LongBefore
TheRibbonIsCut
HowEarlyDecisionsShape
TheFateOfLarge-ScaleProjects
May2026
ByDevanshuMathur,AndreaNogara,Dr.NunoCouto,RichardElCheikh,MawaddaAbdan
GeneratedusingRunwayandFigma
BCG
BostonConsultingGrouppartnerswithleadersinbusinessandsocietytotackletheirmostimportantchallengesandcapturetheirgreatestopportunities.BCGwasthepioneerinbusinessstrategywhenitwasfoundedin1963.Today,
weworkcloselywithclientstoembraceatransformationalapproachaimedatbenefitingallstakeholders—empoweringorganizationstogrow,buildsustainablecompetitive
advantage,anddrivepositivesocietalimpact.
Ourdiverse,globalteamsbringdeepindustryandfunctionalexpertiseandarangeofperspectivesthatquestionthe
statusquoandsparkchange.BCGdeliverssolutions
throughleading-edgemanagementconsulting,technologyanddesign,andcorporateanddigitalventures.Weworkinauniquelycollaborativemodelacrossthefirmand
throughoutalllevelsoftheclientorganization,fueledbythegoalofhelpingourclientsthriveandenablingthemtomaketheworldabetterplace.
Contents
01UnprecedentedScale,
UnforgivingExpectations
02WhereOperationalRisk
IsFormed
03FourCaseStudies:How
OperationalPlanning
ShapesPerformance
•CaseStudy#1:FIFAWorldCup
Qatar2022
•CaseStudy#2:Expo2020Dubai
•CaseStudy#3:IstanbulAirport
•CaseStudy#4:Fontainebleau
LasVegas
04BCG'sAssetOps360:How
toRedefineOperational
ViabilityinCapitalPrograms
BOSTONCONSULTINGGROUPLONGBEFORETHERIBBONISCUT:HOWEARLYDECISIONSSHAPETHEFATEOFLARGE-SCALEPROJECTS4
UnprecedentedScale,
UnforgivingExpectations
Theworldhasneverbuiltlikethisbefore.
Capitalandinfrastructureinvestmentsnowoperateat
amultitrillion-dollarscale.In2026,it'sestimatedthatthetransport,energy,industrial,andresidentialsectorswill
attractover$7trillionincombinedcapitalinvestment.1
Andaccordingtothe2025GlobalCAPEXSurveyfromtheBostonConsultingGroup(BCG),94%oflarge-scaleprojectowners(thosethatspendatleast$5Bannually)expecttomaintainorincreasetheirinvestmentsoverthenext12
months.Atthesametime,54%ofrespondentsinthat
samesurveyreportthatpost-FIDdeliverychallengeshaveintensifiedoverthepastyear.SaudiArabiaalone,underVision2030,isdeployingmorethan$1trillionincapital
expendituresforlarge-scaleprojects.2
Yetthemoststrikingshiftisnotscale.Itisexpectations.
Assetsarenowexpectedtoperformfromdayone.Revenuemustrampuprapidly.Thetolerancefordisruption,whetherpolitical,financial,orreputational,isminimal.Themarginforunderperformancehasdisappeared.
Still,therecordoflarge-scaleprojectshasstruggled
tomeetthesedemands.Onlyaround1in12projectsisdeliveredontimeandonbudget,withcostoverrunsaveragingover60%oftheinitialbudget.3Schedule
slippageoftenreachesonetotwoyears.Berlin’s
BrandenburgAirport,forexample,openedmorethannineyearsbehindscheduleandover€4billionaboveitsoriginalbudget.4
Underpressuretorecovertimeandmoney,developers
oftencompresstesting,training,andcommissioning.
Operationalteamsaremobilizedlate.Systemsareexposedunderliveconditions,shiftingriskdirectlyintooperations.
Theconsequencesaresevere.Congestion,systemfailures,safetyincidents,reputationaldamage,regulatoryscrutiny,andprolongedstabilizationeffortsfollow.
