14Structural–94%Mechanical–81%Pipework–81%ForecastManHourstoComplete–28,624PrimaryIssuesDesignandFabricationIssues:ASignificantquantityofpipespoolsandpipesupportswereincorrectduetofabricationordesignerrors.SinosteelelectedtoRe-SupplyincorrectpipespoolsandinstructedWalztorectifypipesupportsonsite.PipeworkLabellingIssue:Duetopoorlabelling/managementofthepipeworkfabricationinChina,1200pipespoolsweredeliveredtositewithnolabelorlabelledincorrectly.Valves:Latesupplyresultinginextendedinstallationduration.FloatationReagentsPipework2,000m:Sinosteelinstruct/authorisedWalztoprocurefittingsandcommenceinstallationofsiteweldedDN25/15mmpipework10-NOV-14.PotableWater:Sinosteelapprovedpotablewaterlayoutsonthe11-NOV-14enablingWalztocommenceinstallationof1,200mofDN50pipework.SynthesisPipelineNetworkHold:SinosteelinstructWalztonotinstallpiperackinfour(4)locationstoenablecraneaccessatalaterdatetoinstallE-Houses(ThirdPartyContractor).CV3201AccessIssue:Walzunabletocompleteinstallationduetoongoingcivilconstructionofthere-claimtunnel(Cudeco).ExpectedhandovertoWalztoenableinstallationtocommence15-DEC-14.GrindingMillLubrication&DrainPipework:Sinosteelhaveelectedtofabricate74.407mofstainlesssteelpipeworkonsiteandadvisethefabricationdurationwillbe3-4weeks.Sinosteelhavenotcommencedfabricationasat15-NOV-14.PipelineMarkers:Sinosteelunderestimatedtherequiredquantityby500%MaterialSupplyIssue–Slip/FloatingFlangeBolts:Duetoadesignomission/error,Sinosteelsuppliedboltsforslip/floatingflangesweretooshort.CorrectlengthboltswereRe-SuppliedonCDU-028:24-OCT-14.MaterialSupplyIssue-SiteRunPipework:SignificantShortfallinsupplyofsiterunfittingsandpipe.Walzprocuredanotablequantityoffittingsandpipeworkwhichhadleadtimesofupto2-3weeks.MajorDesignConcerns:WalzholdgreatconcerninrelationtoSinosteel’sDesignofpipesupportsandpipeworkaspreviouslyadviseinNCR-0214andformalletterPipeworkDesignConcerns#1.ShipmentSummary-2014SHIPMENTSUMMARY-2014CDU-024CDU-025CDU-026CDU-027CDU-028CDU-029FirstDeliveryOnsite12-DEC-1315-APR-145-JUL-1427-AUG-1424-OCT-1430-NOV-14DeliveryDuration(Cudeco)6Weeks6Weeks8Weeks4Weeks1WeekNotDeliveredStructuralSteel(T)1,21772595550413SteelPipe/Supports(T)43330923.128.429.815PipePercentageOnsite3.1%24.1%67.4%2.1%2.2%1.1%Walznote27.2%ofthepipeworkwasdeliveredonCDU-024&CDU-025,Howeverinstallationofthispipeworkcouldnotcommenceduetoinsufficientpipesupports,pipefittingsandSynthesisPipelineNetwork(SPN)structuralsteelwhichwasdeliveredinCDU-026&CDU-027.CDU-026shipmentcontained67.6%ofthepipework,howeverthein-landdeliverywasnotcompleteduntil30-AUG-14.CDU-026shipmentcontained92.5%ofthepipesupports,howeverthein-landdeliverywasnotcompleteduntil30-AUG-14.Sinosteel’slatedeliveriespreventedWalzfromcommencinginstallationofpipeworkuntilpostdeliveryofCDU-026(AgreedConstructionBaselineSchedulestatesallpipeworkwastobeonsite28-FEB-14).DeliverydurationofallshipmentsfromTownvillePortQLDtoRocklandssitewasunacceptable.WalzadvisedSinosteelbymeansofContractorMeetings&FormalLetterssinceCDU-024andthroughout2014shipments.Tomitigatedelays,WalzprovidedSinosteelwithcomprehensiveprioritylistswhichwereprimarilyignoredandnotfollowed.RFISUMMARYREQUESTFORINFORMATION(RFI)–SUMMARYTABLEIssuesRaisedRFI’sDetailedPipework/Spool539274PipeSupport724255Total1263529Asignificantquantityoffabrication/designissueswereidentifiedwiththepipespoolsandsupport.WalzrectifiedasignificantquantityofpipesupportsonsiteasinstructedtoenableinstallationtoprogresswhilewaitingonRe-SupplyItems.PipeworkSpools
