1SiteReportofAuchanNingboXinxingProject欧尚超市宁波新星店现场报告23EastFacade东立面4SouthFacade南立面5WestFacade西立面6NorthFacade北立面B2地下二层Re-installationofM&EandFFworkisongoing.
机电、消防重新安装。B2地下二层Wallmasonryisongoing.墙体砌筑正在进行。B1地下一层Theinstallationoflightingisongoing.
灯具正在安装。1F地上一层Theinstallationofairductisongoing.
风管正在安装。2F地上二层Wallmasonryisongoing.墙体砌筑正在进行。2F地上二层TheinstallationofFFpipeisongoing.
消防管正在安装。3F地上三层Theinstallationofairductisongoing.
风管正在安装。4F地上四层TheM&Eworkbegins.
开始机电安装。4F地上四层Wallmasonryisongoing.墙体砌筑正在进行。Façade外立面TheinstallationofFacadecurtainframeisongoing.外立面幕墙龙骨正在安装。SteelStructure钢结构Thehoistingofsteelbeamsisongoing.钢梁正在吊装。Theinstallationofsteeldeckisongoing.钢结构楼承板铺装正在进行。SteelStructure钢结构19Mainstructurecompleted
100%主体结构完成100%Steelstructureworkcompleted60%
钢结构完成60%Wallmasonrycompleted75%
砌体完成75%M&Eworkcompleted25%
机电完成25%FFSworkcompleted20%
消防完成20%PhaseIIConstructionSchedule二期工程进度20Mainstructurecompleteon28thSeptember
2013
2013年9月28日主体结构完成Steelstructurecompleteon30thNovember
2013,willbedelayed17days.计划2013年11月25日钢结构完成,将滞后17天。Constructioncompleteon31thDecember2013计划2013年12月31日完成施工。ForFFAcceptance,waitingforDAItoconfirmthepowerequipmentssupplyandPowerBureautoconfirmthedateofformalpowersupplyopening.
关于消防验收,等待非直采确认供电设备的供应以及供电局确认正式用电的开通日期。PhaseIIConstructionSchedule二期工程进度Inthisyear,20meetingshasbeenheldamongtechnical,construction,gallerydepartment(on01/14、02/02、03/07、03/22、03/28、03/29、04/17、05/14、05/21、05/31、06/11、06/21、07/12、07/16、07/24、07/31、08/28、09/12、09/13、09/26),discussingallthemattersneededtobeconfirmedbygallery.Sofar,still7notconfirmed,pleaseseethelistmemobelow.今年,技术部、工程部、招商部门共同召开了20次的会议(分别在01/14、02/02、03/07、03/22、03/28、03/29、04/17、05/14、05/21、05/31、06/11、06/21、07/12、07/16、07/24、07/31、08/28、09/12、09/13、09/26),讨论了所有需要招商部门确认的事宜。截止目前,还有7条没有得到确认,详见后面的清单。AboutGallery关于招商Tobeconfirmed1/4ItemDescriptionsActionPlanresponsiblePartySchedulepriorityDeadlineRemarkImpact1confirmationforcommerciallayoutUpdatedDetaileddesignbaseonthefinallayoutGalleryTechnical2013/1/15-2013/1/23125-Jan-13Finishedonthe25thMarch2013
2PowercapacityfortenantsconfirmationUpdatedDetaileddesignGallery2013/1/15-2013/1/23125-Jan-13Finishedonthe25thMarch2013Constructiondrawing3monthdelayed3DesignSpec/parameter/interfaceconfirmationneedtobeincludedindetaileddesignGallery2013/1/25-2013/2/528-Feb-13Finishedonthe25thMarch2013Constructiondrawing3monthdelayed4ShoppingmallOperationandpropertymanagementrequirementsOperationandmanagementfacilitiesrequirementstobeinputintothedesignGallery2013/2/15-2013/4/20125-Mar-13Designconditionsandreservationneedtobeconfirmedbefore2013/1/31Constructiondrawingdelay5ITandmunicationfortenantsSystemscheme/scope/functionspecGallery2013/3/15-2013/4/3111-Jun-13mechanicalroomreservedConstructiondrawingdelay6BuildingAutomaticManagementsystemSystemscheme/scope/functionspecGallery2013/3/15-2013/4/3111-Jun-13mechanicalroomreservedConstructiondrawingdelay7SecurityandaccesscontrolsystemSystemscheme/scope/functionspecGallery2013/3/15-2013/4/3111-Jun-13mechanicalroomreservedConstructiondrawingdelay8PublicaddresssystemSystemscheme/scope/functionspecGallery2013/3/15-2013/4/3111-Jun-13mechanicalroomreservedConstructiondrawingdelayColorinyellowmeansdelayTobeconfirmed2/4ItemDescriptionsActionPlanresponsiblePartySchedulepriorityDeadlineRemarkImpact9CATVforpublicandtenantsSystemscheme/scope/functionspecGallery2013/3/15-2013/4/3111-Jun-13NotconsiderednowConstructiondrawingdelay10Wi-FiandWirelesscoverageSystemscheme/scope/functionspecGallery2013/3/15-2013/4/3111-Jun-13
11gasneedsandapplicationforTenantsconfirmationengagethedetaileddesignerGallery2013/3/1-2013/3/31125-Apr-13Total600M/hourreservedat20130202
12ShoppingMallinformation/communicationinteractsystemneedspecificstudyanddesignwithneedsconfirmedGallery2013/3/15-2013/4/311-Jun-13
13SMcustomerflowcalculationSystemneedspecificstudyanddesignwithneedsconfirmedGallery2013/3/15-2013/4/321-Jun-13
14ParkingmanagementsystemneedspecificstudyanddesignwithneedsconfirmedGallery2013/4/15-2013/5/3021-Jul-13
15TenantsconstructionmanagementandcommonzoneoperationprotocolandinterfacedetailedmanagementapproachmustbedefinedbeforeinteriorworkstartGallery2013/5/15-2013/7/30225-Sep-13
16TenantsconstructionpermitsdetailedmanagementapproachmustbedefinedbeforeinteriorworkstartGallery2013/7/15-2013/8/30225-Sep-13
ColorinyellowmeansdelayTobeconfirmed3/4ItemDescriptionsActionPlanresponsiblePartySchedulepriorityDeadlineRemarkImpact17TenantsopeningconditionsbySMdetailedmanagementapproachmustbedefinedbeforeinteriorworkstartGallery2013/7/15-2013/8/30225-Sep-13
18TrolleyflowlimitationdesignforthespaceandfacilitiesofthebarriersGallery2013/1/15-2013/1/23325-Jan-13
19SMStaffparking&accesscontrolneedindependsignandinputtoSecuritiessystemGallery2013/3/15-2013/4/3141-Jun-13Finishedonthe25thMarch2013Constructiondrawing3monthdelayed20stormwaterrecyclingReviewandconfirmtheproposalUMAN2013/3/15-2013/4/31415-May-13ProponedM&EDesignDelay21CoolingcapacityfortenantsconfirmationUpdatedDetaileddesignGallery2013/3/1-2013/3/20125-Jan-13Finishedonthe25thMarch2013MEPConstructiondrawingdesign22Landscape/Sign/LogodesignconfirmationCurtainwallDetaileddesignbaseontheSign/LogodesignconfirmationGallery2013/1/15-2013/3/20130-Apr-13