Thesebreakdownsareoftenframedasexecutionfailures
atprojectdelivery.Yetthefactthattheyoccurconsistentlyacrosssectorsandgeographiessuggestssomethingdeeper.Failureisrarelycreatedjustbeforetheopening.Itis
embeddedearlier—indesigntrade-offs,sequencing
priorities,andgovernancechoicesmadelongbeforethefirstguestarrives.
Thispapershiftsthelensupstream.Itexamines
large-scaleprojectsacrosstheirlifecyclestounderstandhowoperationalriskisformed,compounded,and
ultimatelyrevealedunderliveconditions.Ratherthantreatingopeningdayasthestartingpointoffailure,
weinvestigatehowearlydecisionsshapeoperationalperformancewellbeforelaunch.
ThislensalsounderpinsBCG’songoingworkin
embeddingoperationalviabilityearlierinthelifecycleoflarge-capitalprojects.
1.2025,GlobalCAPEXSurvey,TheBostonConsultingGroup.
2.MayaElHachem,JuanFerrer,SophiaFrempongandIgorVukovic,2025,"Megaprojects:OneTrillioninCAPEXCreatingOneMillionFutureJobs,"Boston
ConsultingGroup,July8.
3.BentFlyvbjergandDanGardner,2023,"HowBigThingsGetDone,"PenguinRandomHouse.
4.KateConnolly,2020,“Wewerealaughingstock’:BerlinairportfinallyfinishedasCovidbites,”TheGuardian,October7.
BOSTONCONSULTINGGROUPLONGBEFORETHERIBBONISCUT:HOWEARLYDECISIONSSHAPETHEFATEOFLARGE-SCALEPROJECTS5
WhereOperationalRiskIsFormed
Operationalriskdoesnotbeginonopeningday.Itstarts
duringstrategydefinition,whenearlyassumptionsabout
demand,operatingmodels,andperformancetargetsareset.
Asaprojectmovesintodesignandconstruction,those
assumptionsaretranslatedintofixedlayouts,capacities,
andsysteminterfaces.Flexibilitynarrows.Decisions
becomestructural.Bythetimeaprojectreachestesting
anddelivery,budgetandschedulepressurehave
compressedreadinessactivities,asillustratedinExhibit1.
Onceaprojectentersliveoperations,accumulatedrisk
materializesquicklyandatscale.Operationalteamsshift
fromexecutiontocontainment.Manualinterventions
replaceautomation.Proceduralworkaroundssubstituteforsystemreliability.Extraordinaryeffortbecomesthenorm.
Atthispoint,theseconditionsareexpensivetomanage,
difficulttounwind,andhighlyvisibletoregulators,
stakeholders,and,mostimportantly,thepublic.The
implicationisclear:Theoperationallenscannotbeappliedatdeliveryalone.Instead,itmustbeembeddedearlier—atstrategy,design,andconstruction—whererisktakes
rootandislockedintothesystem.
EXHIBIT1
WhereOperationalRiskReallyBegins
High
OperationalRisk
Low
Unrealisticdemandand
peak-capacityassumptions
Compressedtimelinetodeliverproject
Undefinedgovernanceframework
Frequentpivotsinprojectvision
Noconceptofoperationstoanchordesigndecisions
Operatorsnotengagedearlyindesigndecisions
Demandnottranslatedtooperationalrequirements
Designoptimized
foraestheticsorcost,notoperability
Overlapofdesignandbuildefforts
Latedesignchangesdelayingconstructioncompletion
Systemintegrationgapsacrosscontractors
Constructionprioritiesoverridingoperationalsequencing
Afterconstruction,
constraintsarelockedinandoperational
riskpeaks:
Limitedtestingexposes
issuesclosetoopeningday
Budgetandscheduleoverrunsreduce
readinessscope
Lateopsonboardingcausesinconsistentservicelevels
ut
b
<>
b
v
s
W
l
<>
l
StrategyDesignConstruction
Testing&delivery
Go-live
(Opsstart)
Projectlifecycle
BOSTONCONSULTINGGROUPLONGBEFORETHERIBBONISCUT:HOWEARLYDECISIONSSHAPETHEFATEOFLARGE-SCALEPROJECTS6
FourCaseStudies:
HowOperationalPlanningShapesPerformance
Tounderstandhowearlyoperationalchoicesshape
real-worldoutcomes,weexaminefourlarge-scale
projectsthatmadefundamentallydifferentgovernanceandplanningdecisions.
