第四节网络计划优化
Section4:NetworkPlanOptimization案例:Case:
巳知某工程双代号网络计划如图4.34所示,图中箭线下方括号外数字为工作的正常时间,括号内数字为最短持续时间;箭线上方号外数字工作按正常持续时间完成时所需的直接费;括号内数字为工作按最短持续时间完成时所需的直接费。该工程的间接费用率为0.8万元/d,试对其进行费用优化。Theactivity-on-arrownetworkplanofacertainprojectisshowninFigure4.34.Thenumbersoutsidethebracketsbelowthearrowsrepresentthenormaldurationofthetasks,andthenumbersinsidethebracketsrepresenttheshortestduration.Thenumbersabovethearrowsrepresentthedirectcostwhenthetaskiscompletedinthenormalduration,andthenumbersinthebracketsrepresentthedirectcostwhenthetaskiscompletedintheshortestduration.TheindirectcostrateforthisprojectisRMB8,000perday.Thetaskistooptimizethecost.(解):该网络计划的费用优化可按以下步骤进行:
①根据各项工作的正常持续时间,用标号法确定网络计划的计算工期和关键线路,如图4.35所示。计算工期为19d,关键线路有两条:①③④⑥和①③④⑤⑥(Solution):Thecostoptimizationofthisnetworkplancanbecarriedoutinthefollowingsteps:
①Basedonthenormaldurationofeachtask,usethenumberingmethodtodeterminethecalculationdurationandcriticalpathofthenetworkplan,asshowninFigure4.35.Thecalculatedprojectdurationis19days,andtherearetwocriticalpaths:①③④⑥and①③④⑤⑥.②计算各项工作的直接费用率:②Calculatethedirectcostrateforeachtask:③计算工程总费用:
a.直接费总和:Cd=7.0+90+57+55+8.0+80+5+7.5+65=62.2(万元),
b.间接费总和:Ci=0.8x19=15.2(万元),
c.工程总费用:Ct=Cd+Ci=62.2+15.2=77.4(万元)
④通过压缩关键工作的持续时间进行费用优化(优化过程见表4.3)③Calculatethetotalcostoftheproject:
a.Totaldirectcost:Cd=7.0+9.0+5.7+5.5+8.0+8.0+5.0+7.5+6.5=62.2(RMB10,000),
b.Totalindirectcost:Ci=0.8×19=15.2(RMB10,000),
c.Totalprojectcost:Ct=Cd+Ci=62.2+15.2=77.4(RMB10,000).
④Performcostoptimizationbyshorteningthedurationofcriticaltasks(optimizationprocessshowninTable4.3).A.第一次压缩。
由图4.35可知,该网络计划中有两条关键线路,为了同时缩短两条关键线路的总持续时间,有以下4个压缩方案:
a.压缩工作B,直接费用率为1.0万元/d,
b.压缩工作E,直接费用率为0.2万元/d:,
c.同时压缩工作H和工作l,组合直接费用率为0.7+0.5=l.2(万元/d),
d.同时压缩工作I和工作J,组合直接费用率为0.5+0.2=0.7(万元/d)
在上述压缩方案中,由于工作的直接费用率最小,故应选择工作E作为压缩对象。工作E的直接费用率0.2万元/,小于间接费用率0.8万元/d,说明压缩工作E可使工程总费用降低。将工作E的持续时间压缩至最短持续时间3天,利用标号法重新确定计算工期和关键线路,如图4.36所示A.Firstshortening.
AsseeninFigure4.35,thenetworkplanhastwocriticalpaths.Tosimultaneouslyshortenthetotaldurationofbothcriticalpaths,therearethefollowingfourshorteningoptions:
a.ShorteningthedurationoftaskB,directcostrateisRMB10,000perday,
b.ShorteningthedurationoftaskE,directcostrateisRMB2,000perday,
c.SimultaneouslyshorteningthedurationoftasksHandI,combineddirectcostrateis0.7+0.5=1.2(RMB10,000perday),d.