impacttheprogressofBMdesign23TenantssetbacktoCurtainwallinsidespacetoensuretheimageofentirefacadeGallery2013/7/201-2013/731431-Aug-13
24TenantsmoveinconditionsandscheduleNeedcommonunderstandingforthetenantsmoveinbeforeFFinspectionandtheconstructioncompletiondateGalleryTechnicalConstruction2013/5/15-2013/6/10120-Jun-13Itisnotsameunderstandingwithconstructiondepartmentimpactentireprojecttargetscheduleandsiteconstructionorganization.Tobeconfirmed4/4ItemDescriptionsActionPlanresponsiblePartySchedulepriorityDeadlineRemarkImpact25Tenantsdesignandconstructionmanagementplan&protocolfurtherclarificationneedfromthemanagementtoplanworkingscheduleGalleryTechnicalConstructionUMAN2013/5/15-2013/6/20225-Jun-13
26RequestofB1commercialUpdatedDetaileddesignGallery
TechnicalASAP120-Apr-13
27TheBridgeconnectionwithSanbao
ExpansionGallery
Technical2013/4/15-2013/5/1511-Jun-13pending
28FreshairandventilationofKitchenUpdatedDetaileddesignGallery2013/5/17-2013/5/31130-May-1329locationofthewastewaterofeachtenantUpdatedDetaileddesignGallery2013/5/17-2013/5/31130-May-13
30Gasvolume/locatio
温馨提示
- 1. 本站所有资源如无特殊说明,都需要本地电脑安装OFFICE2007和PDF阅读器。图纸软件为CAD,CAXA,PROE,UG,SolidWorks等.压缩文件请下载最新的WinRAR软件解压。
- 2. 本站的文档不包含任何第三方提供的附件图纸等,如果需要附件,请联系上传者。文件的所有权益归上传用户所有。
- 3. 本站RAR压缩包中若带图纸,网页内容里面会有图纸预览,若没有图纸预览就没有图纸。
- 4. 未经权益所有人同意不得将文件中的内容挪作商业或盈利用途。
- 5. 人人文库网仅提供信息存储空间,仅对用户上传内容的表现方式做保护处理,对用户上传分享的文档内容本身不做任何修改或编辑,并不能对任何下载内容负责。
- 6. 下载文件中如有侵权或不适当内容,请与我们联系,我们立即纠正。
- 7. 本站不保证下载资源的准确性、安全性和完整性, 同时也不承担用户因使用这些下载资源对自己和他人造成任何形式的伤害或损失。
最新文档
- 本溪市桓仁满族自治县2025-2026学年第二学期六年级语文第五单元测试卷部编版含答案
- 晋中市介休市2025-2026学年第二学期六年级语文第五单元测试卷部编版含答案
- 潍坊市安丘市2025-2026学年第二学期五年级语文第六单元测试卷(部编版含答案)
- 眉山地区仁寿县2025-2026学年第二学期六年级语文第五单元测试卷部编版含答案
- 锡林郭勒盟正蓝旗2025-2026学年第二学期六年级语文第五单元测试卷部编版含答案
- 包头市东河区2025-2026学年第二学期六年级语文第五单元测试卷部编版含答案
- 电器策划方案
- 深度解析(2026)《CBT 4386-2015集装箱绑扎杆存放架》
- 深度解析(2026)《CBT 3557-1995船用防火风闸》
- 深度解析(2026)《CB 3785-2013船舶修造企业高处作业安全规程》
- 高速路养护施工安全培训课件
- 2025年工业CT在军事弹药失效分析报告
- 2026年浙江单招酒店管理专业面试经典题含答案含应急处理题
- SJG 171-2024建筑工程消耗量标准
- 新疆维吾尔自治区小学五年级下学期数学第二单元测试卷-因数和倍数单元检测
- 专升本康复治疗2025年物理治疗学测试试卷(含答案)
- 2025年教职人员个人总结
- 钉钉OA管理系统
- 17918-2025港口散粮装卸系统粉尘防爆安全规范
- 2025高二英语阅读理解专项训练120篇
- 2026年版全国助理社会工作师《社会工作实务》考试题含答案(培优a卷)
评论
0/150
提交评论