1.FIFAWorldCupQatar2022(Qatar):Thisprojectembeddedoperationalconsiderationsfromstrategythroughconstruction.Designdecisionsreflected
operatingrealities,resultinginstableandcontrolledoperations.
2.Expo2020Dubai(TheUnitedArabEmirates):Thisprojectinstitutionalizedadetailedconceptofoperations(ConOps)andaccountabilitymodel,ledbythechief
operatingofficer(COO),earlyinthelifecycle.
WhenCOVID-19disruptedcoreassumptions,the
pre-establishedstructureenabledrapidadaptation.
3.IstanbulAirport(Turkey):Constrainedbyextremetimelines,thisprojectenteredoperationsbefore
constructionwascomplete.Oncetheprojectwaspublic,operationalstrainsurfacedimmediately.
4.FontainebleauLasVegas(TheUnitedStates):Thisprojectfacedmultiplestrategicresets.Asaresult,anewoperatingmodelwasimposedonlegacyinfrastructure.Redesign,construction,andactivationtimelinesgot
compressed.Andinitialoperationsbecamestrained.
BOSTONCONSULTINGGROUPLONGBEFORETHERIBBONISCUT:HOWEARLYDECISIONSSHAPETHEFATEOFLARGE-SCALEPROJECTS7
CaseStudy#1:FIFAWorldCupQatar2022
EXHIBIT2
FIFAWorldCupQatar2022:OperationsDesignedEarly,andThusDeliveredatScale
2011-2013
2014-2015
Demandforecasted
capacity
and
modeled
SupremeCommitteeformed,andWorldCupplanembeddedinQatarNationalVision2030
2017
2019
ClubWorldCuphosted
underfullFIFAoperatingstandards
Firststadiumsenteredlivetesting
2021
ArabCupreplicatedWorldCupconditionsacrossallsystems
2022
FIFAWorldCup2022held
2010
Eventawarded
Qatar2022standsasoneofthemostoperationally
successfulmegaeventsinhistory.UnlikepriorWorldCupsthatwereawardedtocountrieswithexistinginfrastructure,Qatarwonthe2010bidbasedonambition:65percentofthecountry’sinfrastructuredidnotyetexist.
Strategy:Fromtheoutset,theWorldCupwasembeddedwithinQatar’sNationalVision2030.In2012,a'SupremeCommittee'wasestablishedasanintegrateddelivery
authority,responsiblefordeliveringtheCupwhilealigningtheprojectwiththecountry'snationaldevelopment
agenda.Infrastructure,urbanplanning,transport,and
securitywerecoordinatedadecadebeforekickoff,turningtheeventintoanationaloperatingprogram.
Design:By2015,Qatarhadbuiltatournamentdemandmodelsimulatingupto3.5millionpeopleanddaily
movementsby800,000.5Themodelsimulatedfull
match-daydemandacrossflights,accommodations,
themetro,highways,fanzones,andstadiums.Real-timedashboardsvisualizedpressurepointshourbyhour.
Whenthresholdswerebreached,capacityandroutingwereadjusted—notafterkickoff,butyearsbefore.
Inparallel,operationalcapabilitywasbeingbuilt.The
JosoorInstitute,createdwiththeSDABocconiSchoolof
Managementin2013,trainedfutureWorldCupleaders
throughcoursesandliverolesatFIFAWorldCupBrazil
2014,UEFAEuro2016,andFIFAWorldCupRussia2018.6Operatorreadinessbegannearlyadecadebeforeopening,wellbeyondstandardeventtimelines.