Re-Supplied/LateDeliveryTOTALNUMBEROFPIPELINES>DN50=EIGHTHUNDRED&NINETYTWO(892)Shipment
CDU-028CDU-029DeliveryDateOnsite24-OCT-1430-NOV-14-ExpectedRe-Supplied/LatePipeSpools27277PercentageofPipelinesEffected30.5%8.6%SinosteelelectedtoRe-Supplythelargemajorityofincorrectspools.TheRe-Suppliedpipespoolsarrivedonsite24-OCT-14(CDU-028)howeverthisshipmentonlyaccountedfor68%oftherequiredRe-SupplyItems.PipeSupports
Re-Supplied/SiteModificationTOTALNUMBEROFPIPESUPPORTS=1,182Shipment
CDU-028CDU-029DeliveryDateOnsite24-OCT-1430-NOV-14-ExpectedRe-SuppliedPipeSupports777No.SupportsModifiedOnsite724PercentageofPipelinesEffected67.77%Walznote67.77%ofthepipesupportsontheprojectrequiredmodificationduetofabricationanddesignerrors.Lostproductivityandflow-oneffectstosubsequentpipeworkinstallationactivitiesweresignificant.UniqueValveSupplySummaryTOTALNUMBEROFUNIQUEVALVEFORPIPEWORK=637Shipment
CDU-027CDU-028CDU-029CDU-030?DeliveryDateOnsite27-AUG-1424-OCT-1430-NOV-14(Expected)?QtyUniqueValves23439234130RunningPercentage38%44%81%100%Asat13-NOV-14thepercentageofoutstandingUniqueValvesis56%.Supplyissuepreventscompletionofthelargemajorityofpipework.Walzarerequiredtore-accessallvalvelocationsuponsupplyofvalvesforinstallation.TomitigatedelaysWalzhaveinstalledspacersinpipeworktoallowinstallationtoprogressintheabsenceofthevalves.Non-UniqueValveSupplySummaryTOTALNUMBEROFNON-UNIQUEVALVEFORPIPEWORK=1365Shipment
CDU-027CDU-028CDU-029CDU-030?DeliveryDateOnsite27-AUG-1424-OCT-1430-NOV-14QtyNon-UniqueValves24117862276RunningPercentage2%88%93%100%Asat13-NOV-14thepercentageofoutstandingNon-UniqueValvesis12%Supplyissuepreventscompletionofsiterunpipework<DN50andinstallationofvalvesinpipework>DN50WalzhavehighlightedtoSinosteelasignificantshortfallinsupplyhasbeenidentifiedfollowingacomparisonofPackingListsVsP&IDMTO.PipeworkLabellingIssueWalzadvisedSinosteelinRFI-0612toRFI-0641datedthe23-JUN-14thatonethousandtwohundred(1200)pipeworkspoolscouldnotbelocatedonthepackinglistsofCDU-026.SinosteeladvisedintheWeeklyContractorMeetingonthe5-JUL-14thattheonethousandtwohundred(1200)pipeworkspoolswereinfactpresentontheshipmenthowevertheyarenotlabelledorlabelledincorrectly.AsadirectresultWalzwererequiredtomeasureandcheckeverypipespool(Approximately8,000)againsteveryisometricdrawing.Lostproductivityandflow-oneffectstosubsequentpipeworkinstallationactivitiesweresignificant.PipeworkLabellingIssue
SitePhotographExampleRedundantPipeworkFloatationReagentsPipework
2,000mofSiteRunPipeRFI-1429dated29-SEP-14,identifiedtheSCH40pipematerialwassuppliedwhichwasunsuitableforpress-fitconnectionsasperdesign.Sinosteelinvestigatedalternativeoptions.Re-SupplyofSCH10material.ChangeDesigntoscrewedfittings,thiswouldenabletheuseofSCH40pipe.DesignwaschangedtobuttweldandWalzwererequestedtosubmitaquotefortheonsitewelding.SinosteelinstructedWalzonthe10-NOV-14toprocurefittingsandcommenceinstallationofsiteweldedDN25/15mmpipework.Scheduleddurationissix(6)weeksaspreviouslyadvisedinnumerousWeeklyContractorMeetingsonsite.PotableWaterPipeworkSinosteelinstructedWalzonthe18-JUL-14toholdinstallationofallpotablewaterpipingtotalling1,200mtotwentysix(26)safetyshowersontheproject.InstallationhadnotcommencedatthistimeastherequiredfittingswereonCDU-026,howeverthesafetyshowershadbeeninstalledatthistime.Sinosteeladviseonthe11-NOV-14thepotablewaterholdisremovedandWalzcancommenceinstallation.Walziscurrentlyconductingareviewofthequantityofsuppliedfittingsandpipe.SynthesisPipelineNetwork(SPN)