SimultaneouslyshorteningthedurationoftasksIandJ,combineddirectcostrateis0.5+0.2=0.7(RMB10,000perday).
Amongtheaboveshorteningoptions,sincethedirectcostrateisthesmallestfortaskE,itshouldbeselectedforshortening.ThedirectcostrateoftaskEisRMB2,000perday,whichislowerthantheindirectcostrateofRMB8,000perday,indicatingthatshorteningthedurationoftaskEcanreducethetotalprojectcost.ReducethedurationoftaskEtoitsminimumof3days,andusethelabelingmethodtorecalculatetheconstructionperiodandcriticalpath,asshowninFig.4.36.图4.36Fig.4.36此时,关键工作E被压缩成非关键工作,故将其持续时间延长为4d,使成为关键工作。
第一次压缩后的网络计划如图4.37所示。图中箭线上方括号内数字为工作的直接费用率。Aftertheshortening,criticaltaskEbecomesanon-criticaltask,soitsdurationisextendedto4daystomakeitacriticaltask.
ThenetworkplanafterthefirstshorteningisshowninFig.4.37.Thenumbersinthebracketsabovethearrowsinthefigurerepresentthedirectcostrateofthetasks.B.第二次压缩。由图4.37可知,该络计划中有3条关键线路,即①③④⑥和①③④⑤⑥及①③⑤⑥。
为了同时缩短3条关键线路的总持续时间,有以下5个压缩方案:B.Secondshortening.AsseeninFigure4.37,therearethreecriticalpathsinthisnetworkplan:①③④⑥,①③④⑤⑥,and①③⑤⑥.
Thereare5schemesavailableforsimultaneouslyshorteningthetotaldurationofthethreecriticalpaths:
a.压缩工作B,直接费用率为1.0万元/d,
b.同时压缩工作E和工作G,组合直接费用率为:0.2+0.8=1.0(万元/d):
c.同时压缩工作E和工作J,组合直接费用率为:0.2+0.2=0.4(万元/d):
d.同时压缩工作G、工作H和工作I,组合直接费用率为:08.+0.7+0.5=2.0(万元/d),
e.同时压缩工作I和工作J,组合直接费用率为0.5+0.2=0.7(万元0)
在上述压缩方案中,由于工作E和工作J的组合直接费用率最小,故应选择工作E和工作J作为压缩对象。工作E和工作J的组合直接费用率0.4万元/d,小于间接费用率0.8万元/d,说明同时压缩工作E和工作J可使工程总费用降低。a.ShorteningthedurationoftaskB,directcostrateisRMB10,000perday,
b.SimultaneouslyshorteningthedurationoftasksEandG,combineddirectcostrateis0.2+0.8=1.0(RMB10,000perday),
c.SimultaneouslyshorteningthedurationoftasksEandJ,combineddirectcostrateis0.2+0.2=0.4(RMB10,000perday),
d.SimultaneouslyshorteningthedurationoftasksG,H,andI,combineddirectcostrateis0.8+0.7+0.5=2.0(RMB10,000perday),
e.SimultaneouslyshorteningthedurationoftasksIandJ,combineddirectcostrateis0.5+0.2=0.7(RMB10,000perday).