ConstructionandTesting:Continuoussimulations
informeddesignandtranslateddirectlyintoconstruction.Eachnewlycompletedstadiumhostedliveeventsas
operationaltrials.In2017,theAmirCupfinalwasusedtotestnewWorldCupvenues;thistestrevealedentry-gatecompressionandpost-matchmetrosurges.In2019,the
FIFAClubWorldCupranfullFIFAprocedures;thistest
revealedgapsintransportcoordinationandaccreditation.In2021,theFIFAArabCupreplicatedacondensedWorldCupacrossalleightstadiums;thistestrevealedpeak
departurecongestionandfan-zoneoverflowpatterns.
Testingdrovecorrection.Gatesequenceswereredesigned.Metrocapacitywasextended.Escalationprotocolswere
tightened.Transportroutingwasrecalibrated.Asaresult,
5.JustusBonza,BenCraze,KnutHaase,MartinHalligan,MatthesKoch,andTobiasVlček,2024,“ControllingtheTransportDemandoftheFIFAWorldCup2022inQatar,”ResearchGate,January.
6.FIFA,2023,“JosoorInstitute:WorkforceDevelopment,”FIFAWorldCupQatar2022SustainabilityReport.
BOSTONCONSULTINGGROUPLONGBEFORETHERIBBONISCUT:HOWEARLYDECISIONSSHAPETHEFATEOFLARGE-SCALEPROJECTS8
Theeconomicsreflectedthisreadiness.WhereasBrazil
generated$4,826millionintotalFIFArevenue,7andRussiabroughtin$6,421million,8Qatardelivered$7,568million,9thehighestrevenueinWorldCuphistory.
Qatar2022succeedednotbecauseitperformedwellatdelivery.Itsucceededbecauseoperationalviabilitywasdesigned,tested,andprovenovera10-yearhorizon.
operationalviabilitywasconfirmedwellbeforetheevent’sofficialstart.
OperationalStart:Thecontrastwithpriortournamentswasclear:Brazil2014beganwithmetrosystemsthat
werelateanduntested.Russia2018facedfood-supplydisruptionsonopeningday.Qatar2022,ontheotherhand,wasfullycommissionedatlaunch.
7.FIFA,2015,“2014FIFAWorldCupBrazilFinancialOverview,”FIFAFinancialReport2014.
8.FIFA,2019,“2018FIFAWorldCupRussiaFinancialOverview,”FIFAFinancialReport2018.
9.FIFA,2023,“2019–2022CycleinReview:2022FinancialHighlights,”FIFAAnnualReport2022.
BOSTONCONSULTINGGROUPLONGBEFORETHERIBBONISCUT:HOWEARLYDECISIONSSHAPETHEFATEOFLARGE-SCALEPROJECTS9
CaseStudy#2:Expo2020Dubai
EXHIBIT3
Expo2020Dubai:BuilttoAdapt,ResilientUnderShock
2016-2018
Visitorjourneysmapped,andstaffing,security,medical,and
2014-2015
ConOpsestablished
withcleargovernanceframework
2020
COVID-19shockdelayedinitialopeningdate
2019
Operationalmanpowerrampedup
2021
Expo2020held
2013
Eventawarded
transportmodelsdeveloped
Expo2020Dubaideliveredasix-monthmegaeventunderunprecedenteddisruption.Butsuchresiliencedidnot
emergeduringacrisis;itwasengineeredyearsearlierthrougharobustoperatingmodel.
Strategy:Asearlyas2015,theorganizingcommittee
developedadetailedend-to-endConceptofOperations
(ConOps).ThisConOpsdefinedhowtheExpowould
functionondayone,day100,andday180.Everyserviceline(security,venuemanagement,foodandbeverage,
retail,transport,etc.)wasassignedownership,service
levels,escalationpathways,andcostparameters.
Operationalaccountabilitywascentralizedundera
COO-ledgovernancemodel.Asaresult,ConOpsbecamethereferenceagainstwhicheveryscopedecision,capacitythreshold,andtrade-offwastested.
