1、Chapter 4 The Contractor, Nominated Subcontractors, Staff and Labour,4.1 The Contractor,Definition of Contractor :the person(s) named as contractor in the Letter of Tender accepted by the Employer and the legal successors in title to this person(s).,THE TRINITY OF THE EMPLOYER, ENGINEER, CONTRACTOR,
2、contractor,employer,engineer,Contract relationship,Contract relationship,Working relationship*,The contractor gets paid for the work he performs and the employer gets the work he is paying for.,Contractors general obligations4.1,1.The contractor shall design (to the extent specified in the contract)
3、, execute and complete the works in accordance with the contract and with the engineers instructions, and shall remedy any defects in the works.,2.The contractor shall provide the Plant and Contractors documents specified in the contract, and all contractors personnel, goods, consumables and other t
4、hings and services.,3.The contractor shall be responsible for the adequacy, stability and safety of all site operations and of all methods of construction.,4.The Contractor shall submit details of the arrangements and methods which the Contractor proposes to adopt for the execution of the Works,5.If
5、 the Contractor shall design any part of the Permanent Works, the Contractor shall comply with sub-paragraph (a)(d),1.language for communication:交流语言 2.as-built document:竣工文件 3.opration and maintenance manuals: 操作和维护手册,The Contractor shall obtain (at his cost) a Performance Security for proper perfo
6、rmance, in the amount and currencies stated in the Appendix to Tender.,保函是一种第三方的经济担保,在符合支付条件下,由银行或保险公司出具。用以担保在合同下合同权利和义务的顺利完成,由合同一方提出要求另一方通过第三方的担保,向合同一方提供合同义务的履行保障。如果另一方没有按照合同的条款或要求履行合同,或有任何违约行为,或在建设期间面临清算,破产,合同一方有权根据保函的条件,向第三方提出赔偿或承担相应的合同违约责任。,Performance Security4.2,Please answer the following que
7、stions: 1.When shall the Contractor deliver the Performance Security? 2.Who shall issue the Performance Security? And what form? 3.What is valid period of the Performance Security? 4.What conditions shall the Employer make a claim under the Performance Security?,1.entity:实体 2.Performance Certificate
8、(Sub-Clause11.9) 3.expiry date:到期日,期满日期,Contractor shall not subcontract the whole of the works. The Contractor shall be responsible for the acts or defaults of any Subcontractor, as if they were the acts or defaults of the Contractor. Unless otherwise stated in the Particular Conditions: 承包商就分包商的违约
9、承担连带责任,Subcontractors4.4,(a) the Contractor shall not be required to obtain consent to suppliers of Materials, or to a subcontract for which the Subcontractor is named in the Contract; 承包商在选择材料供应商或向合同中指明的分包商进行分包时,不需要获得同意 (b) the prior consent of the Engineer shall be obtained to other proposed Subco
10、ntractors; 对其他建议的分包商应取得工程师的同意,(c) the Contractor shall give the Engineer not less than 28 days notice of the intended date of the commencement of each Subcontractors work, and of the commencement of such work on the Site; and 承包商应该至少在28天前将每个分包商工作的拟定开工日期和该工作在现场的拟定开工日期通知工程师 (d) each subcontract shall
11、include provisions which would entitle the Employer to require the subcontract to be assigned to the Employer or in the event of termination. 每个分包合同应该包括,雇主有权根据第4.5款或者如果雇主终止合同时根据第15.2款,将分包合同转让给雇主的规定。 assign: 分派,选派,分配;归于,归属;法律 把(财产,权利、利息)从一人转让给另一人;把编制 n.常用复数法律受让人,接受财产等转让的人,受托者,The Contractor shall set