HoldonInstallationSinosteelinstructedWalzonthe29-SEP-14toholdinstallationofpiperackinfour(4)locationstoallowcraneaccesstoinstalltwenty(20)E-Houses.Theholdeffectscompletionofthefollowingareas;GrindingMillAreaFloatation&MagneticSeparationAreaTableSeparationAreaSpiralSeparationAreaCu&PyriteConcentrateDewateringShedAreaMagnetiteConcentrateDewateringShedAreaCompressedAirStationFloatationReagentsAreaLimeStorageArea
ExpecteddeliveryofE-HousesMID-JAN-15.SPN–SitePhotographs
SinosteelHold–Section#1SPN–SitePhotographs
SinosteelHold–Section#2SPN–SitePhotographs
SinosteelHold–Section#3SPN–SitePhotographs
SinosteelHold–Section#4CV3201
RECLAIMTUNNELACCESSCivilHandoverofCV3201isstilloutstanding.Cudecocompletingexcavationactivities15-NOV-14.CivilWorkbythirdpartycontractorhavenotyetcommencedasat15-NOV-14.ForecastedhandoverforthemechanicalinstallationiscurrentlymidDEC-14.(AgreedConstructionBaselineScheduleis9-MAR-14)Walzhavecompletedandinstalledbeltsonallotherconveyorswiththeexceptionoffinalalignmentactivities.CV3201–RECLAIMTUNNELGrindingMillArea
Lubrication&DrainPipeworkAllGrindingMilllubricationanddrainpipeworkwastobedeliveredtositefullyfabricated.Thelubricationanddrainpipeworkwasdeliveredtositeonthe27-AUG-14onCDU-027,howeverwassuppliedasloosestainlesssteelflanges,fittingsandstandardlengthsofpipe.Walzwasrequestedtoprovideaquotationforweldingandfabricationofpipework.Sinosteelprovideisometricdrawingsoffive(5)pipelines.SinosteeladvisedWalz10-NOV-14Sinosteelwouldperformtheonsitefabricationandweldingofthepipework.SinosteelrequestedWalztoprovidetherequiredweldingequipmentandconsumablesforthiswork.SinosteeladviseduringContractorMeetingonthe10-NOV-14thefabricationprocesswilltake3-4Weeks.Sinosteelhavenotcommencedfabricationasat15-NOV-14.GrindingMillArea
Lubrication&DrainPipework
SitePhotographPipelineMarkers–ProjectWideRFI-1721MediumLabel(DN63andlarger)SmallLabel(UptoDN63mm)QtySupplied1,536147CDU-028QtyRequired
6,0003000Shortfall4,4642,8537,317QtyRequiredisbasedontheCudecoSpecificationforLineMarkersWalzrequestedpipelinemarkersonthe17-MAY-14inRFI-0466.PipelineMarkersweredeliveredtositeonthe24-OCT-14onCDU-028:WalzadvisedSinosteelonthe9-NOV-14inRFI-1721,thequantitysuppliedhasbeengrosslyunderestimated.AccessrequirementfortheinstallationoflinemarkerspreventsWalzfrominstallingwallgirtstothefollowingareas;Floatation&MagneticSeparationAreaTableSeparationAreaCu&PyriteConcentrateDewateringShedAreaMagnetiteConcentrateDewateringShedAreaMaterialSupplyIssue
Slip/FloatingFlangeBoltsSinosteeladviseonthe5-JUL-14thatallsuppliedslip/floatingflangeboltsareincorrectastheyaretooshortandwillbeRe-Supplied.Walz‘pinned’allslip/floatingflangestoenablepipeworkinstallationtoproceedaheadasperSinosteelinstruction.Re-Suppliedboltsarriveonsiteonthe27-AUG-14onCDU-027.Walzwererequiredtore-access358‘pinned’connectionstoinstalltheRe-Suppliedbolts.Lostproductivityandeffectsonsubsequentpump/pipeworkfinalalignmentactivitiesweresignificant.DesignConcern#1