Design:Initialforecastsprojected25millionvisitors,
supportedbyover30,000volunteers.10Theseprojections
weretranslatedintoservicelevelsandcapacitythresholds.In2016,ConOpshelpeddetailcustomerjourneysandmaparrival,screening,circulation,dwelltime,andexitflows.
Assumptionswereconvertedintoquantifiable
requirements:gatecapacity,clinicsizing,staffingratios,paymentinfrastructure,andovernightresetoperations.
ConstructionandTesting:Asdeliveryprogressed,
ConOpsgovernedsequencing,interfaces,andadjacencies.Fullend-to-endrehearsalscouldonlybeginoncevenues
andteamsweremobilized,whichhappenedasearlyas2019.Inparallel,simulationsandscenariotestingstress-testedcrowdsurges,emergencyresponse,
andcommandescalationunderpeakconditions.
ThenCOVID-19fundamentallyalteredeveryoperating
assumptionandprojection.Internationalarrivalsdropped.Healthscreeningbecamemandatory.Densitythresholdswerereduced.Workforceavailabilityfluctuated.
ButbecauseConOpshadalreadydonesomuchwork—definingeverythingfromservicelevelsandownershiptoescalationpathwaysandcapacitybaselines—thesystemdidnotrequireredesign.Itmerelyneededrecalibration.
Healthcontrolswereinsertedintoexistingentry
flows.Crowdlimitswereadjustedagainstestablished
thresholds.Staffingmodelswereresizedwithinpredefinedrolestructures.
Theoperatinglogicremainedstable;onlytheparameterschanged.
10.2022,“Over24millionvisitsasExpo2020Dubaiconnectsmindsandcreatesthefuture,”Expo2020DubaiOfficialWebsite,Dubai.
BOSTONCONSULTINGGROUPLONGBEFORETHERIBBONISCUT:HOWEARLYDECISIONSSHAPETHEFATEOFLARGE-SCALEPROJECTS10
OperationalStart:TheExpoopenedtothepublicin
2021,operatingcontinuouslyforsixmonths.Transportto
theExpowasintegratedwithDubai’sRoadsandTransportAuthority(RTA)throughdedicatedbusesandmetro
services.Acentralizedcontrolroomunifiedsecurity,police,fireservices,andtransportauthoritiesunderreal-time
commandoversight.
Despiteglobaltraveldisruptionandfluctuatingcapacityrestrictions,theExpowelcomedover24millionvisits.
Thelesson:operationalresiliencemustbeengineered
early.Whendisruptionreshapesdemandandconstraints,adefinedoperatingarchitectureabsorbstheshock.
Thesystemflexeswithoutlosingcontrol.
BOSTONCONSULTINGGROUPLONGBEFORETHERIBBONISCUT:HOWEARLYDECISIONSSHAPETHEFATEOFLARGE-SCALEPROJECTS11
CaseStudy#3:IstanbulAirport
EXHIBIT4
IstanbulAirport:RushedIntoOperation,BreakdownsWhenGoingLive
2015-2017
Conceptandcapacity
defined,andconstructionstarted
2022-2024
Operationsstabilized
2019
MigratedfulloperationstoIstanbulAirportunder
IstanbulGrandAirport(IGA)
2018
Limitedoperations
2020-2022
COVID-19impactamplified(early
operationalstrain)
2014
Projectawarded
launched,constructionconcluded
IstanbulAirport,an$11.7billionlarge-scaleproject,11enteredoperationswhileconstruction,commissioning,andsystemintegrationwerestillongoing.
Strategy:In2014,theTurkishgovernmentlaunched
theprojecttopositionIstanbulasaglobalaviationhub.
AtatürkAirporthadreachedcapacityanddemandwas
risingsharply.Strategicdecisionsaboutscaleandambitionweresetcentrallyandmovedrapidlyintodesign.The
airportwasdesignedforaninitialcapacityof90millionpassengersannually,withlong-termexpansionto200
million,positioningitamongthelargesthubsinEurope.