12、 out the Works in relation to original points, lines and levels of reference specified in the Contract or notified by the Engineer. The Contractor shall be responsible for the correct positioning of all parts of the Works, and shall rectify any error in the positions, levels, dimensions or alignment
13、 of the Works.,The Employer shall be responsible for any errors in these specified or notified items of reference, but the Contractor shall use reasonable efforts to verify their accuracy before they are used.,Setting Out4.7,Progress Reports4.21,Unless otherwise stated in the Particular Conditions,
14、monthly progress reports shall be prepared by the Contractor and submitted to the Engineer in six copies. The first report shall cover the period up to the end of the first calendar month following the Commencement Date. Reports shall be submitted monthly thereafter, each within 7 days after the las
15、t day of the period to which it relates. 除非专用条件中另有说明,承包商应编制月进度报告,一式六份提交给工程师。第一次报告所包含的期间,应从开工日期起至紧随开工日期的第一个月历的最后一天止(即应从开工日期起至当月的月底止)。此后应每月提交一次报告,在每次报告期最后一天后7日内报出。,Reporting shall continue until the Contractor has completed all work which is known to be outstanding at the completion date stated in the
16、 Taking-Over Certificate for the Works. 报告应持续至承包商完成了工程接收证书上注明的竣工日期时未完成的全部工作(全部扫尾工作)为止。,Each report shall include: (a) 设计(如有时)、承包商的文件、采购、制造、货物运达现场、施工、安装和调试的每一阶段以及各指定分包商(在第5条【指定分包商】中定义的)实施工程的这些阶段进展情况的图表与详细说明; (b) 反映制造和现场进展状况的照片;,(c) 与每项主要永久设备和材料制造有关的制造商名称、制造地点、进度百分比,以及以下各项的实际或预期日期: (i) 开始制造; (ii) 承包商的
17、检查; (iii) 检验;以及 (iv) 运输和到达现场,(d) 在第6.10款【承包商的人员和设备的记录】中描述的详细情况; (e) 材料的质量保证文件、检验结果及合格证的副本; (f) 依据第2.5款【雇主的索赔】和第20.1款【承包商的索赔】颁发的通知清单;,(g) 安全统计,包括涉及环境和公共关系方面的任何危险事件与活动的详情;以及 (h) 实际进度与计划进度的对比,包括可能影响按照合同完工的任何事件和情况的详情,以及为消除延误而正在(或准备)采取的措施。,Definition of Nominated Subcontractor: a subcontractor who is sta
18、ted in the contract as being a nominated Subcontractor, or whom the Engineer instructs the Contractor to employ as a Subcontractor.,4.2 Nominated Subcontractors,The Contractor shall not be under any obligation to employ a nominated Subcontractor against whom the Contractor raises reasonable objectio
19、n by ,an objection shall be deemed reasonable if it arises from any of the following matters ,unless the employer agrees to indemnify the contractor against and from the consequences of the matter. 有义务做 产生于、起因于 保障某人免于,Objection to Nomination 5.2,下列情况(但不限于)被认为是合理的理由: (a)有理由相信分包商没有足够的能力、资源或资金实力; (b)分包
20、合同没有规定,指定分包商应保障承包商免于承担由指定分包商的任何疏忽或货物误用导致的责任;或 (c)分包合同没有规定,指定分包商对所分包工程,应该: (i)承担分包工程范围的义务和责任,使承包商可以免除其在分包工程项下的义务和责任,以及 (ii)保障承包商免于由于分包商没能按照合同实施分包工程而导致的所有义务和责任。,The Contractor shall pay to the nominated Subcontractor the amounts which the Engineer certifies to be due in accordance with the subcontract
21、. These amounts plus other charges shall be included in the Contract Price in accordance with subparagraph (b) of Sub-Clause 13.5 Provisional Sums, except as stated in Sub-Clause 5.4 Evidence of Payments.,Payments to nominated Subcontractor 5.3,Before issuing a Payment Certificate which includes an