PipeSupportsWalzissueNCR-0214onthe29-OCT-14outliningWalzconcerninrelationtothepipesupportsontheproject.ThetypicalpipesupportdesignbySinosteeldetails16mmholesinthebaseplateforM12x50mmGr4.6Boltstomaketheconnectiontostructuralsteel.Theholesinthestructuralsteelcolumnsare14mm.Walzalsonotedthattheactualbaseplateholes/slottedholesareupto17/18mmduetofabricationerrors/techniquesusedbySinosteelsupplierinChina.Thisissuecausesthewasherandnuttohaveinsufficientbearingcontactareatothebaseplate,andcan/hasresultedinsomeofthewashers/nutspassingthroughor‘folding’intotheholeovertime.Pipesupportsontheprojectarenowfailingundertheselfweightofthepipewithoutcarryinganyservices.DesignConcern#1
PipeSupportsDesignConcern#2
PipeworkConnectionsWalzissueSinosteelformalletterJ03429-LTR-0337-00onthe12-NOV-14outliningWalzconcernrelatingtoSinosteel’sPipeworkDesign.PipeworkisprimarilysupportedbytheVictaulicCouplingconnectionsbetweenpipespools.Thisdesigncausesasignificantamountofunduestressoneachcouplingwhichmaycauseleaksorevenfailureoftheconnection.ItiscommonthroughSinosteel’sdesigntoencounterupto5-10connectionsbetweensupports.WalznoteinVictaulicDesignData26.01,TheVictaulicCouplingManufacturer’smendationsstatethat“Nopipelengthshouldbeleftunsupportedbetweenanytwocouplings”.DesignConcern#2
PipeworkConnections
DesignConcern#3
PumpCasingsWalzissueSinosteelformalletterJ03429-LTR-0337-00onthe12-NOV-14outliningWalzconcernrelatingtoSinosteel’sPipeworkDesign.Walznotedallslurrypipeworkconnectingtopumpsuctionsanddischargesareprimarilysupportedbythepumpcasings.Thisdesignissuemaycausedamagetothepumpcasingsduringoperation.DesignConcern#3
PumpCasings
DesignConcern#4
ConveyorWalkwaysWalznotethatnomid-railhasbeendetailedontheconveyorsideofallwalkways.WalzbelievethisdoesnotcomplywithIndustry,andpossibly,AustralianStandards.ReferAS1657-2013:Fixedplatforms,walkways,stairwaysandladders–Design,constructionandinstallation.DesignConcern#4
ConveyorWalkwaysDesignConcern#4
ConveyorWalkwaysWalzholdconcernswithregardstotheminimalamountofsupportoftheconveyorgridmeshpanels.Allconveyorwalkwaygridmeshissupportedonlybychannelsteeloneithersideofthewalkwayswithoverlapaslittleas20mm.Walzbelievethisincreasesthechanceofapanelfallingiftheclipsshouldcomeloose.DesignConcern#4
ConveyorWalkwaysDesignConcern#4
ConveyorWalkwaysWalznotethatatallinterfacesbetweenconveyorwalkwaysand‘workshop’floorlevelsdonotmeetAustralianStandardsduetothedifferenceinheightsbetweengridmeshpanel
温馨提示
- 1. 本站所有资源如无特殊说明,都需要本地电脑安装OFFICE2007和PDF阅读器。图纸软件为CAD,CAXA,PROE,UG,SolidWorks等.压缩文件请下载最新的WinRAR软件解压。
- 2. 本站的文档不包含任何第三方提供的附件图纸等,如果需要附件,请联系上传者。文件的所有权益归上传用户所有。
- 3. 本站RAR压缩包中若带图纸,网页内容里面会有图纸预览,若没有图纸预览就没有图纸。
- 4. 未经权益所有人同意不得将文件中的内容挪作商业或盈利用途。
- 5. 人人文库网仅提供信息存储空间,仅对用户上传内容的表现方式做保护处理,对用户上传分享的文档内容本身不做任何修改或编辑,并不能对任何下载内容负责。
- 6. 下载文件中如有侵权或不适当内容,请与我们联系,我们立即纠正。
- 7. 本站不保证下载资源的准确性、安全性和完整性, 同时也不承担用户因使用这些下载资源对自己和他人造成任何形式的伤害或损失。
最新文档
- 2026年医疗机构自查报告(3篇)
- 园艺工测试题集与答案解析
- 2026年煤矿井下多气体传感器数据漂移AI实时补偿技术
- 2026年推土机操作证理论考试练习题【含答案】
- ISO 12614-162021 道路车辆液化天然气燃料系统部件第16部分热交换器汽化器标准立项发展报告
- ISO 7752-52021 起重机.控制布局和特性.第5部分桥式和龙门起重机标准立项发展报告
- 培训知识常见试题与精准答案
- 感控知识练习题及答案
- 2026年低压电工考试题库完整版及答案
- 2026版《煤矿安全规程》题库及答案
- 小学道德与法治新部编版二年级上册第一单元第4课第1课时 新中国的生日教案(2025秋)
- 乡镇卫生院外科培训课件
- 《内蒙古低空经济发展白皮书》
- GB/T 45873-2025信息技术车间数字孪生参考架构
- 家居室内设计课件
- 药厂脉动真空灭菌柜技术解析与应用
- 地下矿山动火作业安全管理规定 矿安【2023】149号
- 胎盘、死婴、死胎处理管理制度及处置流程
- 医疗器械经营质量管理规范培训2024
- (高二数学高分突破)第4章《数列》同步单元必刷卷(基础卷)解析版-副本
- 2024年江西省中考英语试卷试题真题及答案详解(精校打印)
评论
0/150
提交评论