Amongtheseshorteningoptions,sincethecombineddirectcostrateoftasksEandJisthelowest,theyshouldbeselectedforshortening.ThecombineddirectcostrateoftasksEandJisRMB4,000perday,whichislowerthantheindirectcostrateofRMB8,000perday,indicatingthatsimultaneouslyshorteningthedurationoftasksEandJcanreducethetotalprojectcost.由于工作E的持续时间只能压缩1d,工作J的持续时间也只能随之压缩1d。工作E和工作J的持续时间同时压缩1d后,利用标号法重新确定计算工期和关键线路。此时,关键线路由压缩前的3条变为2条,即①③④⑥和①③⑤⑥。原来的关键工作H未经压缩而被动地变成了非关键工作。第二次压缩后的网络计划如图4.38所示。此时,关键工作E的持续时间已达最短,不能再压缩,故其直接费用率变为无穷大。SincethedurationoftaskEcanonlybeshortenedby1day,thedurationoftaskJmustalsobeshortenedby1dayaccordingly.AftersimultaneouslyshorteningthedurationoftasksEandJby1day,usethelabelingmethodtorecalculatetheconstructionperiodandcriticalpath.Thethreecriticalpathsbeforeshorteningarereducedtotwo,①③④⑥and①③⑤⑥.ThepreviouslycriticaltaskH,whosedurationisnotshortened,passivelyturnedintoanon-criticaltask.ThenetworkplanafterthesecondshorteningisshowninFig.4.38.Atthispoint,thedurationofcriticaltaskEhasalsoreachedtheminimumandcan'tbefurthershortened,sothedirectcostrateoftaskJbecomesinfinite.C.第三次压缩。由图4.38可知,由于工作E不能再压缩,而为了同时缩短两条关键线路①③④⑥和①③⑤⑥的总持续时间,只有以下3个压缩方案:
a.压缩工作B,直接费用率为1.0万元/d,
b.同时压缩工作G和工作I组合直接费用率为:0.8+0.5=1.3(万元d)
C.同时压缩工作I和工作J,组合直接费率为:0.5+0.2=0.7(万元/d)C.Thirdshortening.AsseeninFigure4.38,sincetaskEcannotbefurthershortened,andinordertosimultaneouslyshortenthetotaldurationoftwocriticalpaths,①③④⑥and①③⑤⑥,thereareonlythefollowingthreeshorteningoptions:
a.ShorteningthedurationoftaskB,directcostrateisRMB10,000perday,
b.SimultaneouslyshorteningthedurationoftasksGandI,combineddirectcostrateis0.8+0.5=1.3(RMB10,000perday),
c.SimultaneouslyshorteningthedurationoftasksIandJ,combineddirectcostrateis0.5+0.2=0.7(RMB10,000perday).上述压缩方案中,由于工作I和工作J的组合直接费用率最小,故应选择工作I和工作J作为压缩对象。工作I和工作J的组合直接费用率0.7万元/d,小于间接费用率0.8万元/d,说明同时压缩工作I和工作J可使工程总费用降低。由于工作J的持续时间只能压缩1d,工作I的持续时间也只能随之压缩1d。工作I和工作J的持续时间同时压缩1d后,利用标号法重新确定计算工期和关键线路。此时,关键线路仍然为两条,即①③④⑥和①③⑤⑥。Amongthecompressionschemesabove,sinceactivityIandactivityJhasthelowestcombineddirectcostrate,activityIandactivityJshouldbeselectedasthecompressiontargets.Thecombineddirectcostrateof0.7(10,000yuan/d)foractivitiesIandJislowerthantheindirectcostrateof0.8(10,000yuan/d),indicatingthatcompressingbothactivitiescanlowertotalprojectcost.AsthedurationofactivityJcanonlybecompressedby1day,thedurationofactivityImustcorrespondinglybecompressedby1day.Aftercompressingbothactivities'durationsby1day,thelabelingmethodisappliedtoredeterminethecalculatedconstructionperiodandthecriticalpath.Atthispoint,therearestilltwocriticalpaths,namely①③④⑥and①③⑤⑥.第三次压缩后的网络计划如图4.39所示。此时,关键工作J的持续时间也已达最短,不能再压缩,故其直接费用率变为无穷大。ThenetworkplanafterthethirdshorteningisshowninFig.4.39.Atthispoint,thedurationofcriticaltaskJhasalsoreachedtheminimumandcan'tbefurthershortened,sothedirectcostrateoftaskJbecomesinfinite.D.第四次压缩。从图4.39可知,由于工作E和工作J不能再压缩,而为了同时缩短两条关键线路①③④⑥和①③⑤⑥的总持续时间,只有以下2个压缩方案:
a.压缩工作B,直接费用率为1.0万元/d,
b.同时压缩工作G和工作l,组合直接费用率为:0.8+0.5=1.3(万元/d)D.Fourthshortening.AsseeninFigure4.39,sincetasksEandJcannotbefurthershortened,andinordertosimultaneouslyshortenthetotaldurationoftwocriticalpaths,①③④⑥and①③⑤⑥,thereareonlythefollowingtwoshorteningoptions:
a.ShorteningthedurationoftaskB,directcostrateisRMB10,000perday,
b.SimultaneouslyshorteningthedurationoftasksGandI,combineddirectcostrateis0.8+0.5=1.3(RMB10,000perday).