Design:Thisambitiontranslatedintoexceptional
complexity.Forexample,atypicallargeairportoperatesfewerthan3,000airfieldgroundlights;Istanbulwas
designedforapproximately35,000.12What’smore,suchcomplexityrequiredcoordinationwithairlines,groundhandlers,andEurocontrol.Finally,thelaunchdateof
2018compresseddevelopmentcycles.Asconstructionprogressed,keyoperationalinterdependencies
continuedtoevolve.
Construction:Constructionprogressedwhileaspectsofthedesignwerestillbeingfinalized.Layoutrevisionswere
incorporatedwhileconstructionproceededonsite.Withlimitedflexibilitytopauseorresequence,momentumanddeadlinestookprecedenceoveroperationalalignment.
TestingandDelivery:InOctober2018,Phase1
operationsstartedevenasadditionalrunways,
terminalcapacity,andexpansionphasesremained
underdevelopmentaspartofthebroadermasterplan.Mandatorytechnicalcommissioningwascompleted,
butwithoutfulloperationalrehearsals.Largeportionsoftheterminalremainedunfinished,sotheairportinitiallyhandledonly20–30flightsperday.
Theresultswerepredictable:Passengersatisfaction
plummeted.Problemsemergedinaccess,circulation,
baggagehandling,routing,andfacilityreadiness.The
AirportOperationalDatabase(AODB)wasnotfully
stabilized;airlinesandgroundhandlersoperatedacross
separatesystems,thusexposingdatamisalignmentunderliveconditions.OperationalcoordinationwassubsequentlyconsolidatedunderanAirportOperationsControlCentre(AOCC),providingunifiedoversightacrossairlines,groundhandlers,andairportsystems.
11.2018,“Erdoganopensnew‘Istanbulairport,’Turkey’sbiggest,”Reuters,October29.
12.2017,“ADBSafegateToCreateMostIntelligentAirfieldAtIstanbulAirport,”AviationWeek.
BOSTONCONSULTINGGROUPLONGBEFORETHERIBBONISCUT:HOWEARLYDECISIONSSHAPETHEFATEOFLARGE-SCALEPROJECTS12
OperationalStart:InApril2019,allflightswere
transferredfromAtatürktoIstanbulAirport.Operationalstrainbecamevisibleimmediately:Flightsarrivedwithoutluggage.Layoutinefficiencies,incompletemoving
walkways,andextendedtaxitimeaddedtothestrain.Basicserviceslaggedexpectations.Withnometro
connectioninplace,accessreliedentirelyonroad
transport,thuscreatingcongestionandmissedflights.Negativemediacoverageexacerbatedthesituation.
InMarch2020,theCOVID-19pandemicbroughtasharpdropintraffic,slowingoperationsuntil2022.Thisperiod
ofreduceddemandprovidedtimetocontinuedevelopinginfrastructureandstabilizeoperations.Overtime,
operatorsstabilizedperformance.Today,theairport
handlesapproximately80millionpassengersannually.
Thelessonisstructural:IstanbulAirportdidnotfailat
opening;itabsorbedoperationalriskthathadaccumulatedacrossearlierphases.Thecostofembeddingoperations
latewaspaidinpublic.
BOSTONCONSULTINGGROUPLONGBEFORETHERIBBONISCUT:HOWEARLYDECISIONSSHAPETHEFATEOFLARGE-SCALEPROJECTS13
CaseStudy#4:FontainebleauLasVegas
EXHIBIT5
FontainebleauLasVegas:DormantforaDecade.OperationalStrainatRestart
2009
Ownershiptransitioned,andprojectwasputon
2017
Ownershiptransitioned,
resumingdesignand
constructionundernewvision
2008-2009
Financialcrisiscaused
bothconstructiontohaltandbankruptcy
2021-2023
Ownershiptransitioned,finalizingconstructionandopeningtheresort
2006
Projectlaunchedasluxurycondo-hotel
2020
COVID-19shock
stalledtheproject
hold
Afternearlytwodecadesofinterruptionandownershipchanges,FontainebleauLasVegasopenedinDecember2023asa$3.7billion13integratedresort.Itseventual
launchwasnotthecontinuationofalineardevelopmentcycle,buttheculminationofmultipleresetsresulting
frommultipleownershipchanges.Theprojectillustrateshowachangeinprojectvision,executedonpartially
completedinfrastructure,jeopardizesthesuccessful
launchandoperationsofalargedevelopmentproject.
