1、Earned Value Management Tutorial Module 8: Reporting,Prepared by:,Module 8 Reporting,Module 8: Government Required Reports,Welcome to Module 8. The objective of this module is to introduce you to Government required reports. The Topics that will be addressed in this Module include: Define Cost Perfo
2、rmance Report (CPR) Define Cost/Schedule Status Report (C/SSR),Module 8 Reporting,Review of Previous Modules,In the previous seven modules, we discussed the framework needed to perform Earned Value and develop an Earned Value Management System (EVMS). In Module 1 we introduced you to earned value an
3、d the requirements for properly implementing an earned value management system (EVMS) In Module 2 we discussed the development of the work breakdown structure (WBS), organizational breakdown structure (OBS) and the integration of WBS and OBS in creating the responsibility assignment matrix (RAM) In
4、Module 3 we discussed the development of the project schedule and the schedule baseline In Module 4 we discussed the development of the project budget and the cost baseline,Module 8 Reporting,Review of Previous Modules,In Module 5 we discussed EVMS criteria and the three key components to earned val
5、ue: Planned Value (PV) , Earned Value (EV) and Actual Cost (AC). In Module 6 we discussed Earned value metrics and performance measurements (CV, SV, SPI, CPI,etc.) In Module 7 we discussed the Integrated Baseline Review (IBR), rebaselining of a project and proper baseline control or change control N
6、ow lets look at the Government reporting requirements for earned value.,Module 8 Reporting,Government Reporting Requirements,There are several reports which may be used for Earned Value Management Reporting and Analysis. The most commonly used reports are: Cost Performance Report (CPR) Cost/Schedule
7、 Status Report (C/SSR) Lets take a look at each type of report on the next page.,Module 8 Reporting,Cost Performance Report (CPR),The Cost Performance Report (CPR) is the most comprehensive of the EVMS reports. It is normally a monthly report and has five different formats. Format 1 Work Breakdown S
8、tructure (WBS) Format 2 Organizational Categories (OBS) Format 3 Baseline Format 4 Staffing (Manpower) Format 5 Variance Analysis Report Generally, all five formats are applied to a contract requiring EVMS. However, the customer may not require all the reports and may delete one or more. Most custom
9、ers will require at least the CPR Format 1 (WBS) and Format 5 (Variance Analysis Report).,Module 8 Reporting,Cost Performance Report (CPR),All Performance Measurement data reported in the CPR are derived from the formal Earned Value Management System (EVMS). All reported changes to the project basel
10、ine, management reserve (MR) and contingency should be traceable through the formal Earned Value Management System (EVMS) and CPR reports. On the following pages, we will look at examples of the five CPR reports using the ACME House Building Project.,Module 8 Reporting,Cost Performance Report (CPR)
11、- Example,Project Start date: January 15th Status Date: January 31th EAC calculations used for the example will be based on the assumptions discussed on Page 35 and 36 of Module 6. See the charts to the right for an overview. Now lets take a look at the Cost Performance Reports (CPR) on the next pag
12、e.,First lets quickly review the projects current status that will be used in the example reports. ACME Home Building Project,Module 8 Reporting,Cost Performance Report (CPR) Format 1 - WBS,The Cost Performance Report (CPR) Format 1 includes current period, cumulative, and at complete values for eac
13、h WBS element. It also contains header data showing quantity, targets, ceilings, and Management Estimate At Completion (MEAC) calculations. This report also contains data about budget, price, Management Reserve (MR), Undistributed Budget (UB), and MEAC cases. A copy of the CPR Format 1 for the ACME
14、Home Building project is on the following page. Please review the entire report but pay close attention to the lower section (highlighted red) of the report. This is the Performance data section that contains the current and cumulative cost and schedule information for the project.,Module 8 Reportin
15、g,Cost Performance Report (CPR) Format 1 - WBS,Module 8 Reporting,Cost Performance Report (CPR) Format 2 Organizational Categories,The Cost Performance Report (CPR) Format 2 includes current period, cumulative, and at complete values for each Organization (Performing or Responsible), It also contain