在上述压缩方案中,由于工作B的直接费用率最小,故应选择工作B作为压缩对象。但是,由于工作B的直接费用率1.0万元/d,大于间接费用率0.8万元/d,说明压缩工作B会使工程总费用增加。因此,不需要压缩工作B,优化方案已得到,优化后的网络计划如图4.40所示。图中箭线上方括号内数字为工作的直接费。
Amongtheaboveshorteningplans,sincetaskBhasthelowestdirectcostrate,itshouldbeselectedforshortening.HoweverHowever,thedirectcostratefortaskBisRMB10,000perday,whichismorethantheindirectcostrateofRMB8,000perday.Therefore,shorteningthedurationoftaskBwillincreasethetotalprojectcosts.Therefore,itisunnecessarytoshortenthedurationoftaskB,andtheoptimizedplanhasbeenobtained.TheoptimizednetworkplanisshowninFig.4.40.Thenumbersinbracketsabovethearrowsinthefigurerepresent
温馨提示
- 1. 本站所有资源如无特殊说明,都需要本地电脑安装OFFICE2007和PDF阅读器。图纸软件为CAD,CAXA,PROE,UG,SolidWorks等.压缩文件请下载最新的WinRAR软件解压。
- 2. 本站的文档不包含任何第三方提供的附件图纸等,如果需要附件,请联系上传者。文件的所有权益归上传用户所有。
- 3. 本站RAR压缩包中若带图纸,网页内容里面会有图纸预览,若没有图纸预览就没有图纸。
- 4. 未经权益所有人同意不得将文件中的内容挪作商业或盈利用途。
- 5. 人人文库网仅提供信息存储空间,仅对用户上传内容的表现方式做保护处理,对用户上传分享的文档内容本身不做任何修改或编辑,并不能对任何下载内容负责。
- 6. 下载文件中如有侵权或不适当内容,请与我们联系,我们立即纠正。
- 7. 本站不保证下载资源的准确性、安全性和完整性, 同时也不承担用户因使用这些下载资源对自己和他人造成任何形式的伤害或损失。
最新文档
- 2026年矿山装载机安全培训内容重点
- 2026年强化调度安全培训内容核心要点
- 女工安全技能培训内容2026年一次通关
- 2026年工程安全作业培训内容实战手册
- 安康地区岚皋县2025-2026学年第二学期六年级语文第五单元测试卷部编版含答案
- 宿州市墉桥区2025-2026学年第二学期六年级语文第五单元测试卷部编版含答案
- 安庆市望江县2025-2026学年第二学期六年级语文第五单元测试卷部编版含答案
- 2026年教育行业数据应用合同协议
- 2026年租房合同协议书网站核心要点
- 荆门市钟祥市2025-2026学年第二学期四年级语文期中考试卷(部编版含答案)
- 山西省吕梁市2025-2026学年高三第二次模拟调研测试生物+答案
- 2026山东青岛海上综合试验场有限公司招聘38人备考题库含完整答案详解(全优)
- 大型赛事活动安保服务方案投标文件(技术标)
- 2026年上半年中小学教师资格考试教育知识与能力(中学)真题附答案解析
- 施工工地员工考核管理制度(3篇)
- 医院耗材监督考核制度
- 2025特变电工校园招聘200人笔试历年常考点试题专练附带答案详解2套试卷
- 2026年山东潍坊市高三一模高考生物模拟试卷(含答案详解)
- 玉林介绍教学课件
- 中建塔式起重机拆卸专项施工方案
- 2026年东莞市厚街控股集团有限公司招聘14名工作人员备考题库含答案详解
评论
0/150
提交评论