Strategy:Theprojectwasinitiallylaunchedin2006
underFontainebleauDevelopment,withtheambition
tointroducemodernluxurytoLasVegas.Theprogramcombinedhospitality,gaming,retail,foodandbeverage,andresidentialcondos.LocatedaboutthreekilometersnorthoftheStrip,thethesiswasproduct-led:Auniqueresortwouldcompensateforthedistancefromcore
footfallintheVegasStrip.
Constructionbeganin2007.However,duringthe2008
financialcrisis,thedeveloperfiledforChapter11.Atthatstage,thecorestructurewaslargelycomplete,butinteriorworks,back-of-houseareas,andlife-safetysystemswereunfinished.
Theprojectthenchangedownershipthreetimes:
1
2
3
In2009,afterbankruptcy,theprojectwassoldandremaineddormant.
In2017,newownershiprelaunchedtheassetas“TheDrewLasVegas,”pivotingtowardaconvention-ledgamingresort.
In2021,afterCOVID-19,FontainebleauDevelopmentreacquiredthepropertyandpositioneditasaluxuryintegratedresort.
Design:Initialdesignproceededconventionally.However,achangingvisionledtocontinuousadjustmentstothe
designdespiteconstructionprogress.Designdecisionswereconstrainedbyexistingstructuresandpreviouslyinstalledsystems.
Forexample,asubstantialredesignwasrequiredin2021toalignthecoreandshellwithupdatedluxurypositioningandnewcoderequirements.Residentialcondolayouts
werereconfiguredintohospitalityrooms.Publicspacesandthebackofhouseweremodernizedafteryears
ofdormancy.
13.MattVillano,2023,“Fontainebleauopens$3.7-billionLasVegasStriphotel,”CNNTravel,October25.
BOSTONCONSULTINGGROUPLONGBEFORETHERIBBONISCUT:HOWEARLYDECISIONSSHAPETHEFATEOFLARGE-SCALEPROJECTS14
ConstructionandTesting:WhenFontainebleau
Developmentrepurchasedtheassetin2021,itsetthegoaltoopenby2023.Asaresult,timelineswerecompressed,
anddesign,construction,andoperationalreadinesseffortsproceededconcurrently.
Onceconstructionwasfinalized,theprojectteamhad
lessthantwomonthstogetupandrunning.Duringthis
period,theyonboardedandtrainedmorethan6,500
teammemberswhilesimultaneouslyresolvinglast-minuteissues(includingincidentssuchaspipefailuresduring
testing).Unsurprisingly,fulloperationalreadinesswasnotachievedbeforeopeningday.
OperationalStart:After16yearsofdevelopment,
FontainebleauLasVegasdebutedonDecember13,2023.Despiteagrandopeningthatfeaturedcelebrities,early
operationsstruggled.Thepropertyunderperformed
againsttargets,withvisibleunderutilizationinboththehotelandgamingfacets.Withinmonthsofopening,
workforceandexecutiveturnoveroccurred,includinglayoffsofdozensoftable-gamedealers.14
Guestsleftmixedreviewsoftheresort.Whilesomepraisedthedesignandqualityoftheamenities,otherscriticized
inconsistentserviceandpoorvalueformoney.Guests
alsoreportedlonginternalwalkingdistances(duetothelayoutconfiguration).Andreportsshoweddiscrepanciesincheck-intimesandroomassignmentsaswellas
housekeepinginconsistencies.