16、s header data showing quantity, targets, ceilings, and MEAC cases. This report also contains data about budget, price, Management Reserve (MR), Undistributed Budget (UB), and MEAC cases. The reporting details in CPR Format 2 are the same as on the CPR Format 1 accept that it is structured by organiz
17、ation. A copy of the CPR Format 2 for the ACME Home Building project is on following page. Please review the entire report but pay close attention to the lower section (highlighted red) of the report. This is the Performance data section that contains the current and cumulative cost and schedule inf
18、ormation for the project.,Module 8 Reporting,Cost Performance Report (CPR) Format 2 Organizational Categories,Module 8 Reporting,Cost Performance Report (CPR) Format 3 Baseline,Cost Performance Report (CPR) Format 3 displays a forecast of monthly changes to the Baseline, Management Reserve, and Undi
19、stributed Budget for the entire project, and contains header data showing schedule dates for the contract and the project.,Module 8 Reporting,Cost Performance Report (CPR) Format 4 Staffing,The Cost Performance Report (CPR) Format 4 displays a forecast of hours and person-months by Organization (Per
20、forming/Responsible), and contains header data showing schedule dates for the contract and the project. This report also contains program variance thresholds for month, cumulative, and at-complete percents and values.,Module 8 Reporting,Cost Performance Report (CPR) Format 5 Variance Analyses Report
21、,The Cost Performance Report (CPR) Format 5 provides narrative explanation of cost, schedule, and other problems related to total contract, undistributed budget (UB), management reserve (MR), PMB, and manpower. The variance reporting thresholds are pre-determined prior to the start of the program. E
22、xplanations and problem analysis reporting is only required for those variances that breech the pre-set threshold(s). The report will indicate those variances needing explanation. A copy of the Variance Analyses Report is on the following page. The variance report uses the ACME Home Building project
23、 information.,Module 8 Reporting,Cost Performance Report (CPR) Format 5 Variance Analyses Report,Header information includes quantified cost and schedule variances and indicates out of tolerance items. Explanations may be required for monthly, cumulative, and at complete variances.,Problem Analysis:
24、 This section is used to explain the variance drivers, abnormal conditions and factors creating variances, and other issues, problems, and concerns.,Task/Project Impact: This section is used to explain the impact to the Control Account and overall Project.,Corrective Action Plan: This section provid
25、es the recovery and risk mitigation plan.,Module 8 Reporting,Cost/Schedule Summary Report (C/SSR),The final standard EVMS report we will review is the Cost/Schedule Summary Report (C/SSR). The C/SSR (Cost/Schedule Summary Report) is used primarily for reporting cost and schedule summary data to the
26、government or contractors on specific procurements. This report includes cumulative and at complete summaries for each WBS element, and contains header data showing contractor and contract information, and MEAC calculations. This report also contains data about contract price, budget, Management Res
27、erve (MR), Undistributed Budget (UB), and MEAC cases. It is very similar to the CPR Format 1 except that the C/SSR has only cumulative information. A copy of the C/SSR for the ACME Home Building project in on the following page.,Module 8 Reporting,Cost/Schedule Summary Report (C/SSR),Module 8 Reporting,Review Module 8,At this point, you have covered all of the content in Module 8. Ta
温馨提示
- 1. 本站所有资源如无特殊说明,都需要本地电脑安装OFFICE2007和PDF阅读器。图纸软件为CAD,CAXA,PROE,UG,SolidWorks等.压缩文件请下载最新的WinRAR软件解压。
- 2. 本站的文档不包含任何第三方提供的附件图纸等,如果需要附件,请联系上传者。文件的所有权益归上传用户所有。
- 3. 本站RAR压缩包中若带图纸,网页内容里面会有图纸预览,若没有图纸预览就没有图纸。
- 4. 未经权益所有人同意不得将文件中的内容挪作商业或盈利用途。
- 5. 人人文库网仅提供信息存储空间,仅对用户上传内容的表现方式做保护处理,对用户上传分享的文档内容本身不做任何修改或编辑,并不能对任何下载内容负责。
- 6. 下载文件中如有侵权或不适当内容,请与我们联系,我们立即纠正。
- 7. 本站不保证下载资源的准确性、安全性和完整性, 同时也不承担用户因使用这些下载资源对自己和他人造成任何形式的伤害或损失。
最新文档
- 2025梧州医学高等专科学校教师招聘考试题目及答案
- 2025江西制造职业技术学院教师招聘考试题目及答案
- 2025承德医学院教师招聘考试题目及答案
- 临安区事业编试题及答案
- 2026天津市消防救援总队水上支队招录政府专职消防员95人建设笔试参考题库及答案解析
- 2026年甘肃省嘉峪关市农业农村局招聘公益性岗位人员建设笔试备考题库及答案解析
- 2026安徽黄山市黟县桃花源人才服务有限公司招聘劳务派遣工作人员1人建设笔试备考试题及答案解析
- 2026年安庆安徽省岳顺人力资源服务有限公司公开招聘8名建设考试参考题库及答案解析
- 2026新疆慧之源图书发行有限公司招聘5人建设考试备考题库及答案解析
- 2026江苏南京大学档案馆、校史博物馆内勤招聘建设笔试参考题库及答案解析
- 物控工作培训
- DBJ41T 189-2017 地下连续墙检测技术规程
- 小学语文命题能力培训
- 外墙保温板(匀质板)施工方案
- 前列腺癌治疗现状
- 24年10月自考13003数据结构与算法试题及答案
- 《人工智能技术基础》课件 第5章 注意力机制
- 保安公司组织架构岗位制度及保安管理制度
- NWT系列扫频仪说明书-中英文版
- 感觉统合教育指导师理论考试复习题库(含答案)
- 断亲协议书模板
评论
0/150
提交评论