22、amount payable to a nominated Subcontractor, the Engineer may request the Contractor to supply reasonable evidence that the nominated Subcontractor has received all amounts due in accordance with previous Payment Certificates, less applicable deductions for retention or otherwise. Unless the Contrac
23、tor: 1.定语从句:在发出包含应付给指定分包商金额的付款证书前 2.宾语从句:证明指定分包商已收到按照此前付款证书应付的、适当的扣除保留金或其他扣除后的所有金额。,Evidence of Payments 5.4,1.1.4.11“retention money” means the accumulated retention moneys which the Employer retains under Sub-Clause 14.3 and pays under Sub-Clause 14.9 保留金:为了确保在施工阶段,或在缺陷责任期间,由于承包商未能履行合同义务,由业主(或工程师)
24、指定他人完成应由承包商承担的工作所发生的费用。 FIDIC合同条件规定,保留金的款额为合同总价的5,从第一次付款证书开始,按期中支付工程款的10扣留,直到累计扣留达到合同总额的5止。,保留金的支付(退还)一般分两次进行。当颁发整个工程的接收证书时,将一半保留金退还给承包商;当工程的缺陷责任期满时,另一半保留金将由工程师开具证书付给承包商。如果工程的缺陷责任期满时,承包商仍有未完工作,则工程师有权在剩余工程完成之前扣发他认为与需要完成的工程费用相应的保留金余款。,思考题一,FIDIC合同条件规定,保留金是在( )时,从承包商应得款项中按投标书附件规定比例扣除的金额。 (A) 支付预付款 (B)
25、中期付款 (C) 竣工结算 (D) 最终支付 参见Sub-Clause 14.3(c),B,思考题二,在FIDIC合同条件下,某项工程的合同保留金总额为300万元,当获得一个区段的工程接收证书时,该区段的合同价值占总工程最终估算价的30%,则应返还的保留金是( )万元。 A 36 B 60 C 45 D 18 参见Sub-Clause 14.9,D,14.9保留金的支付 当已颁发工程接收证书时,工程师应确认将保留金的前一半支付给承包人。如果某分项工程或部分工程颁发了接收证书,保留金应按一定比例予以确认和支付。此比例应是该分项工程或部分工程估算的合同价值,除以估算的最终合同价格所得比例的五分之二
26、(40%)。,分析:,分两次返还,第一次时颁发工程接受证书后,将保留金的一半支付给承包商,如果只限于一个区段或一部分,则返还金额=保留金的一半*移交部分的估算价/最终合同的估算价*40% ,保修期满颁发履约证书后,剩余保留金偿还 所以:返还保留金=300/2*30%*40%=18 万元,Unless (a) and (b) then the Employer may (at his sole discretion) pay, direct to the nominated Subcontractor, part or all of such amounts previously certifi
27、ed (less applicable deductions) as are due to the nominated Subcontractor and for which the Contractor has failed to submit the evidence described in sub-paragraphs (a) or (b) above. The Contractor shall then repay, to the Employer, the amount which the nominated Subcontractor was directly paid by t
28、he Employer. discretion:慎重,慎重;考虑周到;判断力,辨别力;自行决定的自由,指定分包商 1.概念:由业主(或工程师)指定、选定,完成某项特定工作内容并与承包商签订分包合同的分包商。 2.与一般分包商处于相同的合同地位,受承包商的监督、协调。,3.特点(与一般承包商的差异) 选择分包单位的主体不同 指定:业主方,须经总承包商确认 一般:承包商,经业主方核准认可 分包合同工作内容不同 指定:不属于承包商完成的工作范围 一般:承包商承包工作范围的一部分,工程款的支付开支项目不同 指定:从暂定金额内开支 一般:从清单中相应工作内容项内支付 业主对分包商利益的保护不同 指定:在合同条件中列有保护指定分包商的条款 一般:没有保护条款 承包商对分包商违约承担责任的范围不同 指定:承包商不承担指定分包商的违约责任 一般:承包商就分包商的违约承担连带责任,1.make arrangement for 2.rates of wages conditions of labour 3.locally recognized days of rest living quarters 4.t
温馨提示
- 1. 本站所有资源如无特殊说明,都需要本地电脑安装OFFICE2007和PDF阅读器。图纸软件为CAD,CAXA,PROE,UG,SolidWorks等.压缩文件请下载最新的WinRAR软件解压。
- 2. 本站的文档不包含任何第三方提供的附件图纸等,如果需要附件,请联系上传者。文件的所有权益归上传用户所有。
- 3. 本站RAR压缩包中若带图纸,网页内容里面会有图纸预览,若没有图纸预览就没有图纸。
- 4. 未经权益所有人同意不得将文件中的内容挪作商业或盈利用途。
- 5. 人人文库网仅提供信息存储空间,仅对用户上传内容的表现方式做保护处理,对用户上传分享的文档内容本身不做任何修改或编辑,并不能对任何下载内容负责。
- 6. 下载文件中如有侵权或不适当内容,请与我们联系,我们立即纠正。
- 7. 本站不保证下载资源的准确性、安全性和完整性, 同时也不承担用户因使用这些下载资源对自己和他人造成任何形式的伤害或损失。
最新文档
- 电梯采购安装管理制度
- 电梯采购管理制度
- 直接采购内控制度
- 财务采购付款审批制度
- 财政采购一体化管理制度
- 超市水果采购员工作制度
- 超市采购现场管理制度
- 路桥采购信息共享制度
- 软体家具采购流程制度
- 酒店物资采购管理制度及工作流程
- 2026年消防工作计划及重点整治工作
- 2025年提前招生社会工作笔试题及答案
- 中国精神分裂症等防治指南2025版
- 生产计划与控制培训课件
- 2025广东深圳市优才人力资源有限公司招聘聘员8人(派遣至龙城街道)备考题库附答案
- 2025年智能制造工厂自动化升级项目可行性研究报告
- 医院人事科日常工作规范及操作流程
- 国家基层糖尿病防治指南(2025年)学习与解读
- 2025年六盘水辅警协警招聘考试真题及答案详解(名校卷)
- 2025年江苏省事业单位招聘考试综合类专业能力测试试卷计算机类
- 《医疗机构静脉用细胞毒性药物调配质量管理工作规范(第2版)》
评论
0/150
提交评论