FontainebleauLasVegasshowswhathappenswhen
multiplechangesaremadetoanasset’svisionand
strategy:Operationalstrugglesmaterializeateveryturn.Moralesuffers.Underperformanceisinevitable.
14.DavidDanzis,2025,“MoreemployeecutsonLasVegasStripascasinolaysoff‘dozens’ofdealers,”LasVegasReviewJournal,May28.
BOSTONCONSULTINGGROUPLONGBEFORETHERIBBONISCUT:HOWEARLYDECISIONSSHAPETHEFATEOFLARGE-SCALEPROJECTS15
BCG'sAssetOps360:Howto
RedefineOperationalViabilityinCapitalPrograms
Thepatternacrossthesefourcasesisconsistent.Projectsthatperformfromdayonearenotbettermanagedat
launch.Theyarebetterdesignedfromthestart.
Qatar2022didnotsucceedbecauseitsoperationsteamwasexceptionalonopeningday.Itsucceededbecause
operationalviabilitywastreatedasadesignparameterforoveradecade.Expo2020didnotabsorbaglobal
pandemicthroughimprovisation.Itabsorbeditthroughagovernancearchitecturethatwasalreadyinplace.
Whereprojectshavestruggled,thefailurewasrarelycreatedatdelivery.Theriskaccumulatedearlier—instrategyanddesign—andwassimplyrevealedwhenoperationsbegan.
Theimplicationisstructural,notcultural.Operationalviabilitycannotbeboltedonattheend.Itmustbe
embeddedateverystage,fromstrategythrough
construction,whereassumptionsareset,trad
温馨提示
- 1. 本站所有资源如无特殊说明,都需要本地电脑安装OFFICE2007和PDF阅读器。图纸软件为CAD,CAXA,PROE,UG,SolidWorks等.压缩文件请下载最新的WinRAR软件解压。
- 2. 本站的文档不包含任何第三方提供的附件图纸等,如果需要附件,请联系上传者。文件的所有权益归上传用户所有。
- 3. 本站RAR压缩包中若带图纸,网页内容里面会有图纸预览,若没有图纸预览就没有图纸。
- 4. 未经权益所有人同意不得将文件中的内容挪作商业或盈利用途。
- 5. 人人文库网仅提供信息存储空间,仅对用户上传内容的表现方式做保护处理,对用户上传分享的文档内容本身不做任何修改或编辑,并不能对任何下载内容负责。
- 6. 下载文件中如有侵权或不适当内容,请与我们联系,我们立即纠正。
- 7. 本站不保证下载资源的准确性、安全性和完整性, 同时也不承担用户因使用这些下载资源对自己和他人造成任何形式的伤害或损失。
最新文档
- 环境正义与气候技术革新论文
- 一年级数学下册《跳绳》教学设计
- CN115752478B 一种基于路侧导引的露天矿区多车协同装载路径规划方法 (北京踏歌智行科技有限公司)
- 2026年人力资源三级复习题测复习题附答案
- 2026年汽车维修工(中级)职业技能鉴定模拟试题及答案解析
- 2026年包头社工面试题库及答案
- 2026年燃气安全生产企业主要负责人考试竞赛测试练习题附答案
- (2025年)护理技能大赛理论试题及答案
- 2026年电大会计电算化理论考试题题库及答案
- 绿色地球从我做起(教案)-小学生植树节主题班会
- 人工智能+智慧城市停车场系统布局可行性分析报告
- 儿童重症早期康复介入的临床实践指南解读课件
- 皮疹护理个案汇报
- 超声图像质量评价标准与实施细则
- DB32∕T 2060-2024 单位能耗限额
- 企业易制毒化学品管理(企业)
- JG/T 574-2019纤维增强覆面木基复合板
- 租船意向协议书
- 肺癌伴心衰的护理
- 回扣承诺协议书范本
- JC∕T 2558-2020 透水混凝土标准规范
评论
0/150
提交评论